Buas Sands Hotel, LLC v. Liberty Mutual Insurance Company

CourtDistrict Court, D. Maryland
DecidedSeptember 22, 2021
Docket1:21-cv-01214
StatusUnknown

This text of Buas Sands Hotel, LLC v. Liberty Mutual Insurance Company (Buas Sands Hotel, LLC v. Liberty Mutual Insurance Company) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Buas Sands Hotel, LLC v. Liberty Mutual Insurance Company, (D. Md. 2021).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF MARYLAND

BUAS SANDS HOTEL, LLC Plaintiff,

v. Civil Action No. ELH-21-1214 LIBERTY MUTUAL INSURANCE COMPANY, Defendant.

MEMORANDUM This case arises from the construction of the Fenwick Sands Tapestry Hotel in Fenwick, Delaware (the “Hotel”). In April 2019, plaintiff Buas Sands Hotel, LLC (“Sands”), the owner and developer of the Hotel, entered into a construction contract (the “Contract”) with Harkins Contracting, Inc. (“Harkins”), a general contractor, to construct the Hotel. Under the contract, Harkins was required to obtain both a Performance Bond and a Payment Bond (the “Bonds”) to assure its performance. Defendant Liberty Mutual Insurance Company (“Liberty”), as surety, issued the Bonds. Sands has filed suit against Liberty, claiming that Harkins breached its contract with plaintiff, and therefore plaintiff is entitled to recover in accordance with the Bonds. ECF 1 (the “Complaint”).1 But, according to Sands, Liberty has refused to comply. Id. Copies of the Bonds

1 Plaintiff invokes this Court’s diversity jurisdiction, pursuant to 28 U.S.C. § 1332(a)(1). ECF 1, ⁋ 3. Plaintiff is a limited liability company comprised of two members, the “Spiro Buas Irrevocable Family Trust” and the “Spiro and Maryanne Buas Joint Rvocable [sic] Trust,” both of which, plaintiff claims, are citizens of Maryland. ECF 11 at 2; see ECF 1, ⁋ 1. Defendant is a Massachusetts corporation with its principal place of business in Boston, Massachusetts. ECF 1, ⁋ 2; ECF 7 at 1. And, the Complaint seeks to recover nearly $1 million from defendant. ECF 1 at 4-6. Accordingly, I am satisfied that subject matter jurisdiction exists in this case. are appended to the Complaint as exhibits. See ECF 1-1 (the “Performance Bond”); ECF 1-2 (the “Payment Bond”). Plaintiff seeks damages in the amount of $950,000, “together with interest, costs and attorneys’ fees.” ECF 1 at 5-6. Defendant has moved to stay these proceedings pending the outcome of arbitration between Harkins and Sands. ECF 8. The motion is accompanied by a memorandum (ECF 8-1)

(collectively, the “Motion”) and supported by five exhibits: a copy of the Contract (ECF 8-2); a copy of the “General Conditions of the Contract” (ECF 8-3); Harkin’s demand for arbitration, filed with the American Arbitration Association (“AAA”) (ECF 8-4, the “Demand”); Sands’s counterclaim in that proceeding (ECF 8-5); and a copy of an AAA Notice of Hearing (ECF 8-6). Plaintiff opposes the Motion. ECF 10 (the “Opposition”). Defendant has not replied, and the time to do so has expired. See Local Rule 105.2(a). No hearing is necessary to resolve the Motion. See Local Rule 105.6. For the reasons discussed below, I shall grant the Motion. I. Factual Background

On or about April 18, 2019, Sands entered into the Contract with Harkins for construction of the Hotel, in exchange for payment in the amount of $8,575,000.00. ECF 1, ⁋ 4; see ECF 8-2. The Contract specifies that Harkins was required to have “substantially completed” its work, as defined by the Contract, within one year of its start date, plus “any additional days added due to change orders and/or weather delays,” i.e., by April 28, 2020. ECF 1¸ ⁋⁋ 5-6; see ECF 8-2 at 3, §§ 3.3.1, 3.3.2.1. Further, the Contract requires Harkins to pay “liquidated damages in the amount of $2,500.00 per day for each day” beyond this deadline where “substantial completion had not been achieved.” ECF 1, ⁋ 6; see ECF 8-2 at 3, ⁋ 3.3.2.1. Article 6 of the Contract requires that “all disputes between [Harkins and Sands] would be decided by the project Architect, subject to the later right of either party to demand arbitration of contested issues.” ECF 1, ⁋ 6; see ECF 8-2 at 7-8, §§ 6.1-6.2; ECF 8-3 at 40, §§ 15.4.1-15.4.4. Moreover, the Contract provides: “The award rendered by the arbitrator . . . shall be final, and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction

thereof.” ECF 8-3 at 40, § 15.4.2. Under the Contract, Harkins was required to post bonds guaranteeing its performance and payment to subcontractors. ECF 1, ⁋ 4; ECF 8-1 at 2; see also ECF 8-3 at 32¸ § 11.1.2. According to Liberty, Harkins “obtained payment and performance bonds from Liberty for the Project.” ECF 8-1 at 2. About one month after the Contract’s execution, Liberty issued the Bonds, “each in the prime contract amount . . . .” ECF 1, ⁋ 4; see ECF 1-1; ECF 1-2. The Performance Bond specifies, in relevant part, that in the event Harkins fails to perform according to the Contract terms, Sands has the right to declare a “Contractor Default,” provided that it first gives notice to Harkins and Liberty of its intent to do so. ECF 1-1, § 3.1; see also ECF

