Kaufman v. Miller

542 A.2d 391, 75 Md. App. 545, 1988 Md. App. LEXIS 121
CourtCourt of Special Appeals of Maryland
DecidedJune 13, 1988
Docket1489, 1490, September Term, 1987
StatusPublished
Cited by5 cases

This text of 542 A.2d 391 (Kaufman v. Miller) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kaufman v. Miller, 542 A.2d 391, 75 Md. App. 545, 1988 Md. App. LEXIS 121 (Md. Ct. App. 1988).

Opinion

ROBERT M. BELL, Judge.

These appeals by Joel C. Kaufman, t/a Joel C. Kaufman Construction Company, appellant, from judgments of the Circuit Court for Carroll County dismissing appellant’s complaints to enforce Mechanics Lien against Bonnie A. Miller and against Charles B. Miller and Bonnie A. Miller, appellees, present but one question: Is a contractor entitled to maintain an action to establish a Mechanics Lien? Our answer to that question is “yes”. Accordingly, we will reverse and remand for further proceedings.

The well-pleaded allegations of fact contained in appellant’s complaints against appellees disclose the following. 1 Appellant entered into separate contracts with appellee Bonnie A. Miller and appellee Charles B. Miller 2 for the construction of two separate residences on two adjacent lots of real estate owned by appellee Bonnie A. Miller. Each appellee agreed to pay appellant a specified amount for his work. When he was not paid, despite having completed the *547 work, as well as having performed additional work requested by each appellee, appellant filed complaints to establish and enforce Mechanics’ Lien against both appellees. Each complaint contained the express acknowledgement “[t]hat [appellant] is a Contractor as defined in Section 9-101 of the Real Property Article of the Annotated Code of Maryland....”

Appellees were served with, and filed answers to, the complaints. In addition to admitting that appellant was a contractor and that they had a contract with him, each appellee interposed a motion to dismiss for failure to state a cause of action upon which relief can be granted. They offered several bases in support of these motions. Pertinent to this appeal, they argued that appellant, as a contractor, as opposed to a subcontractor, was not entitled to relief pursuant to the Mechanics’ Lien law. It was on this basis that the lower court, after argument, dismissed appellant’s actions.

The Mechanics’ Lien law in effect when the contracts at issue were made and appellant’s complaints were filed was codified in Maryland Real Property Code Ann. §§ 9-101-114 (1981 Replacement Volume, 1987 Cumm. Supp.). An analysis of its provisions renders ineluctable the conclusion that its benefits extend to contractors as well as to subcontractors.

The definitions of “contractor” and “subcontractor” are contained in § 9-101:

(d) Contractor.—“Contractor” means a person who has a contract with an owner.
(g) Subcontractor.—“Subcontractor” means a person who has a contract with anyone except the owner or his agent.

The term “contract”, on the other hand, is defined as “an agreement of any kind or nature, express or implied, for doing work or furnishing material, or both, for or about a building as may give rise to a lien under this subtitle.” Section 9-101(c). These definitions must be considered in *548 light of § 9-102(a), Property subject to lien. That section provides:

(a) Buildings.—Every building erected and every building repaired, rebuilt, or improved to the extent of 25 percent of its value is subject to establishment of a lien in accordance with this subtitle for the payment of all debts, without regard to the amount, contracted for work done for or about the building and for materials furnished for or about the building, including the drilling and installation of wells to supply water, the construction or installation of any swimming pool or fencing, the sodding, seeding or planting in or about the premises of any shrubs, trees, plants, flowers or nursery products, and the grading, filling, landscaping, and paving of the premises.

Reading the definitions in tandem with § 9-102(a), it is clear that, prerequisite to the establishment of a lien on a building on which work has been done and/or materials furnished, there must have been a contract for that work and/or for those materials. Furthermore, it is clear that the purpose of the lien is to ensure that those doing the work or furnishing the materials are paid pursuant to the contract under which they performed. Neither the language of § 9-102(a) nor the definitions previously cited suggests that a contractor may not himself perform the work or furnish the material and thus fall within the protection of the statute. In fact, common sense suggests that one who contracts directly with the owner may, and often does, perform the work and furnish the materials required by the contract.

That the Mechanics’ Lien law applies to contractors is made even clearer by analysis and comparison of §§ 9-104 and 9-105. Section 9-104 is captioned, “Notice to Owner by Subcontractor”, and provides, in pertinent part:

(a) Notice Required to entitle subcontractor to lien.—(1) A subcontractor doing work or furnishing materials or both for or about a building other than a single family dwelling being erected on the owner’s land for his own residence is not entitled to a lien under this subtitle *549 unless, within 90 days after doing the work or furnishing the materials, the subcontractor gives written notice of intention to claim a lien substantially in the form specified in subsection (b) of this section. 3 (2) A subcontractor doing work or furnishing materials or both for or about a single family dwelling being erected on the owner’s land for his own residence is not entitled to a lien under this subtitle unless, within 90 days after doing work or furnishing materials for or about that single family dwelling, the subcontractor gives written notice of an intention to claim a lien in accordance with subsection (a)(1) of this section and the owner has not made full payment to the contractor prior to receiving the notice.
s}: >je sfc H* ?¡e sk
(f) Payments by owner to contractor after notice; limitation on lien against certain single family dwellings.—
(1) On receipt of notice given under this section, the owner may withhold, from sums due the contractor, the amount the owner ascertains to be due the subcontractor giving the notice.
(2) If the subcontractor giving notice establishes a lien in accordance with this subtitle, the contractor shall receive only the difference between the amount due him and that due the subcontractor giving the notice.
(3) Notwithstanding any other provision of this section to the contrary, the lien of the subcontractor against a single family dwelling being erected on the land of the owner for his own residence shall not exceed the amount by which the owner is indebted under the contract at the time the notice is given.

Section 9-105, on the other hand, is captioned simply, “Filing of Claims”, and it provides:

(a) In order to establish a lien under this subtitle, a person entitled to a lien shall file proceedings in the circuit court for the county where the land or any part of *550

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cottage City Mennonite Church, Inc. v. Jas Trucking, Inc.
894 A.2d 609 (Court of Special Appeals of Maryland, 2006)
Brendsel v. Winchester Construction Co.
875 A.2d 789 (Court of Special Appeals of Maryland, 2005)
Moffit Bros. Drywall v. Slacum (In re Slacum)
272 B.R. 335 (D. Maryland, 2001)
Judd Fire Protection, Inc. v. Davidson
773 A.2d 573 (Court of Special Appeals of Maryland, 2001)
Golden Sands Club Condominium, Inc. v. Waller
545 A.2d 1332 (Court of Appeals of Maryland, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
542 A.2d 391, 75 Md. App. 545, 1988 Md. App. LEXIS 121, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kaufman-v-miller-mdctspecapp-1988.