Moses H. Cone Memorial Hospital v. Mercury Construction Corp.

460 U.S. 1, 103 S. Ct. 927, 74 L. Ed. 2d 765, 1983 U.S. LEXIS 17, 51 U.S.L.W. 4156
CourtSupreme Court of the United States
DecidedFebruary 23, 1983
Docket81-1203
StatusPublished
Cited by9,476 cases

This text of 460 U.S. 1 (Moses H. Cone Memorial Hospital v. Mercury Construction Corp.) is published on Counsel Stack Legal Research, covering Supreme Court of the United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moses H. Cone Memorial Hospital v. Mercury Construction Corp., 460 U.S. 1, 103 S. Ct. 927, 74 L. Ed. 2d 765, 1983 U.S. LEXIS 17, 51 U.S.L.W. 4156 (1983).

Opinions

Justice Brennan

delivered the opinion of the Court.

This case, commenced as a petition for an order to compel arbitration under § 4 of the United States Arbitration Act of 1925 (Arbitration Act or Act), 9 U. S. C. §4, presents the question whether, in light of the policies of the Act and of our decisions in Colorado River Water Conservation District v. United States, 424 U. S. 800 (1976), and Will v. Calvert Fire Insurance Co., 437 U. S. 655 (1978), the District Court for the Middle District of North Carolina properly stayed this diversity action pending resolution of a concurrent state-court suit. The Court of Appeals for the Fourth Circuit reversed the stay. 656 F. 2d 933, rehearing denied, 664 F. 2d 936 (1981). We granted certiorari. 455 U. S. 937 (1982). We affirm.

I

Petitioner Moses H. Cone Memorial Hospital (Hospital) is located in Greensboro, N. C. Respondent Mercury Construction Corp. (Mercury), a construction contractor, has its principal place of business in Alabama. In July 1975, Mercury and the Hospital entered into a contract for the construction of additions to the Hospital building. The contract, drafted by representatives of the Hospital, included provisions for resolving disputes arising out of the contract or its breach. All disputes involving interpretation of the contract or performance of the construction work were to be referred in the first instance to J. N. Pease Associates (Architect), an independent architectural firm hired by the Hospital to design and oversee the construction project. With certain [5]*5stated exceptions,1 any dispute decided by the Architect (or not decided by it within a stated time) could be submitted by either party to binding arbitration under a broad arbitration clause in the contract:

“All claims, disputes and other matters in question arising out of, or relating to, this Contract or the breach thereof, . . . shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining unless the parties mutually agree otherwise. This agreement to arbitrate shall be specifically enforceable under the prevailing arbitration law. The award rendered by the arbitrators shall be final, and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof.” App. 29-30.

The contract also specified the time limits for arbitration demands.2

Construction on the project began in July 1975. Performance was to be completed by October 1979.3 In fact, construction was substantially completed in February 1979, and final inspections were made that June.

[6]*6• At a meeting in October 1977 (during construction), attended by representatives of Mercury, the Hospital, and the Architect, Mercury agreed, at the Architect’s request, to withhold its claims for delay and impact costs (i. e., claims for extended overhead or increase in construction costs due to delay or inaction by the Hospital) until the work was substantially completed. On this record, the Hospital does not contest the existence of this agreement, although it asserts that the Architect lacked authority to agree to a delay in presentation of claims or to entertain claims after the contract work was completed.

In January 1980, Mercury submitted to the Architect its claims for delay and impact costs. Mercury and the Architect discussed the claims over several months, substantially reducing the amount of the claims. According to the Hospital, it first learned of the existence of Mercury’s claims in April 1980; its lawyers assumed active participation in the claim procedure in May. The parties differ in their characterizations of the events of the next few months — whether there were “ongoing negotiations,” or merely an “investigation” by the Hospital. In any event, it appears from the record that lawyers for the Hospital requested additional information concerning Mercury’s claims. As a result, on August 12, 1980, Mercury gave a detailed presentation of its claims at a meeting attended by Mercury’s representatives and lawyers, the Hospital’s representatives and lawyers, and representatives of the Architect. Mercury agreed to send copies of its files to an expert hired by the Hospital, and the parties agreed to meet again on October 13.

