VNB Mortgage Corp. v. Lone Star Industries, Inc.

209 S.E.2d 909, 215 Va. 366, 75 A.L.R. 3d 497, 1974 Va. LEXIS 293
CourtSupreme Court of Virginia
DecidedDecember 2, 1974
DocketRecord 730875
StatusPublished
Cited by16 cases

This text of 209 S.E.2d 909 (VNB Mortgage Corp. v. Lone Star Industries, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
VNB Mortgage Corp. v. Lone Star Industries, Inc., 209 S.E.2d 909, 215 Va. 366, 75 A.L.R. 3d 497, 1974 Va. LEXIS 293 (Va. 1974).

Opinion

Cochran, J.,

delivered the opinion of the court.

Spring Construction Co., Inc. (Spring), one of the appellees herein, was general contractor under contracts with appellees Cogic Homes, Inc., and Parker-Riddick Village, Inc. (collectively, the Owners), for the construction of two housing developments in the City of Nansemond. The construction was financed by appellant, VNB Mortgage Corporation (formerly Mortgage Investment Corporation) (VNB), which held deeds of trust on each of the properties to secure advances made by it. Financing of the development projects was insured by the Federal Housing Commissioner, Department of Housing and Urban Development (HUD).

After substantial performance by Spring under the construction contracts (estimated by Spring at 78i/r of completion under one and 907c under the other) the problem arose of providing adequate sewer facilities, not included in the contracts, at an estimated additional cost of $175,000. When the Owners were unable to finance this additional expense, HUD notified VNB by letter of October 12, 1972, that it would not insure payments for work already performed under the contracts in September, 1972, or for any additional advances. VNB thereupon declined to honor requisitions for work performed in September, 1972, or to make any further advances, and construction on both projects ceased. Moreover, in accordance with the contract provisions 109f- had been withheld from each progress payment made to Spring pending completion of the projects, and Spring has never received these withheld sums.

Mechanics’ liens were filed by the general contractor, architects, and by various subcontractors and materialmen, and suits in equity were instituted to enforce these liens. During the pendency of these suits VNB proceeded to have the trustees foreclose and sell the properties at public auction under the *368 deeds of trust, posting surety bonds under Code §§ 43-70 and -71 (Repl. Vol. 1970) to clear the titles of mechanics’ liens. The mechanics’ lien suits were consolidated for trial as two proceedings, and VNB and the trustees under its deeds of trust, as well as the Owners, were parties defendant in the litigation.

VNB contended in the trial court and before us that Spring and the subcontractors and materialmen had waived their rights to file mechanics’ liens for work performed and materials supplied by them at the Owners’ properties. The trial court, after hearing evidence in the consolidated proceedings, entered, on August 23, 1973, and September 4, 1973, the decrees appealed from herein holding that the construction contracts had been breached by the Owners, and that VNB was a party to the breach and was estopped to rely on the alleged waiver, so that the mechanics’ liens were in full force and effect.

Each of the two construction contracts between the respective Owners and Spring was on a standard Federal Housing Administration (FHA) Form which contained the following provision:

“Article 7—Waiver of Lien or Claim
The Contractor shall file no mechanic’s or materialman’s lien or maintain any claim against the Owner’s real estate or improvements for or on account of any work done, labor performed or materials furnished under this Contract.”

VNB argues that by this provision Spring expressly waived its right to file mechanic’s or materialmen’s liens against the properties. We agree.

Spring contends that the language of Article 7 evidences an executory promise, a promise to waive liens in the future rather than a present waiver, and that there was anticipatory breach of the contracts by the Owners which freed Spring from this provision and every other contractual obligation. The alleged anticipatory breach relied on was the failure of the Owners to pay because of the HUD decision to terminate federal insurance of progress payments advanced by VNB. But lien waivers, by their very nature, are given in anticipation of the possibility of nonpayment. Resort to mechanics’ liens generally occurs only when there is a failure to pay, so that the requirement of a waiver of liens is intended to prohibit the contractor from asserting an otherwise available lien when he is not paid by the *369 owner. Walker & Laberge Co. v. Bank, 206 Va. 683, 691, 146 S.E.2d 239, 245 (1966). Nor do we find any merit in Spring’s argument that an exception to the rule that a waiver of liens remains in effect upon nonpayment by the owner should apply where the nonpayment occurs under contracts for which payments are guaranteed by a federal agency.

