Schneider Elect. Build. Critical Systems v. Western Surety Co.

Court of Special Appeals of Maryland·Decided November 30, 2016·No. 0020/15·Published

Opinion

REPORTED

IN THE COURT OF SPECIAL APPEALS OF MARYLAND

No. 20

September Term, 2015

SCHNEIDER ELECTRIC BUILDINGS CRITICAL SYSTEMS, INC.

v.

WESTERN SURETY COMPANY

Krauser, C.J., Berger, Zarnoch, Robert A.

(Senior Judge, Specially Assigned),

JJ.

Opinion by Krauser, C.J.

Filed: November 30, 2016

The issue before us is whether Western Surety Company, the appellee, is bound by the mandatory arbitration clause of an agreement between Schneider Electric Buildings Critical Systems, Inc., the appellant, and National Control Services, Inc. (“NCS”), as that agreement was later incorporated by reference into a subcontract between Schneider Electric and NCS, which was thereafter incorporated by reference into a performance bond issued by Western Surety on behalf of NCS for work it was to perform for Schneider Electric.

The aforementioned agreement between Schneider Electric and NCS, containing the arbitration clause at issue, in this appeal, was entitled the “Master Subcontract Agreement.” Its purpose was to enable Schneider Electric, “from time to time,” to “engage the services of [NCS] to provide labor, material, equipment and services . . . in connection with construction projects,” and its terms were to cover all future subcontracts between them. Of particular relevance to the issue before us, the Master Subcontract Agreement provided that any disputes that might arise between those two corporate entities, which could not be resolved by “good faith negotiations,” must be submitted to arbitration.

One year later, Schneider Electric was retained to assist in the building of a facility at Aberdeen Proving Ground, whereupon it entered into a subcontract agreement with NCS, in accordance with the parties’ Master Subcontract Agreement, providing that NCS was to perform certain work at the construction site of that facility. The subcontract required NCS to furnish a performance bond, which it did. The issuer of that bond was Western Surety. And, significantly, the bond incorporated by reference the subcontract

between Schneider Electric and NCS, which had incorporated by reference the Master Subcontract Agreement between those two parties, with its mandatory arbitration clause.

When NCS thereafter declined to perform the construction required by the subcontract, as a result of a payment dispute, Schneider Electric filed, as provided by the parties’ Master Subcontract Agreement, a demand for arbitration. Although that demand, initially, named only NCS as a respondent, it was subsequently amended to include Western Surety, as a co-respondent, on the grounds that the performance bond, issued by Western Surety, incorporated by reference the subcontract, which, in turn, had incorporated by reference the Master Subcontract Agreement, with its mandatory arbitration clause, and thereby purportedly bound Western Surety to that clause.

In response to its belated inclusion into Schneider Electric’s demand for arbitration, Western Surety filed a petition, in the Circuit Court for Howard County, to stay that arbitration and for a declaratory judgment, avowing, among other things, that it was not a party to Schneider Electric’s and NCS’ agreement to arbitrate their disputes and therefore could not be compelled to participate in the arbitration proceeding pending between them; it asserted, moreover, that Schneider Electric had breached the performance bond and that that breach had relieved Western Surety of any liability under that instrument. Then, following the transfer of this dispute from Howard County to Harford County, the Circuit Court for Harford County granted partial summary judgment in favor of Western Surety, concluding that, under either federal or state law, Western Surety was not subject to the arbitration provision of the incorporated Master Subcontract Agreement and therefore

could not be compelled to participate in the pending arbitration proceeding between Schneider Electric and NCS.

In so ruling, the Harford County circuit court cited three grounds for its decision:

first, the words of the performance bond evinced an intent by Western Surety to guarantee the performance of all construction work to be performed by NCS, but not all contractual obligations undertaken by NCS, pursuant to the subcontract; second, the arbitration clause of the Master Subcontract Agreement, even if ultimately incorporated by reference into the performance bond, mandated arbitration only as to disputes between Schneider Electric and NCS; and, third, to rule otherwise, would, in effect, read out of the performance bond language expressly providing for a judicial resolution of any dispute, involving the bond, that might arise.

Schneider Electric then noted this appeal, contending that the Harford County circuit court’s ruling was in error for two reasons: first, by agreeing, in the performance bond, to “jointly and severally” bind themselves to the performance of the subcontract between Schneider Electric and NCS, both Western Surety and NCS were thereby bound to comply with the arbitration clause incorporated by reference into that subcontract; and, second, because the performance bond incorporated by reference that subcontract, Western Surety was rendered subject to the arbitration clause. Finding no merit to either claim of error, we shall affirm the judgment of the circuit court.

I.

In May 2009, Schneider Electric1 and NCS entered into a “Master Subcontract Agreement,” in which the parties agreed, as noted, that NCS would “provide labor, material, equipment and services necessary to perform work in connection with construction projects, from time to time[.]” The Master Subcontract Agreement set forth, among other things, the terms and conditions that would apply to all future subcontracts between the two companies. It also included a provision, which is the crux of this appeal, that any dispute between them would be subject to arbitration, if they were unable to negotiate a resolution of that dispute.

Several months later, on August 14, 2009, Clark Construction Group, LLC, which is not a party to this matter, entered into a contract with the United States Army Corps of Engineers to build a replacement facility for medical research at Aberdeen Proving Ground in Harford County, Maryland. The following October, Clark Construction, now the general contractor for that construction project, contractually retained the services of Schneider Electric to assist in the construction of that facility.

Seven months after Schneider Electric was engaged, by Clark Construction, as a subcontractor for the construction project, Schneider Electric, pursuant to its Master Subcontract Agreement with NCS, entered into a subcontract with NCS, to perform work

1 When the parties entered into the Master Subcontract Agreement, Schneider Electric was known as TAC Critical Systems, Inc. In July 2011, more than two years after the execution of the Master Subcontract Agreement, TAC Critical Systems changed its name to Schneider Electric Buildings Critical Systems, Inc.

for that project. The subcontract incorporated by reference the Master Subcontract Agreement, which contained the arbitration clause at issue.

Specifically, the subcontract provided that NCS would perform “electrical and pneumatic installation” work at the Aberdeen facility. For that work, NCS was to be paid $2,050,000, “in installments as the Work progresses.”

Free access — add to your briefcase to read the full text and ask questions with AI

Schneider Elect. Build. Critical Systems v. Western Surety Co., (Md. Ct. App. 2016).

Schneider Elect. Build. Critical Systems v. Western Surety Co. (Schneider Elect. Build. Critical Systems v. Western Surety Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

MS Dealer Service Corp. v. Franklin
177 F.3d 942 (Eleventh Circuit, 1999)
Perry v. Thomas
482 U.S. 483 (Supreme Court, 1987)
First Options of Chicago, Inc. v. Kaplan
514 U.S. 938 (Supreme Court, 1995)
Arthur Andersen LLP v. Carlisle
556 U.S. 624 (Supreme Court, 2009)
Rashid v. Schenck Const. Co., Inc.
438 S.E.2d 543 (West Virginia Supreme Court, 1993)
Transamerica Premier Insurance v. Collins & Co.
735 F. Supp. 1050 (N.D. Georgia, 1990)
Hoffman v. Fidelity and Deposit Co. of Maryland
734 F. Supp. 192 (D. New Jersey, 1990)
St. Paul Fire & Marine Ins. Co. v. Woolley/Sweeney Hotel 5
545 So. 2d 958 (District Court of Appeal of Florida, 1989)
Rourke v. Amchem Products, Inc.
863 A.2d 926 (Court of Appeals of Maryland, 2004)