1, ⁋ 10. Upon receiving such notice, Liberty is thereafter obligated either to “[a]rrange for the Contractor, with the consent of the Owner, to perform and complete the Construction Contract,” “[u]ndertake to perform and complete the Construction Contract itself, through its agents or independent contractors,” or “[o]btain bids or negotiated proposals from qualified contractors . . . for performance and completion of the Construction Contract . . . and pay to the Owner the amount of damages . . . in excess of the Balance of the Contract Price incurred by the Owner as a result of the Contractor Default.” ECF 1-1, §§ 5.1-5.3. Under the Payment Bond, Liberty is required to indemnify Sands from all claims by subcontractors. ECF 1, ⁋⁋ 21, 22. The Payment Bond provides that, if Sands notifies Liberty and Harkins of any “claims, demands, liens or suits against the Owner or the Owner’s property by any person or entity seeking payment for labor, materials, or equipment” arising under the Contract, Liberty is required to “indemnify and hold harmless the Owner against a duly tendered claim, demand, lien, or suit.” ECF 1-2, §§ 3-4. According to plaintiff, Harkins failed to complete its work by the deadline of April 28,

2020. See ECF 1, ⁋⁋ 7-8; ECF 8-1 at 3. In July 2020, Sands “approved and certified the amount of $202,500.00 as liquidated damages assessed against Harkins for delay,” up to that date. ECF 1, ⁋ 7. Moreover, according to Sands, Harkins “stopped paying subcontractors in full and issued partial payments to some,” which “resulted in most of those tradesmen refusing to complete their work.” Id. ⁋⁋ 7, 9. In addition, plaintiff alleges that Harkins and its subcontractors withheld “access codes and passwords to critical systems, such as the HVAC.” Id. ⁋ 9. Further, Sands claims that Substantial Completion occurred on September 22, 2020. Id. ⁋ 8. However, plaintiff contends that, after the issuance of a Certificate of Occupancy, Harkins

“essentially abandoned the project.” Id. Sands notified Liberty and Harkins of its intent to declare a Contractor Default and, subsequently, terminated the Contract. Id. ⁋ 10. In plaintiff’s view, the timely provision of this notice triggered Liberty’s obligation to perform under the terms of the Bonds. Id. ⁋⁋ 17, 23. In the Motion, defendant indicates that, according to Harkins, Sands breached the Contract by improperly withholding payments owed to Harkins. ECF 8-1 at 3. To that end, in January 2021 Harkins filed a “Demand for Arbitration with the American Arbitration Association seeking payment” of the contested funds. ECF 8-1 at 4; see ECF 8-4. 2 In the Demand, Harkins asserts that Sands’s claim for liquidated damages was contrary to “an oral agreement between the parties that liquidated damages would not be charged due to delays caused by the owner.” ECF 8-4, ⁋ 7. According to Liberty, on February 11, 2021, Sands filed a counterclaim against Harkins in the arbitration proceeding for damages in the same amount as it seeks to recover from Liberty in this

action. ECF 8-1 at 4; see also ECF 8-5 at 1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Landis v. North American Co.
299 U.S. 248 (Supreme Court, 1936)
Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
Klaxon Co. v. Stentor Electric Manufacturing Co.
313 U.S. 487 (Supreme Court, 1941)
Colgan Air, Inc. v. Raytheon Aircraft Co.
507 F.3d 270 (Fourth Circuit, 2007)
Chirichella v. Erwin
310 A.2d 555 (Court of Appeals of Maryland, 1973)
Institute of Mission Helpers v. Reliance Insurance
812 F. Supp. 72 (D. Maryland, 1992)
Allstate Insurance v. Stinebaugh
824 A.2d 87 (Court of Appeals of Maryland, 2003)
Brendsel v. WINCHESTER CONSTRUCTION CO., INC.
898 A.2d 472 (Court of Appeals of Maryland, 2006)
Bel Pre Medical Center, Inc. v. Frederick Contractors, Inc.
320 A.2d 558 (Court of Special Appeals of Maryland, 1974)
Erie Insurance Exchange v. Heffernan
925 A.2d 636 (Court of Appeals of Maryland, 2007)
Commercial Union Insurance v. Porter Hayden Co.
698 A.2d 1167 (Court of Special Appeals of Maryland, 1997)
Atlantic Contracting & Material Co. v. Ulico Casualty Co.
844 A.2d 460 (Court of Appeals of Maryland, 2004)
All State Home Mortgage, Inc. v. Daniel
977 A.2d 438 (Court of Special Appeals of Maryland, 2009)
Ground Zero Museum Workshop v. Wilson
813 F. Supp. 2d 678 (D. Maryland, 2011)
Bowman v. Goad
703 A.2d 144 (Court of Appeals of Maryland, 1997)
Frederick Contractors, Inc. v. Bel Pre Medical Center, Inc.
334 A.2d 526 (Court of Appeals of Maryland, 1975)
Konover Property Trust, Inc. v. WHE Associates, Inc.
790 A.2d 720 (Court of Special Appeals of Maryland, 2002)
Redemptorists v. Coulthard Services, Inc.
801 A.2d 1104 (Court of Special Appeals of Maryland, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
Buas Sands Hotel, LLC v. Liberty Mutual Insurance Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/buas-sands-hotel-llc-v-liberty-mutual-insurance-company-mdd-2021.