First American Bank v. J.S.C. Concrete Construction, Inc.

523 S.E.2d 496, 259 Va. 60, 2000 Va. LEXIS 20
CourtSupreme Court of Virginia
DecidedJanuary 14, 2000
DocketRecord 990366; Record 990426
StatusPublished
Cited by24 cases

This text of 523 S.E.2d 496 (First American Bank v. J.S.C. Concrete Construction, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
First American Bank v. J.S.C. Concrete Construction, Inc., 523 S.E.2d 496, 259 Va. 60, 2000 Va. LEXIS 20 (Va. 2000).

Opinion

JUSTICE COMPTON

delivered the opinion of the Court.

These two appeals stem from a single suit to enforce mechanics’ liens. Although such a lien is a creature of statute, the lien must have its foundation in a contract, with which the lien must correspond. Sergeant v. Denby, 87 Va. 206, 208, 12 S.E. 402, 402 (1890). Here, we must decide first just what comprises the underlying contract of the parties. Then, the dispositive issue will become whether *63 the contract’s lien waiver provisions control the rights of the lien claimant.

In 1989, Drewer Development Corporation (Drewer or DDC) was a developer of multiple-lot residential projects in Northern Virginia. J.S.C. Concrete Construction, Inc. (JSC), was a concrete flatwork and walls contractor, which had worked for Drewer for a number of years on different projects.

On January 10, 1991, JSC filed memoranda of mechanic’s lien against 13 lots in two different residential projects being developed by Drewer in Loudoun County. In a timely filed suit to enforce the liens, JSC’s bill of complaint named multiple defendants, including Drewer, which was the record owner of the properties, and other mechanic’s lien claimants. The bill also named as defendants First American Bank of Virginia and Commonwealth Abstract Corporation, Trustee (collectively, the Bank), the secured party and trustee, respectively, under construction loan deeds of trust upon the properties.

The cause was referred to a commissioner in chancery who held an evidentiary hearing in August 1995. At that stage of the proceeding, the only parties active in the litigation were JSC and the Bank; Drewer had ceased doing business in 1991.

In a December 1996 report, the commissioner recommended that portions of seven of the original 13 liens be declared valid in the total amount of $39,124.81 out of the $161,252.74 initially claimed. The commissioner also recommended that prejudgment interest be assessed from December 30, 1990.

JSC and the Bank filed exceptions to the commissioner’s report. Following argument of counsel, the chancellor overruled the exceptions, but for two minor items not at issue on appeal, and confirmed the report in a December 1998 final decree. We awarded the Bank and JSC separate appeals and consolidated them.

The facts are undisputed. On March 16, 1989, JSC entered into a “Contractor Base Agreement” with Drewer. The three-page, 29-para-graph, mostly preprinted agreement set forth the general conditions under which JSC would perform work for Drewer. It provided that its purpose was “to fix the obligations” of the parties with regard to the work.

It further provided that the work to be performed would be “specifically described in Work Orders issued but is generally as follows: To supply and install materials and labor for footings (turn down *64 slab) and insulation slab (step from slab to garage) Stoop and Steps and Walls.”

The Base Agreement also provided: “In conjunction with this Agreement, DDC may issue Work Orders from time to time covering the Work to be performed and time for completion at each specific job location. Work Orders will usually be issued prior to the start of required work.” The agreement stated that “the term Work Order shall include forms designated ‘Extra Work Order’ and other similar designations and containing information about commencing such Work and the payment for such Work.”

The agreement further provided that it was “non-exclusive and that DDC is free to contract with any other entity for the performance of the Work described in this Agreement.” Elaborating, the agreement stated that Drewer was “not obligated to issue Work Orders” to JSC. Also, the agreement provided that no payments would be due under it until Drewer received “a Work Completion Certificate which certifies that all Work to be performed under a particular Work Order has been completed satisfactorily.”