We hold that Article 7 was an independent covenant whereby Spring agreed that it would not file any mechanic’s liens in the event of nonpayment. Spring contends that repudiation of the contract cancels the lien waiver, but that rule applies only to bilateral contracts consisting of mutually dependent promises. Simpson v. Scott, 189 Va. 392, 398, 53 S.E.2d 21, 23-24 (1949).

Spring’s counsel conceded in argument before us that he could find no authority to support the estoppel theory on which the decision of the trial court was based, and we agree that this theory is inapplicable in the present case. To determine the rights of the general contractor and the subcontractors, we are concerned primarily with the construction of contracts.

The contracts between Spring and the subcontractors contained the following paragraph:

“(5) Subcontractor agrees to indemnify and hold harmless the Contractor for any and all losses and damages occasioned by or resulting under Contractor’s contract with Owner caused by the fault, negligence or otherwise of Subcontractor, omd agrees further to be bound to the Contractor by the terms of the Agreement, general conditions, drawings and specifications, and to assume toward Contractor all the obligations and responsibilities that the Contractor, by those documents, assumes to the Owner. ’’(Emphasis added.)

VNB asserts that by this provision the waiver of liens set forth in Article 7 of Spring’s contracts with the Owners was incorporated by reference and accepted by the subcontractors. The language of paragraph (5), standing alone, may be susceptible to such an interpretation. See e.g., Harper v. Home Indemnity Company, 140 So.2d 653 (La. Ct. App. 2d Cir. 1962); Walker v. Collins Const. Co., 236 N.W. 334 (Neb. 1931). Nevertheless, it follows but falls far short of the specificity of paragraph (1) of the subcontracts, which provides in pertinent part as follows:

“(1) Subcontractor agrees to furnish all material and perform *370 all work as follows: ... in accordance with the drawings and specifications prepared by [the architect] . . . for said project, and in accordance with all the terms, general conditions and special conditions, and in accordance with drawings and specifications described ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

UNIWEST CONST. v. Amtech Elevator Services
699 S.E.2d 223 (Supreme Court of Virginia, 2010)
Holt v. Nedry
64 Va. Cir. 373 (Fairfax County Circuit Court, 2004)
Judd Fire Protection, Inc. v. Davidson
773 A.2d 573 (Court of Special Appeals of Maryland, 2001)
Gordonsville Energy, L.P. v. Virginia Electric & Power Co.
512 S.E.2d 811 (Supreme Court of Virginia, 1999)
Loudoun Paving, Inc. v. Fort Beauregard Development Corp.
30 Va. Cir. 177 (Loudoun County Circuit Court, 1993)
Virginia Dynamics Co. v. Payne
421 S.E.2d 421 (Supreme Court of Virginia, 1992)
McMerit Construction Co. v. Knightsbridge Development Co.
367 S.E.2d 512 (Supreme Court of Virginia, 1988)
Robinson v. Herrell Construction Co.
7 Va. Cir. 308 (Winchester County Circuit Court, 1986)
Maxum Foundations, Inc. v. Salus Corp.
779 F.2d 974 (Fourth Circuit, 1985)
Urbanational Developers, Inc. v. Shamrock Engineering, Inc.
372 N.E.2d 742 (Indiana Court of Appeals, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
209 S.E.2d 909, 215 Va. 366, 75 A.L.R. 3d 497, 1974 Va. LEXIS 293, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vnb-mortgage-corp-v-lone-star-industries-inc-va-1974.