Walker v. Collins Construction Co.

236 N.W. 334, 121 Neb. 157, 1931 Neb. LEXIS 118
CourtNebraska Supreme Court
DecidedApril 30, 1931
DocketNo. 27695
StatusPublished
Cited by24 cases

This text of 236 N.W. 334 (Walker v. Collins Construction Co.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Walker v. Collins Construction Co., 236 N.W. 334, 121 Neb. 157, 1931 Neb. LEXIS 118 (Neb. 1931).

Opinion

Good, J.

This is an action for foreclosure of mechanics’ liens. Four plaintiffs, each a subcontractor claiming a lien, joined in one petition, each seeking foreclosure of his respective lien. Another lien claimant was made defendant and filed a cross-petition, seeking foreclosure of its lien. Defendant Swift & Company was the owner of the premises. Collins Construction Company was the general contractor, and, while designated in the petition as a defendant, it was not served and made no appearance in the action. Swift & Company filed a demurrer to the petition, on the ground of misjoinder of causes of action. The demurrer was overruled, and defendant answered over, joining issues with the plaintiffs and cross-petitioner. After hearing, the court found for the plaintiffs and cross-petitioner, [159]*159and awarded liens as follows: Edward Walker, $2,348.25; Waltemath Lumber & Coal Company, $20,522.36; C. H. Backers, $2,570.23; Simon Brothers, $501.52; Higbee & Keyes, cross-petitioner, $64.95. Swift & Company, owner of the premises, has appealed.

The first error assigned is that the court erred in overruling the demurrer to the petition. It is clear that there was a misjoinder of causes of action, and that the demurrer should have been sustained. Defendant did not stand upon its demurrer, but elected to answer over and joined issues with the plaintiffs and cross-petitioner. By so doing it waived any error in overruling such demurrer.

In Genho v. Jackson, 99 Neb. 1, it was held: “Where a party demurs to a petition because several causes of action are improperly joined, but answers over after an .adverse ruling thereon, and goes to trial on the merits of an issue he has elected to join, he waives the error, if any, in such ruling.”

Defendant seeks to defeat all the liens on the ground "that the contract between it and the general contractor contained the following provision: “Neither the contractor nor any subcontractor, materialman, nor any other person, shall file or maintain a lien, commonly called a mechanic’s lien, for materials delivered for use in, or work done in the performance of this contract, and the right to maintain such lien by any or all of the above named parties is hereby expressly waived, except in the event of the failure or refusal of the owner to pay the amount called for by any certificate of the architect, within three days of the date of its tender to the owner for payment. Then, and in such case only, shall any of the above named parties have the right to file and maintain a mechanic’s lien.” It is the contention of the defendant that each subcontractor is required to ascertain and know the terms of the contract between the owner and the general contractor and is bound "thereby.

Some jurisdictions hold to the rule contended for by defendant. We think the better rule, and the one sustained hy the great weight of authority, is that a stipulation [160]*160against liens in a contract between the owner and the contractor will not deprive the subcontractor of the right to a lien, unless the latter assents or agrees to the stipulation. 40 C. J. 148.

Another objection lodged by defendant against all of the decrees is that the trial court awarded each lienor interest from the date of filing his lien to the date of the entry of judgment. It may be that where a subcontractor performs a stipulated part of the work, or furnishes a stipulated part of the material, for the erection of a building for a gross sum, as soon as he has completed the work or furnished all of the material, interest might then be computed from the date of the last item of work done or material furnished. That is not the case in any of the liens here involved. In each instance the lien represents an account for labor and materials furnished, running over a period of several weeks or months, and, in most instances, with payments or credits thereon. The rule applicable in such case is, as provided by statute, that, where a lien is claimed for an account for material and labor furnished for the construction of a building, in the absence of an agreement to the contrary, interest may be reckoned only from a date six months after the last item. Comp. St. 1929, sec. 45-104; Platner Lumber Co. v. Theodore, 120 Neb. 804. It appears that excessive interest was allowed on each of the claims in the instant case. Interest should have been reckoned, in each instance where the lien was properly awarded, from and after six months from the date of the last item.

