Ocean Plaza Joint Venture v. Crouse Construction Co.

490 A.2d 252, 62 Md. App. 435, 1985 Md. App. LEXIS 359
CourtCourt of Special Appeals of Maryland
DecidedApril 8, 1985
Docket642, September Term, 1984
StatusPublished
Cited by11 cases

This text of 490 A.2d 252 (Ocean Plaza Joint Venture v. Crouse Construction Co.) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ocean Plaza Joint Venture v. Crouse Construction Co., 490 A.2d 252, 62 Md. App. 435, 1985 Md. App. LEXIS 359 (Md. Ct. App. 1985).

Opinion

*439 ROSALYN B. BELL, Judge.

In this appeal, we consider the effect of an order issued under the mechanics’ lien statute, Md. Real Property Code Ann., § 9-106 (1981, 1983 Cum.Supp.).

The Knott Company (Knott) entered into a contract under which it agreed to design and construct the Ocean Plaza Shopping Center in Ocean City, Maryland, in return for a lump sum payment. Knott subcontracted the excavation and grading portion of the project to Crouse Construction Company (Crouse). This agreement required Crouse to complete the work in accordance with specified plans and drawings contained in the general contract. The subcontract provided for a lump sum payment of $305,000, but the amount could be increased if the general contractor or the owner authorized extra work in writing. Without this prior written authorization, Crouse waived its right to claim additional compensation. Similar modifications of the amount under the general contract required the owner’s written approval of change orders submitted by Knott. The owner is Ocean Plaza Joint Venture (OPJV). 1 Each contract also provided for retainage: (1) The general contract stipulated a 10% retainage or holdback in payment until the architect executed a certificate of completion; (2) The subcontract provided for a 10% retainage until Knott received final payment from OPJV.

Before the excavation began, Knott informed Crouse that, instead of using the fill pit they had specified, Crouse would have to use a pit located two miles further from the construction site. The subcontractor hauled materials to the latter pit between July 27, 1982, and September 1982, but did not obtain a change order, written authorization, or an agreement to extra compensation before or after the *440 use. When Crouse filed its claim for the mechanics’ lien, however, it included a claim of $34,841.52 for the extra cost of hauling the greater distance. According to testimony-relating to the additional hauling required, it was ordinary practice to perform the extra work and submit a change order later.

On October 4, 1982, Crouse executed a change order to increase the subcontract amount from $305,000 to $309,500 for “loading” borrow materials. The agreement previously did not include compensation for loading. No mention of extra compensation for hauling the additional four miles per round trip appeared in this change order, nor in the next one submitted on April 7, 1983. This second order sought to adjust the figure on the prior change order to include additional excavation and grading costs, making the total subcontract amount $315,638.68. On May 9, 1983, Crouse executed a Waiver of Liens against Knott specifically acknowledging payment of the agreed lump sum plus extras as of May 5, 1983, with a remaining balance due of $4,585.88 plus the 10% retainage. This release also noted the total contract figure as “$311,052.80+”. 2 Evidence indicated that an estimate had been submitted to cover the extra hauling, which exceeded the amount ultimately billed. *441 Upon receipt of the required Waiver of Liens and verified draw form, the lender for OPJV disbursed the requested funds to Knott, the general contractor.

Crouse filed this mechanics’ lien action against OPJV in the Circuit Court for Worcester County. The petition contended that $70,371.27 3 remained due and owing for its work regarding the Ocean Plaza Shopping Center. The claim represented four items: (1) the extra cost of hauling fill material — $34,841.52; (2) the unpaid balance from an invoice dated October 25, 1983 — $4,000; (3) the balance due from an invoice dated March 3, 1983 — $729.75; and (4) the retainage withheld on the entire job — $30,500. These figures appear in Crouse’s records as amounts due. The subcontractor also filed the affidavit of Richard Crouse which described the details of the work done.

OPJV responded stating first that Crouse breached Section 11 of the subcontract, which required Crouse to submit to Knott “on a daily basis, duplicate payroll sheets, material tickets, and a statement, or slips for all other charges when performing additional work____” Also, due to disputes between OPJV, Knott, and Crouse, OPJV had not paid the retainage otherwise due Knott. As a result, the owner requested a dismissal of the petition. In support of its Answer, OPJV filed two affidavits: (1) Frank J. McGinnes, President of Knott, alleged that Crouse failed to furnish the documents required by the subcontractor for performing additional work, and that OPJV did not pay Knott the 10% retainage; (2) Richard M. Singer, a partner of OPJV, stated that the retainage had not been paid to Knott, and that other monies remained unpaid “due to disputes between Crouse Construction Company, The Knott Company and [OPJV].” Nowhere in these pleadings did OPJV assert the defense of waiver of liens.

On November 30, 1983, the court conducted a show cause hearing and issued an interlocutory order in the amount of *442 $70,371.27 4 and established a mechanics’ lien on the property. The court also provided for the release of the property upon the owner’s posting bond and directed the scheduling of a hearing on the merits.

The trial on the merits occurred on January 31, 1984. At the outset of the trial, the court announced that, because many of Crouse’s allegations remained uncontroverted by OPJV’s answer and affidavits, they were deemed admitted. Thus, the court would only hear two issues.

During these proceedings, two documents — a “General Release of Liens” dated August 31, 1982, and a “Waiver of Liens” dated May 9, 1983 5 — were received into evidence in relation to the amount of the lien, and Crouse did not object. They were offered by OPJV during questioning of the president of Crouse concerning the delay between the actual hauling and the submission of an invoice. He testified that the February 21, 1983, invoice for $34,841.52 on which he based part of his claim covered the cost of the extra distance travelled to the fill pit during July, August and September of 1982. The president admitted that this work was performed before he signed the waiver and, therefore, he could have demanded the extra amount as of September 1982. But because the figure was not calculated until February 1983, Crouse submitted the invoice instead of seeking approval of the charge as an extra.

The cross-examination of Crouse’s corporate secretary revealed that the company had received an additional back charge of $6,600 from Knott shortly before trial for work actually performed by another contractor. The president of Crouse verified that he had agreed to back charges of up to $5,000 for uncompleted work.

*443 Singer, a general partner of OPJV, indicated that monies were released to the general contractor only after the owner’s lender received written certification that the subcontractors obtained their draw and executed waivers of liens.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Attorney Grievance Commission v. Siskind
930 A.2d 328 (Court of Appeals of Maryland, 2007)
Bowser v. Resh
907 A.2d 910 (Court of Special Appeals of Maryland, 2006)
Howard Chertkof & Co. v. Gimbel
849 A.2d 1036 (Court of Special Appeals of Maryland, 2004)
Westpointe Plaza II Ltd. Partnership v. Kalkreuth Roofing & Sheet Metal, Inc.
675 A.2d 571 (Court of Special Appeals of Maryland, 1996)
Fearnow v. Chesapeake & Potomac Telephone Co.
655 A.2d 1 (Court of Special Appeals of Maryland, 1995)
Reisterstown Lumber Co. v. Royer
605 A.2d 980 (Court of Special Appeals of Maryland, 1992)
St. James Construction Co. v. Morlock
597 A.2d 1042 (Court of Special Appeals of Maryland, 1991)
Gooch v. Maryland Mechanical Systems, Inc.
567 A.2d 954 (Court of Special Appeals of Maryland, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
490 A.2d 252, 62 Md. App. 435, 1985 Md. App. LEXIS 359, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ocean-plaza-joint-venture-v-crouse-construction-co-mdctspecapp-1985.