§ 9-105

Maryland § 9-105
JurisdictionMaryland
Article grpReal Property
Title9

This text of Maryland § 9-105 is published on Counsel Stack Legal Research, covering Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Md. Code Ann., Real Property § 9-105 (2026).

Text

(a)In order to establish a lien under this subtitle, a person entitled to a lien shall file proceedings in the circuit court for the county where the land or any part of the land is located within 180 days after the work has been finished or the materials furnished. The proceedings shall be commenced by filing with the clerk, the following:
(1)A petition to establish the mechanic’s lien, which shall set forth at least the following:
(i)The name and address of the petitioner;
(ii)The name and address of the owner;
(iii)The nature or kind of work done or the kind and amount of materials furnished, the time when the work was done or the materials furnished, the name of the person for whom the work was done or to whom the mate

Free access — add to your briefcase to read the full text and ask questions with AI

Nearby Sections

15
§ 9-101
§ 9-101
§ 9-102
§ 9-102
§ 9-103
§ 9-103
§ 9-104
§ 9-104
§ 9-105
§ 9-105
§ 9-106
§ 9-106
§ 9-107
§ 9-107
§ 9-108
§ 9-108
§ 9-109
§ 9-109
§ 9-110
§ 9-110
§ 9-111
§ 9-111
§ 9-112
§ 9-112
§ 9-113
§ 9-113
§ 9-114
§ 9-114
§ 9-201
§ 9-201
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Maryland § 9-105, Counsel Stack Legal Research, https://law.counselstack.com/statute/md/grp/9-105.