From the evidence it appears that Swift' & Company entered into a contract with the Collins Construction Company for the erection of a produce house in North Platte, costing upwards of $60,000, exclusive of the heating plant. Plaintiff Walker entered into a contract with Collins Construction Company to furnish sand and gravel, to be used in the construction of the building, and also for some hauling of dirt and rubbish, the latter to fill in and level the grounds, so as .to bring them to grade about the structure. The last item of hauling was done on March 18, 1929. ■ The [161]*161lien was filed May 4, 1929. It is clear that if all of the ■work was done and material furnished pursuant to one contract the lien was filed in time. Defendant contends that the hauling was done pursuant to a separate contract, and that the last item of sand and gravel furnished was on March 4, 1929, and that the contracts cannot be ■tacked.

It is a well-settled rule that a lienor may not extend the time for filing his lien by tacking two or more contracts. The question in point is whether the material was furnished and work performed pursuant to one contract or to two separate contracts. The evidence on this point is in conflict. The circumstances, we think, tend rather to support the contention of the plaintiff Walker; While cases .of this character are for trial de novo in this court, yet, where the evidence is in conflict, the fact that the witnesses were before the trial court, that the court had a better opportunity to observe their demeanor, candor and fairness, arid was. in a better position to judge of their credibility, will be taken into consideration by this court; Under, the circumstances, we are impelled to hold that the evidence sustains the"’contention of plaintiff Walker.

With reference to the claim of Waltemath Lumber & Coal Company, defendant’s principal objection thereto is that the account contains certain items of lumber that were not used in and did not become an integral part of the building, but were used for the erection of sheds, latrines and for forms for concrete and was not consumed in such-use; also items for coal that was used to heat the building while in the course of construction and to generate steam-to operate a hoist and concrete-mixer.

It is clear that lumber was absolutely necessary in making forms for concrete, used in the construction of the building. Some was used for scaffolding. It was necessary to have a shed in which to house the material, and-as an office, for keeping the plans, specifications and records of material furnished and time of employees.; Latrines were also a necessary adjunct, and, while the-lumber was not wholly consumed in and did not constitute [162]*162an integral part of the main structure, such lumber was necessary, in order that the main structure could be erected.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Echo Group v. Tradesmen Internat.
980 N.W.2d 869 (Nebraska Supreme Court, 2022)
Lincoln Lumber Co. v. Lancaster
618 N.W.2d 676 (Nebraska Supreme Court, 2000)
Lange Industries, Inc. v. Hallam Grain Co.
507 N.W.2d 465 (Nebraska Supreme Court, 1993)
Ravenna Bank v. Custom Unlimited
391 N.W.2d 557 (Nebraska Supreme Court, 1986)
Steel Suppliers, Inc. v. Ehret, Inc.
486 A.2d 32 (Superior Court of Delaware, 1984)
O'Keefe Elevator Co. v. Second Avenue Properties, Ltd.
343 N.W.2d 54 (Nebraska Supreme Court, 1984)
VNB Mortgage Corp. v. Lone Star Industries, Inc.
209 S.E.2d 909 (Supreme Court of Virginia, 1974)
Paxton & Vierling Steel Co. v. Barmore
187 N.W.2d 590 (Nebraska Supreme Court, 1971)
Disbrow & Co. v. Peterson
287 N.W. 220 (Nebraska Supreme Court, 1939)
Bank of Earlsboro v. J. E. Crosbie, Inc.
1938 OK 48 (Supreme Court of Oklahoma, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
236 N.W. 334, 121 Neb. 157, 1931 Neb. LEXIS 118, Counsel Stack Legal Research, https://law.counselstack.com/opinion/walker-v-collins-construction-co-neb-1931.