This text of Fru-Con Construction Corp. v. Controlled Air (Fru-Con Construction Corp. v. Controlled Air) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fru-Con Construction Corp. v. Controlled Air, (8th Cir. 2009).

Opinion

United States Court of Appeals FOR THE EIGHTH CIRCUIT ___________

No. 08-1712 ___________

Fru-Con Construction Corporation; * Austin Maintenance & Construction, * Inc., a Delaware Corporation, doing * business as Fru-Con/Austin, JV, * * Appellants, * * Appeal from the United States v. * District Court for the * Eastern District of Missouri. Controlled Air, Inc., a Kansas * Corporation, * * Appellee. * ___________

Submitted: September 26, 2008 Filed: July 24, 2009 ___________

Before BYE, BEAM, and SHEPHERD, Circuit Judges. ___________

BEAM, Circuit Judge.

Fru-Con Construction Corporation and Austin Maintenance and Construction, Inc. (the Joint Venture) appeal the district court's application of Colorado River1 abstention to dismiss the Joint Venture's breach of contract action against Controlled Air, Inc. We reverse.

1 Colorado River Water Conservation Dist. v. United States, 424 U.S. 800 (1976). I. BACKGROUND

Nordic Biofuels of Ravenna, L.L.C., hired the Joint Venture through a real estate improvement contract as defined by Nebraska Revised Statute § 52-130 to construct an ethanol production facility in Ravenna, Nebraska. The Joint Venture engaged Controlled Air to construct the grain receiving, storage, and milling system for the facility. Their agreement contained law and forum selection clauses requiring all disputes between the parties to be governed by Missouri law and brought in Missouri state court or the federal district court for the Eastern District of Missouri. Additionally, the contract allowed the Joint Venture to terminate Controlled Air for specified reasons and to take over the work being performed after giving seventy-two hours written notice.

A dispute between Controlled Air and the Joint Venture arose and work ceased on the project. Controlled Air supplied labor and materials through January 14, 2007, and the Joint Venture assumed responsibility for the work on January 17, 2007. Pursuant to the Nebraska Construction Lien Act (NCLA), Controlled Air recorded a construction lien on March 1, 2007, for purportedly unpaid labor and materials. The recording alleged that the Joint Venture owed Controlled Air $1,496,636 for labor and materials provided through January 14. Controlled Air filed suit to foreclose the construction lien in the District Court of Buffalo County, Nebraska, on May 18, 2007. The Joint Venture, however, had previously filed a breach of contract action against Controlled Air in the United States District Court for the Eastern District of Missouri. The complaint alleged that the Joint Venture incurred damages of $1,500,000 after January 17, 2007, as a result of Controlled Air's breach of the agreement.

Believing that its Nebraska lien foreclosure action could serve to litigate the entire dispute between the parties, Controlled Air filed a motion asking the federal court to abstain from or dismiss the Joint Venture's breach of contract claim in the Eastern District of Missouri. Believing that the federal court forum could serve the

-2- same purpose, the Joint Venture filed a lien relief bond in Buffalo County, Nebraska, in accordance with the NCLA, releasing the construction lien and clearing the lien from the title to the real estate in question. A motion to dismiss or stay Controlled Air's lien foreclosure proceeding was then filed by the Joint Venture in the District Court of Buffalo County. Thus, a federal-state forum fight came to life.

A. Nebraska Proceedings

The Joint Venture's motion to dismiss the lien foreclosure proceeding alleged that by filing a surety bond issued by a company authorized to do business in Nebraska, the action was no longer in rem and the forum selection clause applied, mandating jurisdiction in Missouri. During the first hearing on this matter, the Nebraska court held that the bond was ineffective because only a person having an interest in the real estate may file a bond under Nebraska Revised Statute § 52-142, and the Joint Venture did not have an interest in the lien property.2 After the Joint Venture amended the bond, the Nebraska court again held the bond ineffective because it failed to identify where and upon whom service should be made. Finally, after the Joint Venture corrected all purported mistakes, the Nebraska court ruled on the motion to dismiss.

The Nebraska court first noted that the bond discharged the real estate lien,3 but then concluded that the foreclosure action was still in existence "in so much as the lien is transferred to the submitted surety bond." On this basis, the court held that the

2 This was error. Pursuant to Nebraska Revised Statute § 52-131(1), any person (including the Joint Venture, a prime contractor as defined in Nebraska Revised Statute § 52-127(8)), "'who furnishes services or materials pursuant to a real estate improvement contract has a construction lien[,]'" to secure the payment of his or her contract price. Tilt-Up Concrete, Inc. v. Star City/Fed., Inc., 582 N.W.2d 604, 610 (Neb. 1998) (quoting Neb. Rev. Stat. § 52-131(1)). 3 This was a correct analysis.

-3- validity of the original construction lien and the amounts that might be owed on it were still in question. Thus, the court decided that an appropriate remedy was not available in the federal forum and denied the motion to dismiss.

Although the contract action had not been asserted in Nebraska, the state court, in making its ruling, applied Nebraska Revised Statute § 25-415 to dispose of the contract's forum selection clause. That section codifies Nebraska's recognition of forum selection clauses, but provides five exceptions. While the court originally viewed three of the exceptions as potentially applicable, it ultimately determined that the Joint Venture's bond was ineffective in releasing the lien from the real estate, creating an in rem action that had to be resolved at the situs of the dispute–Nebraska. However, as earlier stated, the Nebraska court later recognized its error as to the efficacy of the bond in releasing the real estate lien and thereafter, upon reconsideration, made its dismissal decision based upon the purported "unique[ness of the lien action] to the Nebraska jurisdiction"–making a remedy not available in the federal forum. As mentioned below, the federal district court found this to be error, a matter with which we agree and discuss in greater detail in Section IIA.

B. Federal Proceedings

The District Court for the Eastern District of Missouri recognized its subject matter jurisdiction but granted Controlled Air's motion to abstain from and dismiss the Joint Venture's breach of contract action, but only after the Nebraska court retained jurisdiction over the lien foreclosure proceeding.4 The Joint Venture disputed Controlled Air's motion to abstain in the federal case on grounds that the construction lien property was no longer under the exclusive control of the Nebraska court and

4 Controlled Air's motion to dismiss for lack of personal jurisdiction and improper venue was denied. As Controlled Air did not appeal that ruling it is not before us today.

-4- because the forum selection clause mandated that jurisdiction over its contract action was properly in the federal court.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ambrosia Coal & Construction Co. v. Pagés Morales
368 F.3d 1320 (Eleventh Circuit, 2004)
Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
Brillhart v. Excess Insurance Co. of America
316 U.S. 491 (Supreme Court, 1942)
Gulf Oil Corp. v. Gilbert
330 U.S. 501 (Supreme Court, 1947)
Stewart Organization, Inc. v. Ricoh Corp.
487 U.S. 22 (Supreme Court, 1988)
Wilton v. Seven Falls Co.
515 U.S. 277 (Supreme Court, 1995)
Quackenbush v. Allstate Insurance
517 U.S. 706 (Supreme Court, 1996)
Cutter v. Wilkinson
544 U.S. 709 (Supreme Court, 2005)
United States v. City of Las Cruces
289 F.3d 1170 (Tenth Circuit, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
Fru-Con Construction Corp. v. Controlled Air, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fru-con-construction-corp-v-controlled-air-ca8-2009.