McDonald Stone Co. v. Stern & Marx

142 Ala. 506
CourtSupreme Court of Alabama
DecidedNovember 15, 1904
StatusPublished
Cited by10 cases

This text of 142 Ala. 506 (McDonald Stone Co. v. Stern & Marx) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McDonald Stone Co. v. Stern & Marx, 142 Ala. 506 (Ala. 1904).

Opinion

TYSON, J.

It appears from the cross-bill of the owner, The Mobile Lodge No. 108 Benevolent and Protective Order of Elks, to which the demurrer was interposed by The D. J. McDonald Stone Company, that after the McDonald Company had given the owner notice that it claimed a lien as a sub-contractor for the labor and materials furnished the contractor -as required by § 2731 of the Code, that the owner advanced to the contractor, as a part of the contract price, a sum of money [509]*509more tlian enough to pay off and discharge the claim of The McDonald Company. This money was advanced, it is alleged, to pay for necessary materials and labor to complete the building which the contractor, under the contract, was hound to furnish and was so appropriated.

After this advance was made, other material men and subcontractors gave notice that they claimed liens, but the amount which became due to the contractor, by reason of the advance to him was wholly insufficient to pay all the lienors.

It is not averred in the cross-bill that the contract contained stipulations authorizing the -advance of the money to the contractor. The point made by the demurrer is that The McDonald Stone Company had a lien upon the money paid or advanced to the contractor.

It is first contended by counsel for the Mobile Lodge, the owner, that under the facts alleged, it had the right to make the payment or advancement because there was, at the time of the service of the notice, nothing due the contractor — no such sum was then due to him payable presently or in the future for the reason that he had not then earned it by completing the building. This contention, if we understand it correctly, is predicated upon the proposition that the statutes only give a lien to material men and subcontractors upon any unpaid balance due the contractor by the owner at the time of the service of the notice.

The logic of this contention would lead to the result that if on the day the notice is served there be nothing actually due the contractor, but on the next day or the next week thereafter, there becomes due to him on the contract a sum of money, the material men or subcontractor would have no lien upon it as an unpaid balance and could not subject it.

In the recent case of Alabama & Georgia Lumber Company v. Tisdale, 139 Ala. 250, Ave passed upon this question. In that case Tisdale, the owner, after notice that plaintiff claimed a. lien, made a payment to the contractor. We held that he was liable, and among other things said that “the unpaid balance as used in the statutes means any sum of money which is due Avhen the notice [510]*510is given or that may subsequently become due under the contract to the contractor.” Indeed, that case is decisive of the question here under consideration, unless it can be said that there is a difference between a payment and an advance to the contractor.

That what was there said is the correct construction of the statutés we need, it seems to us, only quote that provision of § 2731 of the Code, providing for notice to the owner, which is in this language, viz; “after such notice, any unpaid balance in the hands of the owner or proprietor shall be held subject to such lien.” But it may be said that Greene v. Robinson, 110 Ala. 507, is opposed to this conclusion. Indeed, that case seems to be relied on as supporting the contention here made. It is true the opinion contains the statement that “the law is very clear that it is only the unpaid balance in the hands of the owner or proprietor at the time of notice to him, that can be made subject to plaintiff’s claim and for which a lien can be enforced.”

But the question here presented and the one presented in Alabama & Georgia Lumber Company v. Tisdale, were not involved in that case, as will be readily seen by a reference to the facts and the exception reserved to the ruling of the trial court brought here for review. In that case the plaintiff’s notice was given on the 19th day of November, 1894. On the trial the defendant, owner, offered to prove by the contractor that he owed him nothing on account of the contract after the 16th day of November, 1904. The court refused to permit this to be done. And this was the question that this court was called upon to decide and it was with respect to that question that the language quoted above was employed.

The McDonald Company having a lien, under the statutes, upon any unpaid balance that may become due under the contract to the contractor, could the owner defeat or impair that lien by advancing money upon the [511]*511contract to the contractor, without the consent of the lienor and when the contract makes no provision for it? This question must be answered in the negative unless there is some provision to be found in the statutes which authorizes the owner to make such an advance. For clearly, in the absence of some statutory provision, if the contractor ever earned this money by the performance of the contract, which the cross-bill shows he did, there is no way by which it could be discharged of the lien except by the consent of the lienor. To hold otherwise would render it impossible to enforce the statute. Indeed, to permit an owner to advance to a contractor a part of the contract price and to thus defeat the lien of a. material man or subcontractor, would confer upon them‘the power, in every instance, to destroy the purposes of the statutes. If payment- may be anticipated and liens destroyed in this way, the statutes may as Well be abolished. Where the contractor goes forward with performance under the contract, as here, an advancement of a part of the contract price amounts to no more than a payment to him on account of that performance and can have no greater effect upon the rights of a lienor than a payment to him after he has earned it? In this respect the case does not differ from that of a person upon whom a. garnishment is served against the estate of another with whom he may have a contract. Unquestionably, if the party .with whom the garnishee has a. contract, declines further performance he may set-off ¡against his liability the cost of completing the work, but if the original contractor performs the contract, the garnishee could not escape liability for the full amount of the money which he had advanced or paid after the service of the writ of garnishment. And the mere fact that he might have been damaged by reason of the failure of the defendant to perform his contract, and, therefore, it was desirable to keep the contractor at work, cannot affect the lien created and acquired by the service of the writ.

The case of Mobile Street Railway v. Turner, 491 Ala. 213, is relied upon as establishing the right of the owner [512]*512in' this case to make the payment to the contractor under the circumstances averred in the cross-bill.

In that case, which was a garnishment, the contract contained an express stipulation conferring upon the owner the right to provide, (upon a certain contingency which the uncontradicted answer of the garnishee disclosed had arisen) at the expense of the contractor, all materials and labor necessary to a completion of the building, which expense was to be deducted from the contract price to be paid the contractor. It clearly has no application here.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Valley Joist, Inc. v. CVS Corp.
954 So. 2d 1115 (Court of Civil Appeals of Alabama, 2006)
Baker Sand & Gravel Co. v. Rogers Plumbing & Heating Co.
154 So. 591 (Supreme Court of Alabama, 1934)
David Lupton's Sons Const. Co. v. Hugger Bros. Const.
148 So. 610 (Supreme Court of Alabama, 1933)
Standard Sanitary Mfg. Co. v. Aird
129 So. 285 (Supreme Court of Alabama, 1930)
Anniston Lumber & Mfg. Co. v. Kirkland
124 So. 207 (Supreme Court of Alabama, 1929)
Richardson Lumber Co. v. Howell
122 So. 343 (Supreme Court of Alabama, 1929)
Baldwin v. Constantine
108 So. 345 (Supreme Court of Alabama, 1926)
Dixie Lumber Co. v. Young
82 So. 129 (Supreme Court of Alabama, 1919)
Dothan Grocery Co. v. H. L. Wofford Son
76 So. 432 (Supreme Court of Alabama, 1917)
Cranford Mercantile Co. v. Wells
70 So. 666 (Supreme Court of Alabama, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
142 Ala. 506, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcdonald-stone-co-v-stern-marx-ala-1904.