Earth Pipeline Services, Inc. v. Columbia Gas Transmission, LLC

CourtUnited States Bankruptcy Court, D. Delaware
DecidedDecember 1, 2020
Docket19-50274
StatusUnknown

This text of Earth Pipeline Services, Inc. v. Columbia Gas Transmission, LLC (Earth Pipeline Services, Inc. v. Columbia Gas Transmission, LLC) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, D. Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Earth Pipeline Services, Inc. v. Columbia Gas Transmission, LLC, (Del. 2020).

Opinion

IN THE UNITED STATES BANKRUPTCY COURT FOR THE DISTRICT OF DELAWARE

In re ) Chapter 11 ) Case No. 18-12378 (CSS) WELDED CONSTRUCTION, L.P. et al., ) ) (Jointly Administered) Debtors. ) EARTH PIPELINE SEREVICES, INC. ) Plaintiff, ) v. ) Adv. Pro. No.: 19-50274 (CSS) ) Adv. Pro. No.: 19-50275 (CSS) COLUMBIA GAS TRANSMISSION, ) LLC, and WELDED CONSTRUCTION, ) (Consolidated) L.P., ) Defendant. ) COLUMBIA GAS TRANSMISSION, ) LLC, ) Counter-claimant, ) v. ) ) EARTH PIPELINE SERVICES, INC, ) ) Counter-defendant. )

OPINION

ARCHER & GREINER, P.C. COHEN, SEGLIAS, PALLAS David W. Carickhoff GREENHALL, & FURMAN, P.C. 300 Delaware Avenue Stephen A. Venzie Suite 1100 Sally J. Daugherty Wilmington, DE 19801 500 Delaware Avenue -and- Suite 730 MAYER BROWN LLP Wilmington, DE 19801 Charles S. Kelley Andrew C. Elkhoury Counsel for Earth Pipeline 700 Louisiana Street Services, Inc. Suite 3400 Houston, TX 77002

Counsel for Columbia Gas Transmission, LLC Dated: December 1, 2020 DJppecg Sontchi, C.J.

INTRODUCTION! Before the Court is Columbia Gas’s Motion to Dismiss with prejudice Earth’s Amended Complaint. Columbia Gas owned the Property and the Project. Welded, a nominal defendant, entered into a contract with Columbia Gas to complete the Project on the Property. Welded then subcontracted Earth to complete work on the Project. Earth, after completing work on the Project, submitted an invoice to Welded for $7,342,519.62 but only received $3,692,219.20 leaving unpaid $3,650,300.42. As a result, Earth filed the above captioned Amended Complaint seeking recovery of $3,650,300.42 from Columbia Gas under three theories: Count 1—for the enforcement of the Liens; Count 2—for recovery under the theory of unjust enrichment; or Count 3— for recovery under the theory of quantum meirut. In response, Columbia Gas filed the Motion to Dismiss with prejudice Earth's Amended Complaint because, (1) Earth either (i) waived its right to file or record a mechanic’s lien under the terms of the Subcontract or (ii) owes Columbia Gas nothing under West Virginia law and the terms of the Subcontract; and (2) Earth cannot seek quasi-contractual claims where the claim is based on recovery under the express terms of a contract — the Subcontract.

1 Capitalized terms used herein shall have the meaning ascribed to them infra.

For the reasons set forth below, the Court will grant the motion to dismiss, without prejudice on Counts 2 and 3 for unjust enrichment and quantum meirut, and with

prejudice on Count 1 for the enforcement of liens. JURISDICTION & VENUE The Court has jurisdiction over this matter, pursuant to 28 U.S.C. §§ 157 and 1334. Venue is proper pursuant to 28 U.S.C. §§ 1408 and 1409. Earth does not consent to the Court’s entry of a final order on this matter.2 STATEMENT OF FACTS A. Parties Plaintiff Earth Pipeline Services, Inc. (“Earth”) is a Wyoming corporation with its principal place of business in Washington, Pennsylvania.3 Columbia Gas Transmission, LLC (“Columbia Gas”) is a Delaware limited liability company, with a principal place of

business in Houston, Texas.4 Welded Constructed, L.P. (“Welded”) is a Delaware limited partnership, with a principal place of business in Perrysburg, Ohio.5 B. Events In early 2018, Columbia Gas hired Welded as a general contractor to construct Spread 1 of the Mountaineer Xpress Pipeline Project (the “Project”) on property owned

2 Plaintiff Earth Pipeline Services, Inc.’s Response and Brief in Opposition to Defendant Columbia Gas Transmission’s Motion to Dismiss Plaintiff Earth Pipeline Services, Inc.’s Amended Complaint (the “Response”), Adv. Proc. No. 19-50274 [D.I. 36], at 1. 3 Amended Complaint, Adv. Proc. No. 19-50274 [D.I. 23], at ¶ 1. 4 Id., at ¶ 2. 5 Id., at ¶ 3. by Columbia Gas in Marshall and Wetzel counties, West Virginia (the “Property”).6 On or about March 20, 2018, Welded entered into a written subcontract with Earth (“the

