United States v. Lifecycle Construction Services LLC

CourtDistrict Court, D. Maryland
DecidedJune 26, 2024
Docket8:23-cv-01118
StatusUnknown

This text of United States v. Lifecycle Construction Services LLC (United States v. Lifecycle Construction Services LLC) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Lifecycle Construction Services LLC, (D. Md. 2024).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF MARYLAND

* UNITED STATES OF AMERICA, * for the use and benefit of * ROMAN MECHANICAL, INC. * * Plaintiff, * * Civ. No.: MJM-23-1118 v. * * LIFECYCLE CONSTRUCTION * SERVICES, LLC, et al. * * Defendants. * * * * * * * * * * * *

MEMORANDUM OPINION AND ORDER United States of America, for the use and benefit of Roman Mechanical, Inc. (“Plaintiff” or “Roman”), brings this action against Lifecycle Construction Services, LLC (“Lifecycle”) and The Hanover Insurance Company (“Hanover”) (collectively “Defendants”) under 28 U.S.C. § 1331 and 40 U.S.C. § 3133, alleging breach of contract, quantum meruit/unjust enrichment, violations of the Miller Act, and violations of the Maryland Prompt Payment Act. See Compl. (ECF No. 1). Plaintiff’s claims arise out of a 2021 subcontract between Lifecycle, the general contractor, and Roman, the subcontractor, for a construction project for the United States Navy in Annapolis, Maryland. This matter is before the Court on Defendants’ Motion to Dismiss (the “Motion”). ECF No. 23. The Motion is fully briefed and ripe for disposition. No hearing is necessary. See Loc. R. 105.6 (D. Md. 2023). For the reasons set forth below, the Motion will be GRANTED IN PART and DENIED IN PART.

I. BACKGROUND On or about August 12, 2016, the U.S. Navy hired Lifecycle as a general contractor for improvements and construction at the MWR Annapolis Naval Academy Cottages (the “Project”). Compl. ¶ 7. On August 16, 2016, Lifecycle executed a payment bond with Hanover to ensure that all parties supplying labor and materials for the Project would be paid. Id. ¶ 8; ECF No. 1-2 (Payment Bond). “On September 10, 2021, Lifecycle subcontracted with [Roman] for Roman to provide HVAC and plumbing work and materials to the Project.” Compl. ¶ 9. The base amount of the subcontract agreement (the “Subcontract”) was $227,500.00. Id. ¶ 10. “During the course of the project, Lifecycle approved change orders in the amount of $9,850.00[,]” bringing the total

value of the Subcontract to $237,350.00. Id. ¶¶ 11–12. Roman worked on the Project from October 4, 2021, to January 13, 2023, and completed its work in accordance with the Subcontract. Id. ¶ 14– 15. Roman alleges that Lifecycle failed to pay $47,892.50 of the $237,350.00 owed to Roman under the Subcontract. Id. ¶ 13. Roman also alleges that, due to Lifecycle’s mismanagement, it incurred additional delay damages of $170,932.60. Id. ¶¶ 17, 22. Thus, Roman’s total claimed damages are $218,825.10. Id. ¶ 23. On April 26, 2023, Roman filed its four-count Complaint against Defendants. Count I alleges that Defendants are jointly and severally liable under the payment bond for the balance due of $218,825.10. Id. ¶¶ 29–36. Count II alleges that Defendants breached the Subcontract “by

failing to timely pay Roman” the balance due. Id. ¶¶ 41, 43. Count III alleges, in the alternative to breach of contract, that Roman may recover the balance due under equitable theories of quantum meruit and unjust enrichment. Id. ¶¶ 45, 51, 53. Finally, Count IV alleges that Lifecycle violated the Maryland Prompt Payment Act (the “Act”) because “Lifecycle received payment for Roman’s materials and labor, but did not timely pay Roman as required by the . . . Act.” Id. ¶ 62.

II. STANDARD OF REVIEW Under Rule 8(a)(2) of Federal Rules of Civil Procedure, a complaint must contain “a short and plain statement of the claim showing the pleader is entitled to relief.” Fed. R. Civ. P. 8(a)(2). This rule is to “give the defendant fair notice of what the . . . claim is and the grounds upon which it rests.” Bell Atl. Corp. v. Twombly, 550 U.S. 544, 555 (2007) (cleaned up). To survive a Rule 12(b)(6) motion to dismiss, a plaintiff must plead enough factual allegations “to state a claim to relief that is plausible on its face.” Twombly, 550 U.S. at 570. “A claim has facial plausibility when the plaintiff pleads factual content that allows the court to draw the reasonable inference that the defendant is liable for the misconduct alleged.” Ashcroft v. Iqbal,

