Thomas O'Connor & Co. v. Insurance Co. of North America

697 F. Supp. 563, 1988 U.S. Dist. LEXIS 12724, 1988 WL 113525
CourtDistrict Court, D. Massachusetts
DecidedOctober 12, 1988
DocketCiv. A. 88-1638-C
StatusPublished
Cited by6 cases

This text of 697 F. Supp. 563 (Thomas O'Connor & Co. v. Insurance Co. of North America) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thomas O'Connor & Co. v. Insurance Co. of North America, 697 F. Supp. 563, 1988 U.S. Dist. LEXIS 12724, 1988 WL 113525 (D. Mass. 1988).

Opinion

MEMORANDUM

CAFFREY, Senior District Judge.

The plaintiff subcontractor, Thomas O’Connor & Co., Inc. (“O'Connor”), has brought this action against Insurance Company of North America (“INA”) for payment under a surety bond. INA is the payment bond surety of Distral Energy Corporation (“Distral”), the general contractor. This case is before the Court on defendant’s motion to stay proceedings pending arbitration between O’Connor and Distral. Defendant requests a stay of this Court’s proceedings pursuant to section 3 of the United States Arbitration Act, 9 U.S.C. § 1 et seq., and the Court’s inherent powers to control its docket. After a hearing and consideration of the pleadings, and for the reasons discussed below, this Court rules that defendant’s motion to stay proceedings pending arbitration should be allowed.

In February of 1986, Distral, along with certain other general contractors, entered into a contract (“the Warren Contract”) with Warren Energy Resource Co., Limited Partnership. The contract provided for construction work to be performed on the Warren County New Jersey Resource Recovery Project (“the Resource Recovery Project”) in Warren County, New Jersey. The Warren Contract included an arbitration clause covering all “claims or disputes” between the parties arising in connection with performance of work under the contract. 1

*565 The Warren Contract also required Dis-tral to secure a payment bond. Pursuant to that contract provision, Distral executed a payment bond with INA, the defendant in the present case. INA bound itself to pay all persons furnishing “labor, services, materials or supplies” under the Warren Contract in the event Distral failed to make timely payment. The payment bond also states that the Warren Contract is by reference made part of the bond.

In a subcontract (“the Subcontract”) dated March 10, 1987, between Distral and O’Connor, O’Connor agreed to install two boiler units and two external economizer units as part of the Resource Recovery Project. The Subcontract incorporates by reference certain general conditions listed in the Warren Contract, including the arbitration clause and the payment bond provision.

O’Connor now seeks to recover $1,108,-402.52 under the INA payment bond for “labor, services, materials, and supplies for use in the prosecution of the work” performed under the Subcontract (See Complaint ¶¶ 3-5). The plaintiff has concurrently filed a demand for arbitration against Distral, pursuant to the arbitration clause. O’Connor has attempted, therefore, to bring its claim for payment regarding work performed on the Resource Recovery, Project in two different forums.

It is clear that INA is entitled to rely on the arbitration clause included in the Warren Contract. The payment bond executed by Distral with INA as surety explicitly incorporates by reference the Warren Contract. As described earlier, the Warren Contract contains an arbitration clause which states that “all claims or disputes” arising in connection with the performance of work under the agreement “shall be determined by binding arbitra-tion_” It is also apparent that O’Con-nor is bound by the arbitration clause, as the Subcontract explicitly incorporates by reference the arbitration provision in the Warren Contract. O’Connor cannot be heard to invoke the protection of the INA payment bond, as incorporated by reference in the Subcontract, while disavowing incorporation of the arbitration clause in the bond as well as the Subcontract. See, e.g., Exchange Mutual Insurance Co. v. Haskell Co., 742 F.2d 274 (6th Cir.1984) (sound approach is to allow arbitration where the surety bond includes by reference the obligation to arbitrate); J & S Construction Co., Inc. v. Travelers Indemnity Co., 520 F.2d 809 (1st Cir.1975) (where contract was explicitly incorporated by reference in the surety bond, the surety, although not a party to the - construction contract, could assert contractual right under arbitration clause). Cf. Cost Brothers, Inc. v. Travelers Indemnity Co., 760 F.2d 58 (3rd Cir.1985) (surety may not compel subcontractor to submit its dispute to arbitration where surety is not a party to the agreement to arbitrate and the bond does not incorporate by reference the underlying agreement).

Section 3 of the United States Arbitration Act (“the Act”) requires a court in which suit has been brought “upon any issue referable to arbitration under an agreement in writing for such arbitration” to stay the action pending arbitration once the court is satisfied that the issue is arbi-trable under the agreement. 9 U.S.C. § 3. 13 B Wright, Miller & Cooper, Federal Practice & Procedure § 3569, p. 169. A motion to stay proceedings will not be granted pursuant to § 3 unless the contract in question evidences a transaction involving interstate commerce. Bernhardt v. Polygraphic Co. of America, Inc., 350 U.S. 198, 201-02, 76 S.Ct. 273, 275-76,100 L.Ed. *566 199 (1956); Warren Bros. Co. v. Cardi Corp., 471 F.2d 1304, 1307 n. 2 (1st Cir. 1973). Furthermore, the party applying for the stay must not be in default in the arbitration proceedings, or the stay will be denied. New Process Steel Corp. v. Titan Indus. Corp., 555 F.Supp. 1018, 1021 (S.D. Tex.1983).

In the present case, the conditions necessary for a stay of this Court’s proceedings, pursuant to § 3 of the Act, are satisfied. First, there exists a written agreement, binding on both parties to this action, containing an arbitration clause. The arbitration clause is incorporated by reference in both the Subcontract between O’Connor and Distral and the payment bond binding INA as Distral’s surety. Second, this Court is satisfied that the central issue in this action, namely, O’Connor’s right to payment for work performed under the Subcontract, is arbitrable under the agreement. The arbitration clause covers “all claims or disputes” arising between the parties occurring in connection with performance of work under the Warren Contract. Clearly, O’Connor’s claim for payment for work performed on the Resource Recovery Project is covered by the broad language contained in the arbitration clause. See, e.g., New Process Steel Corp. v. Titan Indus. Corp., 555 F.Supp. at 1021 (in determining whether an issue is arbitra-ble under the agreement, the court will look to language of the arbitration clause).

Third, the agreement in question does evidence a transaction involving interstate commerce.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
697 F. Supp. 563, 1988 U.S. Dist. LEXIS 12724, 1988 WL 113525, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thomas-oconnor-co-v-insurance-co-of-north-america-mad-1988.