Lincoln Lumber Co. v. Lancaster

618 N.W.2d 676, 260 Neb. 585, 2000 Neb. LEXIS 222
CourtNebraska Supreme Court
DecidedOctober 27, 2000
DocketS-99-1048
StatusPublished
Cited by24 cases

This text of 618 N.W.2d 676 (Lincoln Lumber Co. v. Lancaster) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lincoln Lumber Co. v. Lancaster, 618 N.W.2d 676, 260 Neb. 585, 2000 Neb. LEXIS 222 (Neb. 2000).

Opinion

Connolly, J.

This is an appeal from a foreclosure action on construction liens filed under the Nebraska Construction Lien Act, Neb. Rev. Stat. §§ 52-125 through 52-159 (Reissue 1998). Appellees, Lincoln Lumber Company and Kaser Painting, Inc. (Kaser), petitioned the district court for foreclosure of their construction liens filed on property purchased by appellants Lee W. Lancaster and Angela L. Lancaster.

*587 Union Bank and Trust Company (Union Bank) provided the funds for the Lancasters’ permanent financing, which were secured by a deed of trust that Union Bank concurrently assigned to appellant NationsBanc Mortgage Corporation (NationsBanc).

The district court entered judgment for both Kaser and Lincoln Lumber and determined that NationsBanc’s security interest had priority over Kaser and Lincoln Lumber only to the extent the funds had been used to pay for the disbursements made under the prior construction security interest. NationsBanc and the Lancasters appeal from that order, which was made final by the court on July 30, 1999.

Under our de novo review, we determine that the district court erred by not giving effect to a stipulation between Lincoln Lumber and NationsBanc that NationsBanc’s security interest had priority over Lincoln Lumber’s construction lien. Therefore, NationsBanc is entitled to have full priority for its security interest over the construction lien of Lincoln Lumber, and we modify the judgment accordingly.

BACKGROUND

On October 21, 1994, the Lancasters entered into a purchase agreement with Daugherty Construction, Inc. (Daugherty), for the construction of a new home at 801 Mary Court in Lincoln, Nebraska. The contract price was for $92,479. On April 7,1995, Daugherty took out a blanket construction loan for several properties from Union Bank. Union Bank filed its security interest for the loan with the register of deeds on the same day, and the amount of the security interest for 801 Mary Court was $74,800. State Title Services, Inc. (State Title), served as Union Bank’s disbursement agent for the construction improvement on the property.

Daugherty was the legal titleholder during the entire construction period until the closing with the Lancasters, and the company filed a notice of commencement on April 6, 1995, listing Daugherty as the contracting owner and titleholder. Around September 21, 1995, Daugherty filed for bankruptcy. On September 20, 1995, Kaser filed a construction lien against the property for $2,032, and on September 21, Lincoln Lumber filed a construction lien on the property for $21,498.

*588 For a time, work on the property came to a stop after the filing of the liens. The house was 75 percent complete at the time of the filings, around the end of September, and the record shows that $66,094.69 of Union’s security interest had been disbursed as of August 4, 1995.

Approximately 3 months before the Lancasters’ closing on February 22, 1996, State Title authorized subcontractors to come in and complete the home for the Lancasters.

At closing, the Lancasters paid $17,888.52, in addition to $1,934 in overages the Lancasters paid directly to subcontractors, for a total of $19,822.52. The Lancasters also obtained financing from Union Bank for $75,500, which was secured by a deed of trust and assigned to NationsBanc on the same day. Because State Title had disbursed $66,094.69 on the construction loan before the liens were filed, $9,405.31 of the permanent financing funds were paid over and above the $66,094.69.

At trial, Lincoln Lumber stipulated that NationsBanc’s security interest had priority over its construction lien. Kaser filed an answer and cross-petition to Lincoln Lumber’s petition in district court, asking that its lien be given first priority, but did not appear at trial and was not party to this stipulation.

The Lancasters argued at trial that their lien liability was limited by their status as “protected party contracting owners.” The district court found that the Lancasters were protected parties, but not contracting owners, and that NationsBanc’s lien was superior to the construction liens only to the extent that its security interest had been used to pay for the actual disbursements made under the original construction loan before the liens were filed. The district court therefore entered judgment for both Lincoln Lumber and Kaser for the full amount of their liens plus interest and ordered the property sold if the judgments were not paid. The Lancasters and NationsBanc timely appeal from that order.

ASSIGNMENTS OF ERROR

The Lancasters and NationsBanc assign that the district court erred in finding that the Lancasters were not protected party contracting owners and thereby not entitled to the protections of § 52-136(5). NationsBanc assigns that the district court erred in *589 limiting its security interest to the amount of disbursements made under the original construction loan.

STANDARD OF REVIEW

An action to foreclose a construction lien is one grounded in equity. In an appeal of an equitable action, an appellate court tries factual questions de novo on the record and reaches a conclusion independent of the findings of the trial court, provided, where credible evidence is in conflict on a material issue of fact, the appellate court considers and may give weight to the fact that the trial judge heard and observed the witnesses and accepted one version of the facts rather than another. Tilt-Up Concrete v. Star City/Federal, 255 Neb. 138, 582 N.W.2d 604 (1998); Midlands Rental & Mach. v. Christensen Ltd., 252 Neb. 806, 566 N.W.2d 115 (1997).

Statutory interpretation presents a question of law, in connection with which an appellate court has an obligation to reach an independent conclusion irrespective of the decision made by the court below. In the absence of anything to the contrary, statutory language is to be given its plain and ordinary meaning; an appellate court will not resort to interpretation to ascertain the meaning of statutory words which are plain, direct, and unambiguous. Philpot v. Aguglia, 259 Neb. 573, 611 N.W.2d 93 (2000); Ferguson v. Union Pacific RR. Co., 258 Neb. 78, 601 N.W.2d 907 (1999).

ANALYSIS

The Lancasters argue that they have no lien liability because they are protected party contracting owners and the fluids they paid at closing were used to satisfy their obligation under their purchase agreement with Daugherty.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lancaster County v. Slezak
317 Neb. 157 (Nebraska Supreme Court, 2024)
Nore Electric v. S & H Holdings
316 Neb. 197 (Nebraska Supreme Court, 2024)
Echo Group v. Tradesmen Internat.
980 N.W.2d 869 (Nebraska Supreme Court, 2022)
Archer Daniels Midland Co. v. State
Nebraska Supreme Court, 2015
Cramer v. State, Department of Motor Vehicles
240 P.3d 8 (Nevada Supreme Court, 2010)
Fru-Con Construction Corp. v. Controlled Air, Inc.
574 F.3d 527 (Eighth Circuit, 2009)
State ex rel. Jeany v. Cleveland Concrete Construction, Inc.
107 Ohio St. 3d 20 (Ohio Supreme Court, 2005)
Schmidt v. Feikert
631 N.W.2d 537 (Nebraska Court of Appeals, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
618 N.W.2d 676, 260 Neb. 585, 2000 Neb. LEXIS 222, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lincoln-lumber-co-v-lancaster-neb-2000.