Marsh v. Loffler Housing Corp.

648 A.2d 1081, 102 Md. App. 116, 1994 Md. App. LEXIS 150
CourtCourt of Special Appeals of Maryland
DecidedOctober 27, 1994
DocketNo. 186
StatusPublished
Cited by10 cases

This text of 648 A.2d 1081 (Marsh v. Loffler Housing Corp.) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Marsh v. Loffler Housing Corp., 648 A.2d 1081, 102 Md. App. 116, 1994 Md. App. LEXIS 150 (Md. Ct. App. 1994).

Opinion

HARRELL, Judge.

Appellants, H. Brandis and Jo Ann K. Marsh (Marshes), appeal from an Order of the Circuit Court for St. Mary’s County (Raley, J.) granting the motion of appellee, Loffler Housing Corporation (Loffler), to modify an arbitrator’s award in a contract dispute so as to include costs and attorneys’ fees.1 We have re-ordered appellants’ issues as follows:

Issues

I. Did the lower court have the authority to award Loffler attorneys’ fees where the Uniform Arbitration Act authorizes attorneys’ fees only if so provided in the arbitration agreement between the parties?
II. Did the lower court have authority to modify the arbitrator’s award to reallocate the costs of the arbitration and to include attorneys’ fees incurred by Loffler where none of the three enumerated bases set forth in the Uniform Arbitration Act for modification of an award by a court were satisfied by the facts of this case?

[120]*120 Facts

In September 1988, appellants purchased a three-story house on Knight Road, Leonardtown, Maryland in St. Mary’s County. Appellants decided to renovate and expand their house, and solicited bids from various contractors for the renovation. Appellants ultimately selected appellee to serve as general contractor on the project.

On 4 October 1989, appellants and appellee entered into an American Institute of Architects (AIA) standard construction contract (AIA Contract), with the attendant AIA General Conditions of the Contract for Construction (General Conditions). Article 16.1.7 of the AIA Contract, entitled “Other Documents, if any, forming part of the Contract Documents are as follows:”, provided:

It is agreed that the documents listed below and attached to this contract routinely used by Loffler Housing Corporation, shall be executed by the appropriate respective parties to this agreement and shall become part of this agreement. Where there are conflicts between this document and those listed below, this document shall supersede those listed below....

The first document listed and attached was the Home Improvement Contract, duly signed and executed by appellants at the same time as the AIA Contract. The Home Improvement Contract provided, in pertinent part, that:

In the event that payment under this contract is enforced through legal action, or other collection action, homeowner agrees to pay contractor’s costs and attorney’s fees related to said action.

Article 4.5 of the General Conditions set forth the agreement to arbitrate any dispute arising out of or relating to the AIA Contract. It stated:

Any controversy or claim arising out of or related to the contract, or the breach thereof, shall be settled by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association....

[121]*121Paragraph six of the Construction Industry Arbitration Rules (Rules) in effect at the time the contract was executed stated that the initiating party shall provide written notice setting forth the nature of the dispute to the other party. Paragraph eight explained that once a claim is filed, any new or different claims or counterclaims shall also be made in writing.

Once the contract was executed, appellee began construction on appellants’ home. Subsequently, a dispute developed regarding the final three payments remaining to be made by appellants to appellee pursuant to the AIA Contract. On 15 April 1992, appellee filed a mechanic’s lien petition in the circuit court against appellants’ property, seeking $3993.38, plus interest. In response, appellants, among other things, filed a petition for arbitration based on the arbitration clause in the General Conditions. On 22 May 1992, the circuit court stayed the mechanic’s lien action and ordered the parties to arbitrate their dispute.

In July 1992, appellants filed a written claim against appellee with the American Arbitration Association (AAA) alleging that appellee performed defective workmanship and requested improper and excessive charges for the work performed.2 Appellants requested $151,000 in damages. Appellee counterclaimed, seeking $50,000 for an unpaid balance, lost revenue, and items not previously billed. During twelve days of hearings, both sides presented substantive evidence regarding their written issues submitted to the arbitrator. Appellee also apparently offered documentation of its attorneys’ fees.3 Both sides were then granted leave to file post-hearing briefs.

[122]*122On 12 August 1993, the arbitrator awarded appellee $2791 and denied appellants’ claims in their entirety. Specifically, the award stated: 1) all subcontractor warranties would be honored; 2) the parties would split administrative fees and. expenses of the AAA as well as the compensation and expenses of the arbitrator; and 3) the award was in full settlement of all claims and counterclaims submitted by the parties. There was no mention of attorneys’ fees.

On 3 September 1993, appellants filed with the arbitrator a motion to clarify his award as to three issues: 1) what was included in “administrative fees and expenses;”4 2) which defective workmanship was to be covered by “warranties;” and 3) whether appellee was required to submit “as-built” plans as provided for in the AIA Contract. Appellee filed a response to the motion to clarify, generally opposing appellants’ motion, but also requesting that the award be clarified to order appellants to pay costs and expenses plus appellee’s attorneys’ fees. Citing Md.Code Ann., Cts. & Jud.Proc. § 3-221,5 appellee renewed its argument that because the clause in the Home Improvement Contract awarded costs and attorneys’ fees if appellee enforced payment via legal action or other collection action, the arbitrator should have included costs and attorneys’ fees in his award. On 5 October 1993, the arbitrator filed a clarified award generally reaffirming his award of 12 August 1993. Again, however, the award was silent as to attorneys’ fees.

[123]*123On 17 September 1993, while the motions to clarify were pending, appellants filed in the Circuit Court for St. Mary’s County a motion to vacate the arbitrator’s award, arguing that the award was “completely irrational when viewed against the twelve days of hearings and thousands of pages of documentation presented by the parties and the substantive contract provisions.” On 20 October 1993, appellee filed an opposition to the motion to vacate and a petition to correct or modify the award. Appellee’s motion to correct or modify the award argued, pursuant to Md.Code Ann., Cts. & Jud.Proc. § 3-223(b)(2) (1989 Replacement Volume & 1993 Supp.) and Bernard v. Kuhn, 65 Md.App. 557, 501 A.2d 480 (1985),6 that the circuit court must modify the arbitrator’s award to include appellee’s costs and attorneys’ fees. Appellants filed an opposition to appellee’s petition to correct or modify and a reply to appellee’s opposition to the petition to vacate the award. Appellants argued that none of the statutory bases set forth in § 3-223(b)(2) was met in this case, and that Bernard

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kumar v. Dhanda
17 A.3d 744 (Court of Special Appeals of Maryland, 2011)
Comprehensive Orthopaedics & Musculoskeletal Care, LLC v. Axtmayer
980 A.2d 297 (Supreme Court of Connecticut, 2009)
Parks v. Sombke
732 A.2d 907 (Court of Special Appeals of Maryland, 1999)
Casias v. Dairyland Insurance
1999 NMCA 046 (New Mexico Court of Appeals, 1999)
Blitz v. Beth Isaac Adas Israel Congregation
694 A.2d 107 (Court of Special Appeals of Maryland, 1997)
Society of American Foresters v. Renewable Natural Resources Foundation
689 A.2d 662 (Court of Special Appeals of Maryland, 1997)
Baltimore Gas & Electric Co. v. Commercial Union Insurance
688 A.2d 496 (Court of Special Appeals of Maryland, 1997)
Birkey Design Group, Inc. v. Egle Nursing Home, Inc.
687 A.2d 256 (Court of Special Appeals of Maryland, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
648 A.2d 1081, 102 Md. App. 116, 1994 Md. App. LEXIS 150, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marsh-v-loffler-housing-corp-mdctspecapp-1994.