Hoffman v. Fidelity and Deposit Co. of Maryland

734 F. Supp. 192, 1990 U.S. Dist. LEXIS 4133, 1990 WL 41890
CourtDistrict Court, D. New Jersey
DecidedApril 9, 1990
DocketCiv. A. 89-4405 (JCL)
StatusPublished
Cited by41 cases

This text of 734 F. Supp. 192 (Hoffman v. Fidelity and Deposit Co. of Maryland) is published on Counsel Stack Legal Research, covering District Court, D. New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hoffman v. Fidelity and Deposit Co. of Maryland, 734 F. Supp. 192, 1990 U.S. Dist. LEXIS 4133, 1990 WL 41890 (D.N.J. 1990).

Opinion

OPINION AND ORDER

LIFLAND, District Judge.

BACKGROUND

Plaintiff Lee Hoffman (“Hoffman”) contracted with Albert Garlatti (“Garlatti”) on August 15, 1986. Garlatti agreed to construct a warehouse addition for Hoffman. The contract (“Contract”) between Hoffman and Garlatti contained the following arbitration clause:

“8.1.14. Dispute Resolution. All claims, disputes and other matters in question between the parties to this Agreement, arising out of or related to this Agreement or the breach thereof, shall be decided by arbitration or litigation, at the election of the owner____”

Defendant Fidelity and Deposit Company of Maryland (“Fidelity”) executed and delivered to Hoffman a performance bond (the “Bond”). The Bond incorporated the Contract by reference:

“Whereas, Contractor has by written agreement dated August 15, 1986, entered into a contract with Owner for construction of Building Addition at the existing facility of Fast Forward, Inc., Oak Glenn Road, Howell, N.J. in accordance with drawings and specifications prepared by M. Israel & Associates 620 Shrewsbury Avenue, Red Bank, New Jersey 07701 which contract is by reference made a part hereof, and is hereinafter referred to as the Contract.” (emphasis added)

A dispute has arisen under the Contract. Hoffman claims that the construction was faulty. Pursuant to the above-quoted dispute resolution language, Hoffman served Garlatti with a demand for arbitration. This arbitration proceeding is currently pending before the American Arbitration Association. Hoffman also served a demand for arbitration on Fidelity in which Hoffman asserted a claim under the Bond. Fidelity has refused to participate in the arbitration, arguing that there is no arbitration agreement between Fidelity and Hoffman.

Presently before the court is Fidelity’s motion for a declaratory judgment stating that Hoffman’s claims against Fidelity on the Bond are not arbitrable. Hoffman has cross-moved pursuant to the Federal Arbitration Act (9 U.S.C. § 4) for partial summary judgment on Count Two of the complaint for an order compelling arbitration of Fidelity’s liability under the Bond.

ISSUES UPON WHICH THE PARTIES AGREE

1. The Contract dispute between Hoffman and Garlatti is properly before the arbitrators pursuant to the dispute resolution section of the Contract.

2. Fidelity will be bound by the decision of the arbitrators on the underlying Contract dispute. Fidelity seeks to exclude from the arbitration process only its defenses to liability on the Bond (e.g. waiver, alteration of risk).

3. There are no questions of fact precluding the entry of summary judgment.

4. The Contract involved interstate commerce.

5. The Federal Arbitration Act (9 U.S.C. § 1 et seq.) is applicable.

ISSUES IN DISPUTE

Fidelity argues that the incorporation by reference was intended only to define the scope of the work to be performed by Garlatti, and not to define the obligation of Fidelity. Fidelity further argues that even if the arbitration clause is incorporated into the Bond, the clause does not apply to Fidelity. Fidelity argues that the language “between the parties to this agreement” *194 limits the application of the arbitration clause to Hoffman and Garlatti. Hoffman argues that the incorporation by reference of the Contract obligated Fidelity to arbitrate all issues relating to the Bond, including any defenses.

DISCUSSION

In contracts governed by the Federal Arbitration Act, questions as to the construction and enforceability of arbitration agreements are controlled by federal substantive law. Cost Brothers Inc. v. Travelers Indemnity Co., 760 F.2d 58, 60 (3d Cir.1985).