Subcontract”).7 The Subcontract provided that, among other things, Earth would perform mechanical clearing of the pipeline construction right-of-way and all extra work spaces and access roads for the Project on the Property.8 On or about June 22, 2018, Welded, at the direction of Columbia Gas, informed Earth that it was terminating the Subcontract.9 Earth invoiced Welded for $7,342,519.62, reflecting labor performed and materials used in furtherance of the Subcontract.10 To

date, Welded only paid Earth $3,692,219.20 for its work.11 On September 12, 2018, Earth filed two separate notices of mechanic’s liens, pursuant to West Virginia Code § 38-2-1, et seq., (the “Lien Law”). One notice was filed in Marshall County, West Virginia, and another in Wetzel County, West Virginia (together, the “Notices” or “Liens”).12 The Notices were each recorded in the amount of $3,650,300.42—which reflects the difference

between the invoice for $7,342,519.62 and the $3,692,219.20 paid.13

6 Id., at ¶ 5. 7 Id., at ¶ 8. 8 Id., at Ex. 1, page 2 of 25. 9 Id., at ¶ 13. 10 Id., at ¶ 16. 11 Id., at ¶ 18. 12 Id., at ¶ 20; filed with the Clerk of the Marshall County Commission, at Instrument No. 1445514, Mechanic’s Lien Book 11 at page 574; filed with the Clerk of the Wetzel County Commission, at Instrument No. 257004, Mechanic’s Lien Book 6 at page 872 13 Id. C. Subcontract The Subcontract contains two provisions relevant to liens. First, the following clause (the “Lien Clause”):

Subcontractor shall cause any Lien which may be filed or recorded against the Work, the Facility, the Work Site or any lands or property of Company to be released and discharged forthwith at the cost and expense of Subcontractor . . . No amounts are payable by Contractor to Subcontractor so long as a Lien remains registered against the Work, the Facilities, the Work Site or any lands or property of Contractor, arising out of the Work.14

Second, a clause from the indemnity section (the “SLI Clause”) stating:

Subcontractor shall defend, indemnify and hold harmless Contractor . . . from and against any and all Claims of whatever nature . . . which may be brought against Contractor Indemnified Parties . . . to the extent caused by: *** (F) all Liens and claims made or liability incurred by Contractor on account of the Work performed or materials supplied by any Subcontractor, including fees and expenses of legal counsel, but only to the extent Subcontractor has been paid by Contract [sic] all amounts due under this Agreement[.]15

D. Procedural Background On October 22, 2018, Welded filed a voluntary petition for relief under Chapter 11 of the Bankruptcy Code with this Court.16 On or about March 8, 2019, Earth filed complaints to foreclose the Liens in the circuit courts of Marshall and Wetzel counties,

14 Id., at Ex. 1, pages 15–16 of 25 (Ex. G to the Subcontract). 15 Amended Complaint, at Ex. 1, page 17 of 25 (Ex. G to the Subcontract) (emphasis added). 16 Id., at ¶ 21. and named Columbia Gas as a defendant (the “Foreclosure Complaints”).17 Columbia Gas then moved for removal of the Foreclosure Complaints.18 On or about April 10, 2019,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Mayer v. Belichick
605 F.3d 223 (Third Circuit, 2010)
Warren General Hospital v. Amgen Inc.
643 F.3d 77 (Third Circuit, 2011)
Usa Machinery Corporation v. Csc, Ltd.
184 F.3d 257 (Third Circuit, 1999)
Pilcher v. Commonwealth
583 S.E.2d 70 (Court of Appeals of Virginia, 2003)
United Dispatch, Inc. v. E. J. Albrecht Co.
62 S.E.2d 289 (West Virginia Supreme Court, 1950)
Bauer Enterprises, Inc. v. Frye
382 S.E.2d 71 (West Virginia Supreme Court, 1989)
McMerit Construction Co. v. Knightsbridge Development Co.
367 S.E.2d 512 (Supreme Court of Virginia, 1988)
State Ex Rel. Frazier & Oxley, L.C. v. Cummings
569 S.E.2d 796 (West Virginia Supreme Court, 2002)
Eastern Steel Constructors, Inc. v. City of Salem
549 S.E.2d 266 (West Virginia Supreme Court, 2001)
Reddy v. Community Health Foundation of Man
298 S.E.2d 906 (West Virginia Supreme Court, 1982)
Robinson v. Cabell Huntington Hospital, Inc.
498 S.E.2d 27 (West Virginia Supreme Court, 1997)
Ison v. Daniel Crisp Corp.
122 S.E.2d 553 (West Virginia Supreme Court, 1961)
Bethlehem Mines Corporation v. Haden
172 S.E.2d 126 (West Virginia Supreme Court, 1969)
Wellington Power Corp. v. CNA Surety Corp.
614 S.E.2d 680 (West Virginia Supreme Court, 2005)
Elmore v. State Farm Mutual Automobile Insurance
504 S.E.2d 893 (West Virginia Supreme Court, 1998)
Haynes v. DaimlerChrysler Corp.
720 S.E.2d 564 (West Virginia Supreme Court, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Earth Pipeline Services, Inc. v. Columbia Gas Transmission, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/earth-pipeline-services-inc-v-columbia-gas-transmission-llc-deb-2020.