§ 9-302

Maryland·Article grp Real Property·Title 9
(a)Except for work done or materials furnished under a contract enumerated in § 9–305 of this subtitle, a contractor or subcontractor who does work or furnishes material under a contract shall be entitled to prompt payment under subsection (b) of this section.
(b)(1) If the contract is with an owner, the owner shall:
(i)If the contract does not provide for specific dates or times of payment, pay to the contractor undisputed amounts owed under the terms of the written contract, within the earlier of: 1. 30 days after the day on which the occupancy permit is granted; or 2. 30 days after the day on which the owner or the owner’s agent takes possession; or
(ii)If the contract provides for specific dates o

Free access — add to your briefcase to read the full text and ask questions with AI

Maryland § 9-302 — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Nearby Sections

15
§ 9-101
§ 9-101
§ 9-102
§ 9-102
§ 9-103
§ 9-103
§ 9-104
§ 9-104
§ 9-105
§ 9-105
§ 9-106
§ 9-106
§ 9-107
§ 9-107
§ 9-108
§ 9-108
§ 9-109
§ 9-109
§ 9-110
§ 9-110
§ 9-111
§ 9-111
§ 9-112
§ 9-112
§ 9-113
§ 9-113
§ 9-114
§ 9-114
§ 9-201
§ 9-201
View on official source ↗