Judd Fire Protection, Inc. v. Davidson

773 A.2d 573, 138 Md. App. 654, 2001 Md. App. LEXIS 96
CourtCourt of Special Appeals of Maryland
DecidedJune 1, 2001
Docket1180, Sept. Term, 2000
StatusPublished
Cited by2 cases

This text of 773 A.2d 573 (Judd Fire Protection, Inc. v. Davidson) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Judd Fire Protection, Inc. v. Davidson, 773 A.2d 573, 138 Md. App. 654, 2001 Md. App. LEXIS 96 (Md. Ct. App. 2001).

Opinion

KENNEY, Judge.

This appeal arises from a decision of the Circuit Court for Baltimore County granting a mechanic’s lien that had been opposed by appellant, Judd Fire Protection, Inc.' (“Judd”). Judd raises three issues on appeal, which we have reworded as follows:

1. Did the trial court err in finding that individual employees of a sub-subcontractor had standing to bring an *657 action against a subcontractor under Maryland’s Mechanics’ Lien statute when the sub-subcontractor furnished the subcontractor with a Mechanics’ Lien release?

2. Did the trial court err when it failed to use the contract price as the measure of damages?

3. Did the trial court err by failing to offset judgments in favor of those Appellees who previously were awarded restitution by the District Court in criminal proceedings against their employer, Steven Ramsey, the owner of SDR Fire Protection?

For the reasons set forth below, we answer the first question in the negative and the second in the affirmative. We do not reach the third question.

FACTUAL BACKGROUND

The property involved in this case is an apartment building owned by Woodlawn Limited Partnership (“Woodlawn”) and known as “Parkview at Woodlawn.” Woodlawn had entered into a general contract with Whiting-Turner, Inc. (“Whiting-Turner”) for construction of the building. Whiting-Turner subsequently subcontracted with Judd to install the automatic fire sprinkler systems (the “sprinkler system”).

Judd began installation of the sprinkler system in September of 1998. In October of 1998, Whiting-Turner accelerated the timetable for completion of the project. In order to meet the accelerated schedule, Judd was obliged to enter into a series of subcontracts with SDR Fire Protection (“SDR”), a business owned by Steven Ramsey. Appellees in this case were SDR employees.

Judd and SDR entered into four subcontracts, one for each floor on the west side of the building. SDR was responsible for installing a total of 749 sprinkler heads and pipes, and it was also responsible for testing the system after installation. The total contract price was $13,987 and covered labor only. Ramsey testified that the contract price “was done on a by the head basis.” Judd testified that the contract price was based on $17 per sprinkler head.

*658 SDR first sent people to the site on or about November 21, 1998. SDR and its employees entered into a collective bargaining agreement on or about December 4,1998.

SDR had completed about 85% of its work on the first floor, the attic, and the second floor when its employees walked off the job because their paychecks were being returned for insufficient funds. The date of the work stoppage was disputed. 1 In addition to failing to pay its employees, SDR did not have the proper insurance coverage required by its contracts with Judd.

As a result of SDR’s labor problems, Judd entered into an agreement whereby it paid SDR for work completed, less insurance payments made by Judd, and SDR signed a Lien Release. Judd paid SDR a total of $7,243.69, 2 which it calculated by multiplying $17 by the number of sprinkler heads actually installed. The Lien Release included a provision that materialmen would not be entitled to assert any liens against either the property or Judd. SDR did not obtain lien releases from any of the employees who had been working on the site.

Ramsey eventually was convicted of check fraud and was incarcerated at the time of the proceedings before the circuit court on the mechanic’s lien claim. In addition, some of the employees who had worked on the project had filed civil suits against Ramsey and obtained judgments, which were not satisfied. Consequently, on February 9, 1999, ten of SDR’s former employees filed a Petition to Establish Mechanics’ Lien against the Parkview at Woodlawn property. The plaintiffs in the action were: Larry Davidson, William Gilliam, Mike Green, John Hodge, Dennis Johnson, Melvin Morrison, Gary Nokes, Steve Randall, David Shirley, and Anthony S. Wood (the “plaintiffs”). They requested a lien in the amount of $37,910.52.

*659 Judd intervened in the case and filed an answer on April 20, 1999, on behalf of both Woodlawn and Whiting-Turner. That same day, Judd filed a motion to compel arbitration, 3 which the circuit court granted. The plaintiffs, unhappy with being ordered to arbitrate, filed a motion to alter or amend judgment on July 16,1999, which the court granted. 4

A hearing was held on April 17, 2000, and, at its conclusion, the court entered judgment in favor of Judd against Larry Davidson, Melvin Morrison, Gary Nokes, and David Shirley, all of whom failed to appear at the hearing. Counsel then submitted closing arguments by memoranda, and the parties returned to court on June 1, 2000.

Following a hearing, the court entered judgment against Judd and in favor of the remaining six plaintiffs. The court found that the plaintiffs were “entitled to recover the reasonable value of the services rendered in each instance by each employee considered separately.” The court then ordered Judd to pay damages as follows: (1) to Michael Green the sum of $3,973.93; (2) to John Hodge the sum of $3,973.93; (3) to Steven Randall the sum of $2,299.79; (4) to William Gilliam the sum of $3,870.36; (5) to Dennis Johnson the sum of $1,984.80; and (5) to Anthony Woods the sum of $2,669.47. The court also assigned to Judd any judgments and orders of restitution obtained by any of the six plaintiffs against Ramsey as a result of prior criminal or civil proceedings. This appeal followed.

DISCUSSION

Standard of Review

When an action has been tried without a jury, we review the case on both the law and the evidence, but we will not reverse a case on the evidence in the absence of clear *660 error. Md. Rule 8—131(c); Narayen v. Bailey, 130 Md.App. 458, 461, 747 A.2d 195 (2000). Our review on matters of law, however, is more expansive. Narayen, 130 Md.App. at 461, 747 A.2d 195.

I. Standing

Judd first argues that appellees lacked standing to maintain an action under Maryland’s Mechanics’ Liens statute, Md. Code (1974, 1996 Repl.Vol., 1999 Supp.), § 9-101 et seq. of the Real Property Article (“RP”).

A mechanics’ lien is a statutorily created in rem remedy.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Benway v. Maryland Port Administration
989 A.2d 1239 (Court of Special Appeals of Maryland, 2010)
Himes Associates, Ltd. v. Anderson
943 A.2d 30 (Court of Special Appeals of Maryland, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
773 A.2d 573, 138 Md. App. 654, 2001 Md. App. LEXIS 96, Counsel Stack Legal Research, https://law.counselstack.com/opinion/judd-fire-protection-inc-v-davidson-mdctspecapp-2001.