Standard Sanitary Mfg. Co. v. Aird

129 So. 285, 221 Ala. 520, 1930 Ala. LEXIS 342
CourtSupreme Court of Alabama
DecidedMay 29, 1930
Docket6 Div. 343.
StatusPublished
Cited by14 cases

This text of 129 So. 285 (Standard Sanitary Mfg. Co. v. Aird) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Standard Sanitary Mfg. Co. v. Aird, 129 So. 285, 221 Ala. 520, 1930 Ala. LEXIS 342 (Ala. 1930).

Opinions

SAYRE, J.

While appellee held a second mortgage on a certain lot or parcel of land, the owner, Tillman, contracted with Aldridge for the erection of an apartment house thereon. Pending the completion of the building, appellee filed his bill to foreclose his mortgage, making sundry subcontractors and materialmen, among others, parties defendant. These appellants, subcontractors and materialmen, came in, claiming liens on the property. The final decree denied the liens so claimed, and the subcontractors and materialmen have appealed.

The consolidation of claims and causes brought about by the procedure followed in this cause was proper. Ex parte Brown, 58 Ala. 541; Hagan v. Riddle Co., 209 Ala. 606, 96 So. 863.

Appellants, proceeding according to the provisions of section 8840 of the Code, sought to have liens on the property declared in their favor for the unpaid balance in the hands of the owner at the time of the notices served on him. Appellee purchased the property pend-' ing these proceedings and has undertaken to defend against the liens claimed.

Appellants gave notice as the statute prescribes, and there was then in the hands of the owner a considerable sum; but the contractor had given orders on the owner for payments to the architect whom he had employed and to a lumber company which had furnished materials and credit for use in and about the buildings, which had been accepted by the owner, payable in the future, and these orders, if allowed, will absorb the balance which the court decreed to them rather than to appellants. These parties, thus favored, had not invoked the aid of the statute; had not given the notice prescribed by section 8840 of the Code.

The decree (July 25, 1929) appears to have followed the law as stated in Dixie Lumber Co. v. Young, 203 Ala. 115, 82 So. 129 (May 1, 1919), in which it was held that where a materialman furnished materials to a contractor without notifying the owner at the time that they were furnished -in compliance with Code 1923, § 8832 (Code 1907, § 4754), no lien was acquired for any unpaid balance due by them to the contractor until notice was given. But the law as stated in the last-named case was materially changed in Le Grand v. Hubbard, 216 Ala. 164, 112 So. 826, 828 (May 5, 1927), where it was held that section 8840 of the Code of 1923 operated to give to subcontractors and materialmen potential liens, which, on notice to the owner, date back to the commencement of the work, as against liens claimed by outsiders or subcontractors and materialmen who have not invoked the aid of the statute, and thereupon become fixed, subject only to pro rata distribution of the amount in the hands of the owners among those entitled to such liens. Code, § 8854.

The record does not' indicate that the contractor’s orders upon the owner have been paid. Appellee’s suggestion is that the payment or nonpayment of these orders is not material to the issue in this case. However that may be, we prefer to consider the ease made by the record.

*522 Appellee quotes from the opinion in Le Grand v. Hubbard as follows: “We are not now dealing with the rights of one who has, by act of the owner and contractor, become entitled to the money theretofore due the contractor.” We continue the quotation as follows: “We would merely note that under section 8861 the assignee is ‘invested with all the rights of the original holder of the lien.’ This implies the assignee has no higher standing than the original lienholder, and takes his place in the line at the pay window.”

We quote section 8861: “Any claim for which a lien is provided in this article [the article providing liens for mechanics and materialmen.—§§ 8832-8S62] may be assigned; and the assignee shall be thereby invested with all the rights of the original holder of the lien, and be entitled to all his remedies to enforce them.”

