Mervin L. Blades & Son, Inc. v. Lighthouse Sound Marina and Country Club

377 A.2d 523, 37 Md. App. 265, 1977 Md. App. LEXIS 304
CourtCourt of Special Appeals of Maryland
DecidedSeptember 13, 1977
Docket1096, September Term, 1976
StatusPublished
Cited by9 cases

This text of 377 A.2d 523 (Mervin L. Blades & Son, Inc. v. Lighthouse Sound Marina and Country Club) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mervin L. Blades & Son, Inc. v. Lighthouse Sound Marina and Country Club, 377 A.2d 523, 37 Md. App. 265, 1977 Md. App. LEXIS 304 (Md. Ct. App. 1977).

Opinion

Powers, J.,

delivered the opinion of the Court.

Mechanics’ liens in Maryland were transformed into little more than debt claims when the Court of Appeals, following several due process rulings of the United States Supreme Court, decided Barry Properties v. Fick Bros., 277 Md. 15, 353 A. 2d 222, on 10 February 1976. The Court prefaced its discussion of the issue raised in that case with this explanation, at 19:

“The basis of the present attack — that the imposition of a lien without notice and an opportunity for a prior hearing, as the Maryland statute authorizes, deprives the owner of his property without procedural due process — emanates from a quartet of recent Supreme Court decisions which address the question of whether certain statutory prejudgment creditor remedies are consonant wTith the due process clause of the Fourteenth Amendment. In the order they were decided, those cases are: Sniadach v. Family Finance Corp., 395 U. S. 337, 89 S. Ct. 1820, 23 L.Ed.2d 349 (1969) (garnishment of wages); Fuentes v. Shevin, 407 U. S. 67, 92 S. Ct. 1983, 32 L.Ed.2d 556 (1972) (replevin of personalty); Mitchell v. W. T. Grant Co., 416 U. S. 600, 94 S. Ct. 1895, 40 L.Ed.2d 406 (1974) (sequestration of personalty pursuant to *267 vendor’s lien); and North Georgia Finishing, Inc. v. Di-Chem, Inc., 419 U. S. 601, 95 S. Ct. 719, 42 L.Ed.2d 751 (1975) (garnishment of bank account).”

After a thorough and exhaustive analysis of the constitutional principles expressed in the cited opinions of the Supreme Court, and of the Maryland statute, the Court said, at 33:

“We conclude, therefore, that, because it allows prejudgment seizures without notice, a prior hearing or other sufficient safeguards, and cannot be justified under the extraordinary circumstances exception, Maryland’s mechanics’ lien law is incompatible with the due process clauses of Article 23 and the Fourteenth Amendment.” 1

The mechanics’ lien laws of Maryland, as they existed before the decision in Barry Properties, were found in Code, Real Property Article, Title 9, Subtitle 1, and were codified as §§ 9-101 to 9-111. Procedural implementation of the statutory law was found in the BG Rules.

Briefly summarized, the law, the numerous interpretive decisions, and the BG Rules, provided that a lien attached to a building and to the land covered by it, and as much immediately adjacent land of the same owner as may be necessary for the ordinary and useful purposes of the building, for work done and for materials furnished for or about the building. The lien' attached at the time the work was done or the materials were furnished, and had priority over any mortgage, judgment, lien, or encumbrance attaching to the building or ground subsequent to the commencement of the building. All valid mechanics’ liens on any building and ground shared equal priority. §§ 9-101, 9-102.

*268 To preserve his lien, a claimant was required to file a claim or statement of his demand in the office of the clerk of the circuit court before the expiration of 180 days 2 after the work was finished or the materials furnished. What the claim was required to set forth was specified in § 9-105 (c i.

The final step, and the first judicial step, followed as prescribed in § 9-106. Unless within one year after the claim was filed, the claimant brought an equity suit to enforce it, the lien expired. If a suit to enforce the lien was timely filed, the lien remained until the case was concluded. The owner of the property, or other person interested, could at any time file an equity suit to compel the claimant to prove the validity of the lien. A claimant’s suit to enforce his lien invoked the special statutory in rem jurisdiction of the equity court. Trial of such a suit could involve one or more of several issues, such as whether proper notice of intent to claim the lien was given, if required by § 9-103; whether the lien was preserved beyond its original life of 180 days by the timely filing of a claim; whether the claim as filed satisfied the requirements of § 9-105 (c); or whether the claimant is entitled to the full amount claimed. A finding of a valid lien in any amount normally resulted either in payment, so as to discharge the lien, or in a decree for sale of the property to satisfy the lien. Rule BG73.

It should be noted that the entire proceeding, from the creation of the lien to its discharge, was in rem, and even a final judgment after trial did not result in an in personam money judgment against any party. Indeed, § 9-109 explicitly preserved “the right of any person, to whom any debt is due for work done or material furnished, to maintain any personal action against the owner of the building or any other person liable for the debt.”

Having held in Barry Properties that Maryland’s mechanics’ lien law violated due process, the Court of Appeals looked for severable salvage, to “preserv[e] enough *269 to have a law capable of fulfilling the principal legislative intent.” At 36-37. The Court said, at 37:

“We think that this can be accomplished by excising that portion of the statute which purports to create a lien from the time work is performed or materials furnished to the time a lien is established by judicial determination in a proceeding sufficient with respect to due process. We therefore hold that under the current statute there can be no existing lien on property until and unless the claimant prevails either in a suit to enforce the claimed lien or in some other appropriate proceeding providing notice and a hearing (i.e., a declaratory judgment action). What the claimant, be he a general contractor or subcontractor, possesses up to that point in time is a chose in action. Under this ruling, we believe, the statute continues to effectuate the primary legislative intent, yet the owner is not deprived of a significant property interest without due process since the owner’s interest is not impinged upon until after he is provided with notice and an opportunity for a hearing. It follows that § 9-107 (b), to the extent that it grants mechanics’ liens ‘priority over any mortgage, judgment, lien or encumbrance attaching to the building or ground subsequent to the commencement of the building’ but prior to the time the lien is established by a judicial determination, is also null and void since to hold otherwise would permit contractors to seize with their left hand what we have said they cannot grasp with their right.”

It will be seen that the very valuable right which was preserved was the right of a creditor for labor or materials to proceed in rem

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arfaa v. Martino
946 A.2d 995 (Court of Appeals of Maryland, 2008)
Martino v. Arfaa
906 A.2d 945 (Court of Special Appeals of Maryland, 2006)
Wolf Organization, Inc. v. Oles
705 A.2d 40 (Court of Special Appeals of Maryland, 1998)
Ocean Plaza Joint Venture v. Crouse Construction Co.
490 A.2d 252 (Court of Special Appeals of Maryland, 1985)
Cabana, Inc. v. Eastern Air Control, Inc.
487 A.2d 1209 (Court of Special Appeals of Maryland, 1985)
Himmighoefer v. Medallion Industries, Inc.
487 A.2d 282 (Court of Appeals of Maryland, 1985)
Hill v. Parkway Industrial Center
435 A.2d 472 (Court of Special Appeals of Maryland, 1981)
Talbott Lumber Co. v. Tymann
428 A.2d 1229 (Court of Special Appeals of Maryland, 1981)
Tyson v. Masten Lumber & Supply, Inc.
408 A.2d 1051 (Court of Special Appeals of Maryland, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
377 A.2d 523, 37 Md. App. 265, 1977 Md. App. LEXIS 304, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mervin-l-blades-son-inc-v-lighthouse-sound-marina-and-country-club-mdctspecapp-1977.