The remaining paragraphs of the Base Agreement included provisions requiring JSC, for example, to become familiar with plans and specifications, to cooperate with other contractors, to obtain all required licenses and permits, to indemnify Drewer for all claims arising from performance of the work, to provide new materials, to keep the job site free of waste and rubbish, and to obtain necessary insurance coverage.

Additionally, the agreement contained a paragraph providing that JSC waived all rights to file mechanics’ liens against the property for any labor, services, or materials furnished to Drewer.

During the time when JSC performed work for Drewer a pattern of performance was established between the parties. JSC would only begin work on a Drewer project when Drewer issued preprinted work order forms labeled “Extra Work Order.” These forms would name the particular project, identify the type of dwelling involved and its lot location, list the concrete work to be performed and state the price to be paid JSC. The date of the work order indicated the date that JSC was authorized to begin construction.

Printed at the foot of the form was a paragraph labeled “Work Completion Certificate.” As we have said, this was used to notify Drewer that the work had been completed satisfactorily upon the date the form was signed on behalf of JSC.

*65 According to the evidence, there were basically three phases of the concrete work on each dwelling: (1) Footings and foundation, (2) slabs, and (3) stoops and hearth. Drewer would issue three separate Extra Work Order forms to JSC for the three phases of the concrete work on each particular house and lot. The three forms were always issued on the same date and each form was for a different phase of the concrete work. No single form listed all three phases of the concrete work.

Once the forms were received, JSC, or its subcontractor, would proceed with the work, phase by phase, as the house reached the stage of construction called for by each work order. As the phase of the work described in each form was completed, JSC would submit the dated Work Completion Certificate to Drewer. Payment from Drewer for that phase of work would be due JSC at the time each certificate was submitted.

A portion of the Work Completion Certificate deals with the subject of mechanics’ liens. It purports to waive any rights to file mechanics’ liens only “upon receipt of payment from Drewer Development.”

Keeping in mind that the initial issue we must decide is just what comprised the contract between the parties, we shall summarize the commissioner’s finding on that question, which was confirmed by the chancellor. The commissioner stated that, although the Contractor Base Agreement outlined the general terms and conditions of the work that would be required by JSC, “the agreement was nonexclusive with DDC reserving the right to contract with any other party for the work described. Only when DDC issued work orders to JSC and JSC accepted the orders by supplying the materials and labor was a contractual offer and acceptance established.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Allied Terminals, Inc. v. HMT, Inc.
89 Va. Cir. 206 (Chesapeake County Circuit Court, 2014)
In re Cunningham
478 B.R. 346 (N.D. Indiana, 2012)
Ricky I. Parsons v. Diana L. Parsons
Court of Appeals of Virginia, 2012
Uss v. Virginia Retirement System
82 Va. Cir. 398 (Fairfax County Circuit Court, 2011)
Dallan Construction, Inc. v. Super Structures General Contractors, Inc.
79 Va. Cir. 11 (Hanover County Circuit Court, 2009)
Louis James Clemente v. Ellen Louise Clemente
Court of Appeals of Virginia, 2006
Shahnaz M. Ahmed v. Syed M. Ahmed
Court of Appeals of Virginia, 2004
Syed M. Ahmed v. Shahnaz A. Ahmed
Court of Appeals of Virginia, 2004
Andrew Thomas McGarry v. Beverly Brandon McGarry
Court of Appeals of Virginia, 2002
Ryan Incorporated v. Toll Brothers Inc
43 F. App'x 601 (Fourth Circuit, 2002)
Thomas Joseph Goudreau v. Katherine Lynn Goudreau
Court of Appeals of Virginia, 2001
Kerr v. T.A. McMullen Consultants, Inc.
10 F. App'x 190 (Fourth Circuit, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
523 S.E.2d 496, 259 Va. 60, 2000 Va. LEXIS 20, Counsel Stack Legal Research, https://law.counselstack.com/opinion/first-american-bank-v-jsc-concrete-construction-inc-va-2000.