On October 6, Mercury’s counsel telephoned the Hospital’s counsel to confirm that the scheduled meeting would go forward. The Hospital’s counsel said he would call back the next day. When he did, he informed Mercury’s counsel that the Hospital would pay nothing on Mercury’s claim. He also said that the Hospital intended to file a declaratory judgment action in North Carolina state court.

[7]*7True to its word, the Hospital filed an action on the morning of October 8 in the Superior Court of Guilford County, N. C., naming Mercury and the Architect as defendants. The complaint alleged that Mercury’s claim was without factual or legal basis and that it was barred by the statute of limitations. It alleged that Mercury had lost any right to arbitration under the contract due to waiver, laches, estoppel, and failure to make a timely demand for arbitration. The complaint also alleged various delinquencies on the part of the Architect. As relief, the Hospital sought a declaration that there was no right to arbitration; a stay of arbitration; a declaration that the Hospital bore no liability to Mercury; and a declaration that if the Hospital, should be found liable in any respect to Mercury, it would be entitled to indemnity from the Architect. The complaint was served on Mercury on October 9. On that same day, Mercury’s counsel mailed a demand for arbitration.

On October 15, without notice to Mercury, the Hospital obtained an ex parte injunction from the state court forbidding Mercury to take any steps directed toward arbitration. Mercury objected, and the stay was dissolved on October 27. As soon as the stay was lifted, Mercury filed the present action in the District Court, seeking an order compelling arbitration under § 4 of the Arbitration Act, 9 U. S. C. § 4.4 Jurisdiction was based on diversity of citizenship. On the Hospital’s motion, the District Court stayed Mercury’s federal-court suit pending resolution of the state-court suit because the two suits involved the identical issue of the arbitrability of Mercury’s claims. App. to Pet. for Cert. A-38.

[8]*8Mercury sought review of the District Court’s stay by both a notice of appeal and a petition for mandamus. A panel of the Court of Appeals for the Fourth Circuit heard argument in the case, but before the panel issued any decision, the court informed the parties that it would consider the case en banc. After reargument, the en banc court held that it had appellate jurisdiction over the case under 28 U. S. C. § 1291. It reversed the District Court’s stay order and remanded the case to the District Court with instructions for entry of an order to arbitrate.

II

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Waters, J. v. Express Container
2022 Pa. Super. 182 (Superior Court of Pennsylvania, 2022)
MBC Development, LP v. Miller, J.
2022 Pa. Super. 141 (Superior Court of Pennsylvania, 2022)
Kohlman, D. v. Grane Healthcare Co.
2022 Pa. Super. 118 (Superior Court of Pennsylvania, 2022)
Villa v. Gruma Corporation
E.D. California, 2020
Gonzalez v. Comenity Bank
E.D. California, 2019
Schneider Elect. Build. Critical Systems v. Western Surety Co.
Court of Special Appeals of Maryland, 2016
Sandquist v. Lebo Automotive, Inc.
376 P.3d 506 (California Supreme Court, 2016)
United States v. Tyrone Davis
825 F.3d 1014 (Ninth Circuit, 2016)
Sakkab v. Luxottica Retail North America, Inc.
803 F.3d 425 (Ninth Circuit, 2015)
Sandoval v. M1 Auto Collisions Centers
309 F.R.D. 549 (N.D. California, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
460 U.S. 1, 103 S. Ct. 927, 74 L. Ed. 2d 765, 1983 U.S. LEXIS 17, 51 U.S.L.W. 4156, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moses-h-cone-memorial-hospital-v-mercury-construction-corp-scotus-1983.