The Eleventh, Sixth, Fifth, Second and First Circuits, and several district courts, have required sureties to arbitrate issues relating to a performance bond where the performance bond incorporates by reference a contract containing an arbitration clause. U.S. Fidelity and Guaranty Co. v. West Point Construction Co., 837 F.2d 1507, 1508 (11th Cir.1988) (incorporation by reference of a subcontract containing an arbitration clause “expresse[d] an intention of the parties, including [the surety] to arbitrate disputes”); Exchange Mutual Insurance Co. v. Haskell Co., 742 F.2d 274, 276 (6th Cir.1984) (“[A] party does not have to be a signatory to the contract when the contract is specifically incorporated by reference in the surety bond.”); Compania Espanola de Petroleos v. Nereus Shipping, 527 F.2d 966, 973-74 (2nd Cir.1975); Cianbro Corp. v. Empresa Nacional de Ingenieria, 697 F.Supp. 15 (D.Me.1988); See J & S Construction Co., Inc. v. Travelers Indemnity Co., 520 F.2d 809, 810 (1st Cir.1975) (surety permitted to stay litigation pending arbitration because “the contract [containing the arbitration clause] was explicitly incorporated by reference in the surety bond.”); O’Connor and Co. v. Insurance Co. of North America, 697 F.Supp. 563 (D.Mass.1988) (surety permitted to stay litigation pending arbitration); Cf. Cost Brother v. Travelers, 760 F.2d 58 (3d Cir.1985) (because performance bond did not incorporate by reference the contract containing the arbitration clause, the surety was not a party to the arbitration agreement).

In Exchange Mutual, the court was required to take the incorporation by reference one step further than is necessary here. The performance bond incorporated by reference the sub-contract, which incorporated by reference the contract, which contained the arbitration clause. The arbitration and the incorporation by reference clauses involved in Exchange Mutual were similar to the language involved in the present case:

All claims, disputes, and other matters in question arising out of, or relating to this contract or the breach thereof ... and which can not be settled by negotiation between the contractor and the owner, shall be [resolved by arbitration]
[the] subcontract is hereby referred to and made a part hereof [the performance bond].

Similarly, in Cianbro Corp. v. Empresa Nacional De Ingenieria, 697 F.Supp. 15 (D.Me.1988) the primary contract did not contain an arbitration clause, but the subcontract contained language similar to that involved in the present case:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hardee v. CMH Homes, Inc
E.D. Louisiana, 2021
Morel v. U.S. Xpress, Inc.
E.D. Louisiana, 2020
Reed v. Royal Sonesta, Inc.
E.D. Louisiana, 2020
KOONS v. JETSMARTER, INC
D. New Jersey, 2019
DAVIMOS v. JETSMARTER, INC
D. New Jersey, 2019
White v. Spaulding
D. Massachusetts, 2019
Warner v. Spaulding
D. Massachusetts, 2018
Schneider Electric Buildings Critical System, Inc. v. Western Surety Co.
165 A.3d 485 (Court of Appeals of Maryland, 2017)
Schneider Elect. Build. Critical Systems v. Western Surety Co.
Court of Special Appeals of Maryland, 2016
Schneider Electric Buildings Critical Systems, Inc. v. Western Surety Co.
149 A.3d 778 (Court of Special Appeals of Maryland, 2016)
Great American Insurance v. Hinkle Contracting Corp.
826 F. Supp. 2d 969 (S.D. West Virginia, 2011)
Ebner v. FINANCIAL ARCHITECTS, INC.
763 F. Supp. 2d 697 (D. Delaware, 2011)
Spirtas Co. v. Insurance Co. of State of Pa.
555 F.3d 647 (Eighth Circuit, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
734 F. Supp. 192, 1990 U.S. Dist. LEXIS 4133, 1990 WL 41890, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hoffman-v-fidelity-and-deposit-co-of-maryland-njd-1990.