And we now add: There is no denial of appellee’s right to retain the share which would have been due to his equitable assignors, that is, the parties to whom he promised payments upon a pro rata distribution of the sum due upon the contract at the date of the notice or thereafter (McDonald Stone Co. v. Stern, 142 Ala. 506, 38 So. 643), as provided by section S854. The statement now is that appellee’s assignors, by taking assignments of the contractor’s orders upon the owner, secured to themselves or their assignee no higher or better right than other subcontractors or materialmen whose claims, then, or now after compliance with' the statute, remain unsatisfied. As the court observed in Alabama & Georgia Lumber Co. v. Tisdale, 139 Ala. 250, 36 So. 618, 620, in view of a closely related though not identical status of conflicting claims, “Such construction [as appellee .here contends for] would put it in the power of the owner and contractor to practically destroy the lien of the employee and material-men.” That construction was reprobated by the court in that case. In the circumstances of this case, appellee’s construction of the statute would permit the owner and contractor to provide for the payment of some subcontractors and materialmen to the exclu-sion of others, and that has been the effect according to the decree now under review. But in Le Grand v. Hubbard, supra, there was a writ of garnishment against the owner. The lien of the garnishment attached prior to the giving- of notice to the owner required of persons furnishing materials or labor to the contractor. The materialmen were decreed priority in payment. The decree was affirmed. In the course of its opinion the court said: “This section [8854] clearly negatives any idea that liens date from the giving of notice to the owner as between the lienholders. It will be readily seen this section cannot have .effect if garnishment liens may intervene between the claimants under this see-lion. Laborers, for example, cannot give notice until work is done and wages accrued.” The principle of that case applies here. Appellee, who stands in the shoes of the owner, claims priority over subcontractors and materialmen, who have given the statutory notice, for the claims of other subcontractors and materialmen, who have not given the notice, but, in lieu thereof, rely upon the fact that the contractor has given them orders on the owner, who has accepted such orders to ue paid, for aught appearing in this record, in the future. If owners and contractors shall be allowed thus to bring about inequalities between subcontractors and materialmen having-claims of equal merit, then, to quote McDonald Stone Co. v. Stern, 142 Ala. 511, 38 So. 643, 645, “If payment may be anticipated and liens destroyed in this way, the statutes [section 8854, providing for pro rata distribution among lienholders, and related sections] may as well be abolished.”

In view of the opinion filed by FOSTER, L, the following further statement is considered to be necessary:

In Lavergne v. Evans Bros. Construction Co., 166 Ala. 289, 52 So. 318, 319, the following construction of the presently relevant parts of the statute was accepted by the court as correctly stating the legislative purpose: “Under the statute the lien of mechanic and materialman attaches from the commencement of the building or improvement, subject, however, to be defeated and lost if the claim be not verified and filed with the judge of probate within the time prescribed,” citing Welch v. Porter, 63 Ala.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Justice v. ARAB LUMBER AND SUPPLY, INC.
533 So. 2d 538 (Supreme Court of Alabama, 1988)
Scott Paper Co. v. Adair Truck & Equipment Co.
542 F.2d 1257 (Fifth Circuit, 1976)
Huffman-East Development Corp. v. Summers Electric Supply Co.
263 So. 2d 677 (Supreme Court of Alabama, 1972)
Pacific Insurance Company v. Wilbanks
214 So. 2d 279 (Supreme Court of Alabama, 1968)
Friday Lumber Company v. Johnston
180 So. 2d 259 (Supreme Court of Alabama, 1965)
Peavy Lumber Company v. Murchison
130 So. 2d 338 (Supreme Court of Alabama, 1961)
Adams Supply Co. v. United States Fidelity & Guaranty Co.
111 So. 2d 906 (Supreme Court of Alabama, 1959)
Porter v. Porter
63 So. 2d 804 (Supreme Court of Alabama, 1953)
Hollywood, Inc. v. Clark
15 So. 2d 175 (Supreme Court of Florida, 1943)
Ex Parte Ashton
165 So. 773 (Supreme Court of Alabama, 1936)
Baker Sand & Gravel Co. v. Rogers Plumbing & Heating Co.
154 So. 591 (Supreme Court of Alabama, 1934)
David Lupton's Sons Const. Co. v. Hugger Bros. Const.
148 So. 610 (Supreme Court of Alabama, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
129 So. 285, 221 Ala. 520, 1930 Ala. LEXIS 342, Counsel Stack Legal Research, https://law.counselstack.com/opinion/standard-sanitary-mfg-co-v-aird-ala-1930.