Baker Sand & Gravel Co. v. Rogers Plumbing & Heating Co.

154 So. 591, 228 Ala. 612, 102 A.L.R. 346, 1934 Ala. LEXIS 53
CourtSupreme Court of Alabama
DecidedMarch 29, 1934
Docket6 Div. 406.
StatusPublished
Cited by26 cases

This text of 154 So. 591 (Baker Sand & Gravel Co. v. Rogers Plumbing & Heating Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baker Sand & Gravel Co. v. Rogers Plumbing & Heating Co., 154 So. 591, 228 Ala. 612, 102 A.L.R. 346, 1934 Ala. LEXIS 53 (Ala. 1934).

Opinion

*615 BOULDIN, Justice.

The question of first importance is that of priority between a mortgagee of real estate and materialmen furnishing materials to an original contractor for the erection of a building thereon. The mortgage was executed and recorded prior to the beginning of work on the building.

In such ease by express statute, the mortgage has the superior lien on the land, but as to the building liens under the mechanic’s lien law are superior to all other liens, mortgages, or incumbrances. Oode, § 8833.

In this case the mortgagee claims priority as to the building.

The material facts touching this issue may be briefly summarized thus:

The owner of a lot or parcel of land in the city of Tuscaloosa entered into a contract with an original contractor to erect an apartment house thereon. The contractor undertook to furnish all the labor and material.

The contract price was the actual cost of labor and material, plus a fee of $4,000 to the. contractor, total cost not to exceed $45,000.

Payments were to be made to the contractor on estimates of the architect as the work progressed.

To begin the enterprise the owner negotiated a construction loan of $17,500, executing a mortgage therefor.

The contractor, in aid of the procurement of such loan, entered into a separate instru: ment in writing with the mortgagee, stipulating that in consideration of such loan to the owner, the contractor subordinated his lien on the proposed building to that of such mortgage.

It appears this loan was intended to be temporary in character, it being contemplated the owner would later negotiate a large loan for needed funds to complete the enterprise, out of which this temporary loan should be paid. Accordingly, it was stipulated in the construction contract between owner and contractor that his lien on the building be subordinated to the final mortgage to the extent of $17,500. This final loan was never obtained; leading to the embarrassment presented in the record.

The contract stipulated that the cost “shall be paid by the owner to the contractor, in current funds, and only upon certificate of the architect, as follows: Four Thousand Dollars ($4,000.00) to be paid to the party of the first part on architect certificates issued along as work progresses. As soon as permanent loan has been placed by the party of the second part then the party of the second part is to pay to party of the first part 85% of all labor and material then due and is to continue to pay 85% of all labor and material every two weeks as work progresses.”

It was further stipulated: “If at any time there shall be evidence of any lien or claim for which, if' established, the owner of the said premises might become liable, and which' is chargeable to the contractor, the owner shall have the right to retain out of any payment then due or thereafter to become due an amount sufficient to completely indemnify them against such lien or claim.”

This latter provision obviously refers to contemplated liens in favor of laborers and materialmen.

By a supplemental contract of same date as the original, and part of the same transaction, it was stipulated:

Bl. Owner elected to furnish all necessary brick to be delivered at building site at Tuscaloosa, Ala., and also approximately 10,000 pieces of reenforced tile which material is to be used by the contractor. Owner further agree to furnish receipted bills for the purchase of this material.
“2. A warranty deed conveying the property subject to the construction loan of $17,-506.00 is to be executed by V. G. Foster and placed in escrow with the Mortgage Oo. of Alabama, upon the following terms and conditions:
“(a) If within thirty (30) days from the completion of the building, the contractor has not been paid all sums due on said contract (with the exception of $4000.00 construction fee), then the contractor shall have the election to request escrow agent to deliver said deed, in which event the delivery and acceptance of said deed shall be a full and complete discharge of the rights of the party arising out of said contract. Provided that if within 30 days the owner shall submit evidence of payment of all sums due contractor other than $4000.00 then escrow agent shall return deed to owner.”

The contractor proceeded with the erection of the building, incurring large bills with numerous concerns for materials to be used and which were used in the building. These bills are unpaid. These materialmen took all needful steps to perfect their liens, and filed separate bills to enforce the same. These *616 suits were duly consolidated, and decrees rendered for the several amounts due, and adjudging liens therefor.

The court ascertained and decreed an unpaid balance due from the owner to the contractor.