556 U.S. 662, 663 (2009). A complaint need not include “detailed factual allegations,” but it must set forth “enough factual matter (taken as true) to suggest” a cognizable cause of action, “even if . . . [the] actual proof of those facts is improbable and . . . recovery is very remote and unlikely.” Twombly, 550 U.S. at 555–56 (internal quotation marks omitted). Furthermore, federal pleading rules “do not countenance dismissal of a complaint for imperfect statement of the legal theory supporting the claim asserted.” Johnson v. City of Shelby, 574 U.S. 10, 10 (2014) (per curiam). However, “a plaintiff’s obligation to provide the grounds of his entitlement to relief requires more than labels and conclusions, and a formulaic recitation of the elements of a cause of action’s elements will not do.” Twombly, 550 U.S. at 555 (cleaned up). When considering a motion to dismiss, a court must take the factual allegations in the

complaint as true and draw all reasonable inferences in favor of the plaintiff. King v. Rubenstein, 825 F.3d 206, 212 (4th Cir. 2016). At the same time, “a court is not required to accept legal conclusions drawn from the facts.” Retfalvi v. United States, 930 F.3d 600, 605 (4th Cir. 2019) (citing Papasan v. Allain, 478 U.S. 265, 286 (1986)).

III. DISCUSSION In their Motion, Defendants argue: (A) Count IV should be dismissed because the Subcontract’s Virginia choice-of-law provision bars Plaintiff’s Maryland Prompt Payment Act claim; (B) Count III should be dismissed because Plaintiff cannot recover in equity for claims that are exclusively governed by the terms of the Subcontract; (C) Plaintiff’s claims for delay damages in Counts I, II, and III should be dismissed because Plaintiff (1) failed to adhere to the Subcontract’s notice provision and (2) waived its delay damages claims; and finally, (D) Hanover should be dismissed from Count II because Plaintiff cannot recover for breach of contract against Hanover under the Miller Act. The Court addresses each of Defendants’ arguments in turn.

A. Choice of Laws and Maryland Prompt Payment Act (Count IV) Count IV of the Complaint seeks recovery under Maryland’s Prompt Payment Act (the “Act”). Defendants argue that the Subcontract’s choice-of-law provision bars Plaintiff from recovering under the Act. The Act generally provides that a contractor or subcontractor who, pursuant to an express or implied contract, does work or furnishes material for or about a building shall be entitled to payment in accordance with prescribed deadlines. Md. Code Ann., Real Prop. §§ 9-301 & 9-302.

Among other things, the Act requires a contractor to pay a subcontractor “undisputed amounts owed to its subcontractors within [seven] days” of receipt of payment for the subcontractors’ “work or materials.” Md. Code Ann., Real Prop. § 9-302(b)(3). Remedies for payment violations include equitable relief, interest on the amount owed, reasonable costs, and, in the instance of bad faith, reasonable attorney’s fees. Id. at § 9-303(b).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Papasan v. Allain
478 U.S. 265 (Supreme Court, 1986)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Kunda v. C.R. Bard, Inc.
671 F.3d 464 (Fourth Circuit, 2011)
Sanders v. Mueller
133 F. App'x 37 (Fourth Circuit, 2005)
CDC-LCGH, LLC v. Mayor and City Council
313 F. App'x 637 (Fourth Circuit, 2009)
Utica Mutual Insurance Co. v. National Indemnity Co.
173 S.E.2d 855 (Supreme Court of Virginia, 1970)
VNB Mortgage Corp. v. Lone Star Industries, Inc.
209 S.E.2d 909 (Supreme Court of Virginia, 1974)
Board of Supervisors v. Southern Cross Coal Corp.
380 S.E.2d 636 (Supreme Court of Virginia, 1989)
Bender-Miller Co. v. Thomwood Farms, Inc.
179 S.E.2d 636 (Supreme Court of Virginia, 1971)
Stanley's Cafeteria, Inc. v. Abramson
306 S.E.2d 870 (Supreme Court of Virginia, 1983)
United Masonry Inc. v. Riggs National Bank
357 S.E.2d 509 (Supreme Court of Virginia, 1987)
Alternatives Unlimited, Inc. v. New Baltimore City Board of School Commissioners
843 A.2d 252 (Court of Special Appeals of Maryland, 2004)
United States v. Centex Const. Co., Inc.
638 F. Supp. 411 (W.D. Virginia, 1985)
Ace American Insurance v. Grand Banks Yachts, Ltd.
587 F. Supp. 2d 697 (D. Maryland, 2008)
Baker v. ANTWERPEN MOTORCARS LTD.
807 F. Supp. 2d 386 (D. Maryland, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
United States v. Lifecycle Construction Services LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-lifecycle-construction-services-llc-mdd-2024.