Tyson v. Masten Lumber & Supply, Inc.

408 A.2d 1051, 44 Md. App. 293, 1979 Md. App. LEXIS 435
CourtCourt of Special Appeals of Maryland
DecidedDecember 6, 1979
Docket240, September Term, 1979
StatusPublished
Cited by14 cases

This text of 408 A.2d 1051 (Tyson v. Masten Lumber & Supply, Inc.) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tyson v. Masten Lumber & Supply, Inc., 408 A.2d 1051, 44 Md. App. 293, 1979 Md. App. LEXIS 435 (Md. Ct. App. 1979).

Opinion

Gilbert, C. J.,

delivered the opinion of the Court.

INTRODUCTION.

It is written that:

“Nothing in the world lasts Save eternal change.” ( 1 )

This appeal, arising under the Mechanic’s Lien Law is illustrative of the wisdom of those words.

The settled law of Maryland was jolted when the Supreme Court, in a series of cases, Sniadach, 2 Fuentes, 3 Mitchell, 4 and North Georgia Finishing, 5 tolled the death knell for this State’s former Mechanic’s Lien Law. Md. Real Prop. Code Ann. §§ 9-101 to 9-111 (1974). It was not until seven years after Sniadach, and one year after North Georgia Finishing, however, that the Court of Appeals, in Barry Properties v. Fick Bros., 277 Md. 15, 353 A.2d 222 (1976), presided over the interment on procedural due process grounds of the then Mechanic’s Lien Law.

In laying to rest a statute that traced its roots to 1838, 6 Judge Digges, writing for the majority 7 in Barry, said:

“We ... hold that under the current statute [then Md. Real Property Code Ann. §§ 9-101 to 9-111( 8 )] *295 there can be no existing lien on property until and unless the claimant prevails either in a suit to enforce the claimed lien or in some other appropriate proceeding providing notice and a hearing (i.e., a declaratory judgment action).” 277 Md. at 37, 353 A.2d at 235.

THE LAW.

The legislative reaction to Barry was to enact an emergency law, effective May 4,1976, eighty-three days after the Barry decision. 9 The new law was designed to avoid the procedural due process denial found in the former statute.

Prior to Barry, the statute permitted a lien to attach to a building and the land covered by it for material furnished or work done for or in or about the building. Mervin L. Blades and Son, Inc. v. Lighthouse, 37 Md. App. 265, 267, 377 A.2d 523, 525 (1977). The lien, which attached as soon as the work was done or the materials were furnished, took priority over other liens which attached subsequent to the start of the building, except other mechanics’ liens, provided an action was filed to enforce it within 180 days. The mechanics’ liens shared equality. Id. In order to preserve the lien past the 180 day period, it had to be filed in the appropriate circuit court within 180 days next following the performance of the work or the furnishing of the materials. Former section 9-105(e). If the laborer or material supplier was a subcontractor, that is, one who did not contract directly with the owner of the building, he was required to give notice to the owner within 90 days next following the performance of the work or delivery of the material of an intention to claim a lien. Former section 9-103(a); Barry v. Fick, 277 Md. at 19-20, 353 A.2d at 226; Recent Legislation, 6 U. of Balt. L. Rev. 181, 184 (1976).

The girth of the lien, as soon as the work was performed or the material supplied, immediately created a cloud on the *296 title of the property concerned for the owner. Id. 277 Md. at 23, 353 A.2d at 228. That cloud, the Court of Appeals decided, deprived the owner of a “ ‘significant property interest’ ... and thus, the limitations of due process” were held applicable. 277 Md. at 24, 353 A.2d at 228.

The former Maryland law allowed “an owner to be deprived of a significant property interest without notice or a prior hearing.” 277 Md. at 31, 353 A.2d at 232. The denial of notice or the prior hearing conflicted with the rationale of Sniadach, Fuentes, Mitchell, and North Georgia Finishing, supra.

The present law, as we have previously stated was enacted to cure the ills of the former statute. Under the current act a lien does not automatically attach to the owner’s building upon the performance of work or the supplying of materials. It is only when a building is “erected ... repaired, rebuilt or improved to the extent of 25 per cent of its value” 10 that a mechanic’s lien may be established.

A person claiming a lien must file a proceeding in the circuit court for the county where the land or any part of it lies, within 180 days after the completion of the work or the furnishing of the materials. * 11

When, however, the petitioner is a subcontractor, he is not entitled to a lien, unless “within 90 days after doing the work 0* furnishing the materials, he gives written notice of his intention to claim a lien____” Md. Real Prop. Code Ann. § 9-104(a) (1979). The new law requires that the notice be given in substantially the following form:

“Notice to Owner or Owner’s Agent of Intention to Claim a Lien

Subcontractor did work or furnished material for or about the building generally designated or briefly described as

The total amount earned under the subcontractor’s undertaking to the date hereof is $............ *297 of which .......is due and unpaid as of the date hereof. The work done or materials provided under the subcontract were as follows: (insert brief description of the work done and materials furnished, the time when the work was done or the materials furnished, and the name of the person for whom the work was done or to whom the materials were furnished).

I do solemnly declare and affirm under the penalties of perjury that the contents of the foregoing notice are true to the best of the affiant’s knowledge, information, and belief.

(Individual) on behalf of ............... (Subcontractor) (insert if subcontractor is not an individual)”

“The notice,” the statute provides, “is effective if given by registered or certified mail, return receipt requested, or [is] personally delivered to the owner by the claimant or his agent.” § 9-104(c). Notice to one of several owners is notice to all. § 9404(d).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Martino v. Arfaa
906 A.2d 945 (Court of Special Appeals of Maryland, 2006)
Brendsel v. Winchester Construction Co.
875 A.2d 789 (Court of Special Appeals of Maryland, 2005)
Howard Chertkof & Co. v. Gimbel
849 A.2d 1036 (Court of Special Appeals of Maryland, 2004)
Gravett v. Covenant Life Church
841 A.2d 342 (Court of Special Appeals of Maryland, 2004)
Westpointe Plaza II Ltd. Partnership v. Kalkreuth Roofing & Sheet Metal, Inc.
675 A.2d 571 (Court of Special Appeals of Maryland, 1996)
Reisterstown Lumber Co. v. Royer
605 A.2d 980 (Court of Special Appeals of Maryland, 1992)
DMH Joint Venture v. Hahner
562 A.2d 772 (Court of Special Appeals of Maryland, 1989)
Ami Operating Partners Ltd. Partnership v. Jad Enterprises, Inc.
551 A.2d 888 (Court of Special Appeals of Maryland, 1989)
Kaufman v. Miller
542 A.2d 391 (Court of Special Appeals of Maryland, 1988)
E.L. Gardner, Inc. v. Bowie Joint Venture
494 A.2d 988 (Court of Special Appeals of Maryland, 1985)
Ocean Plaza Joint Venture v. Crouse Construction Co.
490 A.2d 252 (Court of Special Appeals of Maryland, 1985)
Cabana, Inc. v. Eastern Air Control, Inc.
487 A.2d 1209 (Court of Special Appeals of Maryland, 1985)
Marteg Corp. v. ZONING BD. OF REVIEW, ETC.
425 A.2d 1240 (Supreme Court of Rhode Island, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
408 A.2d 1051, 44 Md. App. 293, 1979 Md. App. LEXIS 435, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tyson-v-masten-lumber-supply-inc-mdctspecapp-1979.