It appearing the building could not be removed from the lot without tearing it down, and virtually destroying its value, the court decreed a sale of the property as a whole, and decreed the priorities of the several lien-holders in the proceeds.

The value of the parcel of land, without the building, was ascertained and decreed, and the mortgage above mentioned decreed a first lien on the proceeds of sale to that amount.

It was further decreed that the mortgage lien on the building was superior to material-men’s liens who had dealt with and furnished materials to the contractor; and, accordingly, it was decreed that the balance of the mortgage debt be given priority of payment out of the proceeds of the building, subordinating the decrees for materials.

The trial court, in his ruling, expressed the view that liens of such materialmen are by way of subrogation to the lien of the contractor, and his contract with the mortgagee subordinating his lien to that of the mortgage also subordinated those of the materialmen.

The decree is not based on any finding of actual notice to materialmen of the subordination agreement between mortgagee and contractor. Materialmen here argue the evidence shows a want of such notice, and we do not understand this to be controverted.

Such agreement was recorded long after work was begun on the building. We have no statute in Alabama providing for the record of construction contracts as in some states. The only record of mechanics’, liens provided by law is a record of statements of claims of lienors to be filed and recorded in the office of the judge of probate under Code, § 8836. The record of such subordination agreement, even if prior to the beginning of work on the building, cannot operate, as constructive notice.

Dealing with the question of materialmen’s liens as derivative in character, and by way of subrogation to the contractor’s lien, the statutes themselves, as well as our decisions, fully negative any such concept.

The statutes create a direct, separate, and independent lien in favor of each class of persons named, each to be kept alive and enforced for himself in his own right. No failure of the contractor to follow up or establish his lien, nor any estoppel which would prevent him from so doing, can defeat other lienors.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Boyington v. Bryan
174 So. 3d 347 (Court of Civil Appeals of Alabama, 2014)
Simmons First Bank v. Bob Callahan Services, Inc.
13 S.W.3d 570 (Supreme Court of Arkansas, 2000)
Bailey Mortg. Co. v. Gobble-Fite Lumber Co.
565 So. 2d 138 (Supreme Court of Alabama, 1990)
Bettinger v. Stephens Wholesale Building Supply Co.
487 So. 2d 1369 (Court of Civil Appeals of Alabama, 1986)
Burgess Min. & Const. Corp. v. Lees
440 So. 2d 321 (Supreme Court of Alabama, 1983)
Almeida v. Almeida
669 P.2d 174 (Hawaii Intermediate Court of Appeals, 1983)
Wohlschlegel v. Uhlmann-Kihei, Inc.
662 P.2d 505 (Hawaii Intermediate Court of Appeals, 1983)
Schrader v. Benton
635 P.2d 562 (Hawaii Intermediate Court of Appeals, 1981)
Abell-Howe Co. v. INDUSTRIAL DEVELOPMENT BD., ETC.
392 So. 2d 221 (Court of Civil Appeals of Alabama, 1980)
VNB Mortgage Corp. v. Lone Star Industries, Inc.
209 S.E.2d 909 (Supreme Court of Virginia, 1974)
Empire Home Loans, Inc. v. WC BRADLEY COMPANY
241 So. 2d 317 (Supreme Court of Alabama, 1970)
Pacific Insurance Company v. Wilbanks
214 So. 2d 279 (Supreme Court of Alabama, 1968)
Fleming v. Napili Kai, Ltd.
430 P.2d 316 (Hawaii Supreme Court, 1967)
Rabren v. Andalusia Lumber and Supply Company
188 So. 2d 279 (Supreme Court of Alabama, 1966)
Sylvester v. Strickland
177 So. 2d 905 (Supreme Court of Alabama, 1965)
East Gadsden Bank v. Bagwell
143 So. 2d 438 (Supreme Court of Alabama, 1962)
Mazel v. Bain
133 So. 2d 44 (Supreme Court of Alabama, 1961)
First National Exchange Bank v. Hughson
74 S.E.2d 797 (Supreme Court of Virginia, 1953)
Bull v. Armstrong
48 So. 2d 467 (Supreme Court of Alabama, 1950)
Harden v. Wood Lumber Co.
178 So. 540 (Supreme Court of Alabama, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
154 So. 591, 228 Ala. 612, 102 A.L.R. 346, 1934 Ala. LEXIS 53, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baker-sand-gravel-co-v-rogers-plumbing-heating-co-ala-1934.