McMerit Construction Co. v. Knightsbridge Development Co.

367 S.E.2d 512, 235 Va. 368, 4 Va. Law Rep. 2555, 1988 Va. LEXIS 62
CourtSupreme Court of Virginia
DecidedApril 22, 1988
DocketRecord 850441
StatusPublished
Cited by12 cases

This text of 367 S.E.2d 512 (McMerit Construction Co. v. Knightsbridge Development Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McMerit Construction Co. v. Knightsbridge Development Co., 367 S.E.2d 512, 235 Va. 368, 4 Va. Law Rep. 2555, 1988 Va. LEXIS 62 (Va. 1988).

Opinion

THOMAS, J.,

delivered the opinion of the Court.

The issue in this appeal is whether, by executing documents known as contractor’s affidavits, McMerit Construction Company (“McMerit”) waived its right to file a mechanic’s lien against property owned by Knightsbridge Development Company, Inc. (“Knightsbridge”). The trial court ruled that McMerit waived its lien rights. We disagree. Therefore, we will reverse the judgment of the trial court.

On July 11, 1983, Knightsbridge and McMerit entered into a contract for the construction of a 14-story condominium complex in Rosslyn, Virginia. Article 9 of the General Conditions of the Contract for Construction concerned “Payments and Completion.” A specially drafted provision, subparagraph 9.5.6, was added to Article 9; it provided as follows:

*370 Each application for a progress payment to be valid must be accompanied by a partial lien waiver and release, in form satisfactory to Owner, from the Contractor covering all work performed through the date of the previous months application together with, if requested by Owner, similar lien waivers from all subcontractors performing work under this Contract or otherwise on the job.

Knightsbridge supplied the forms to McMerit for use in making applications for payment. McMerit was required to sign a document designated “Contractor’s Affidavit.” That document did not contain the words “lien” or “waiver.” It nowhere expressly states that it is a lien waiver. But it did provide as follows:

The CONTRACTOR acknowledges receipt from OWNER of payment of all sums due for work performed, labor and materials furnished or supplied to the date of the previous advance in connection with the construction of the Project. All subcontractors, contractors, suppliers, materialmen, laborers and workmen employed or engaged by the CONTRACTOR on the Project have been paid for all work previously performed for which payment has been made by or on behalf of OWNER, and all sums due for materials and supplies furnished to CONTRACTOR or for the Project have been paid for up to and including the period covered by the last preceding advance which was made on the 19th day of February, 1985, in the amount of $1,577,818.00.
It is understood that this Affidavit and Sworn Statement together with attached Contractor Application for Payment No. 19 will be delivered by OWNER to TITLE INSURERS for the purpose of obtaining advances of money to or for the benefit of OWNER.

(Emphasis added). McMerit submitted 19 applications for payment including therewith 19 contractor’s affidavits. If these affidavits constituted valid lien waivers, they would waive all liens for money owed prior to February 19, 1985.

By contrast, the form required of the subcontractors and materialmen was labeled, “Partial Affidavit, Waiver of Lien And Release.” That document provided in pertinent part as follows:

*371 The undersigned does hereby forever release and discharge the Company, the Building and the land upon which the Building is located, from any and all causes of action, suits, debts, liens, damages, claims, and demands whatsoever in law or equity which the undersigned and/or its assigns ever had, now have, or ever will have against the Company, the Building, and/or the land upon which the Building is located, by reason of the delivery of materials and/or the performance of work relating to the construction of the Building.

Over the course of the construction, disputes arose between McMerit and Knightsbridge concerning certain aspects of the work. McMerit contended that it was required to perform work and supply materials in excess of what was required by the contract. McMerit detailed many of its claims in a document entitled CPR 102. The parties reached agreement as to some of the disputed items and set forth the agreed-upon matters in a document entitled Change Order 30, dated December 20, 1984. That change order contained an attachment which reserved McMerit’s right to advance the other claims which had been set forth in CPR 102, but not agreed to by Knightsbridge; the attachment provided in pertinent part as follows: “Execution and delivery of this change order shall not be construed to constitute waiver or abandonment of any claims, defenses, or other matters that might be asserted by either party in respect of CPR #102 or the subject matter thereof.”

On February 27, 1985, McMerit filed a lien against the project in the amount of $603,710. Knightsbridge challenged the validity of that lien pursuant to Code § 43-17.1.

An evidentiary hearing was held on March 29, 1985. There, it was established that Knightsbridge had long been aware of McMerit’s claims for additional pay. Knightsbridge’s vice president, F. Pearson Ames, testified that when Change Order 30 was signed, it was intended by Knightsbridge to be a temporary settlement in anticipation of arbitration, but that Knightsbridge did not expect a lien to be filed. He testified that the reservation-of-right provision in Change Order 30 was included so that neither party would prejudice its rights in arbitration.

Ames also testified that the contractor’s affidavit was the partial lien waiver called for in paragraph 9.5.6 of the general conditions of the contract. On cross-examination, Ames admitted knowing *372 that McMerit was making claims for additional monies at the same time it was filing pay requests acknowledging that it had been paid all sums due. He admitted further that the contractor’s affidavits were never relied on by Knightsbridge to bar McMerit’s claims for additional funds.

A representative of the title insurance company also testified. He stated that the contractor’s affidavit was treated as a release of liens. He said further that his company first became aware of McMerit’s claim for additional monies when McMerit filed its lien.

McMerit’s project manager testified that the owner never advised McMerit that the contractor’s affidavits meant claims could not be submitted. He refuted the statement in the contractor’s affidavit that all payments had been made in a timely manner. When asked on cross-examination the significance of the contractor’s affidavit, the project manager said it was a document McMerit was told it had to sign in order to get paid. He also testified that, at the time of trial, McMerit had not been paid all sums due for the costs of labor and materials supplied to the project.

McMerit’s president testified that he never told Knightsbridge that McMerit intended to waive its lien rights with respect to the project. When he was asked what the contractor’s affidavit was he stated as follows:

A. I think it’s important to note it’s a partial waiver of lien and not a general waiver of lien.
Q. By “partial waiver of lien,” do you mean it’s associated with the progress payments so that it relates to each prospective progress payment?
A. That would be correct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

JTH Tax, LLC v. Gilbert
M.D. Florida, 2022
Welded Construction, L.P.
D. Delaware, 2020
TWP Enterprises, Inc. v. Dressel
82 Va. Cir. 211 (Loudoun County Circuit Court, 2011)
In re Estate of Rohrbaugh
80 Va. Cir. 253 (Fairfax County Circuit Court, 2010)
Weindorf v. Netscape Communications Corp.
173 F. App'x 44 (Second Circuit, 2006)
Allen Burke Easterly v. Pamela Jo Easterly
Court of Appeals of Virginia, 2002
Pysell v. Keck
559 S.E.2d 677 (Supreme Court of Virginia, 2002)
First American Bank v. J.S.C. Concrete Construction, Inc.
523 S.E.2d 496 (Supreme Court of Virginia, 2000)
Virginia Dynamics Co. v. Payne
421 S.E.2d 421 (Supreme Court of Virginia, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
367 S.E.2d 512, 235 Va. 368, 4 Va. Law Rep. 2555, 1988 Va. LEXIS 62, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcmerit-construction-co-v-knightsbridge-development-co-va-1988.