Total Environmental Concepts, Inc. v. Federal Insurance Company

District Court, S.D. Ohio·Decided April 4, 2023·No. 2:20-cv-03992·Unknown

Opinion

UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF OHIO EASTERN DIVISION

TOTAL ENVIRONMENTAL CONCEPTS, INC.

Plaintiff, Case No. 2:20-cv-3992 v. Judge Edmund A. Sargus, Jr. Magistrate Judge Kimberly A. Jolson

FEDERAL INSURANCE COMPANY.,

Defendant. OPINION AND ORDER This matter arises on Defendant Federal Insurance Company’s Motion to Dismiss or Stay Pursuant to the Federal Arbitration Act. (ECF No. 15). Also disposed of in this order is Plaintiff Total Environmental Concepts, Inc.’s Motion for Leave to File Sur-Reply. (ECF No. 22). For the reasons set forth below, the Court DENIES Defendant’s Motion to Dismiss or Stay. (ECF No. 15). Plaintiff’s Motion for Leave to File Sur-Reply is GRANTED. (ECF No. 22). I. Procedural Background Plaintiff Total Environmental Concepts, Inc. (TECI) filed this action in the Southern District of Ohio against Defendant Federal Insurance Company on August 6, 2020. (ECF No. 1). Plaintiff alleged Federal Insurance Company (FIC, also referred to as “Surety”) owed it “amounts unpaid pursuant to TECI’s contract with non-party Brican, Inc.” (Id., at 1). In compliance with the Miller Act, FIC had acted as surety to Brican. (Id., at 1). Defendant FIC filed the instant Motion to Dismiss on March 4, 2021. (ECF No. 15). Plaintiff Responded on March 17, 2021. (ECF No. 18). Defendant Replied shortly after, on April 1, 2021. (ECF No. 21). Plaintiff then sought leave from the Court to file a Sur-Reply on April 2, 2021. (ECF No. 22). Included with Plaintiff’s motion was the Sur-reply. (ECF No. 22, Exhibit 1). II. Factual Background

In 2017 a Veterans Administration contractor, Brican, entered into a subcontract with TECI. (ECF No. 1, Exhibit 2, at 1). Brican had contracted with the Veterans Administration to perform improvements to a project titled the “Columbus Boiler Plant Replacement. (ECF No. 1, at 1). TECI’s subcontract obliged the company “to provide certain fuel tank installation and controls work and attendant materials for the Project.” (ECF No. 1, at 3). Pursuant to the Miller Act, Brican obtained a payment bond from a surety. (ECF No. 1, Exhibit 1). Bonds of this type are meant “to secure payment to subcontractors for work performed on the Project” and are required by the Act. (ECF No. 1, at 3) (ECF No. 18, at 3). The surety in question, Federal Insurance Company, provided the bond, which was titled “payment Bond, No. 8244-89-27.” (ECF No. 1, at 3) (ECF No. 1, Exhibit 1). However, while

FIC’s bond guaranteed payment to TECI, the two never entered any contract together. (ECF No. 18, at 3). After entering into its subcontract with Brican, TECI began performing work on the Project. (ECF No. 1, at 3). However, Brican and TECI eventually came to dispute payment. (Id., at 3–4). TECI alleged that it was owed money that Brican refused to pay. (Id.). This dispute escalated, until TECI finally filed suit in the Southern District of Ohio on August 6, 2020. (ECF No. 1). TECI alleged one Miller Act violation stemming from Brican’s refusal of payment. Because FIC acted as Brican’s surety, TECI sued FIC to recover the payment bond. (Id., at 4–5). FIC, however, argues that TECI must arbitrate their dispute. (ECF No. 15). III. Standard The Federal Arbitration Act (“Act”) provides that “[a] written provision in any . . . contract evidencing a transaction involving commerce to settle by arbitration a controversy thereafter arising out of such contract or transaction . . . shall be valid, irrevocable, and

enforceable, save upon such grounds as exist at law or in equity for the revocation of any contract.” 9 U.S.C. § 2. “The preeminent concern of Congress in passing the Act was to enforce private agreements into which parties had entered, and that concern requires that [courts] rigorously enforce agreements to arbitrate . . . .” Dean Witter Reynolds, Inc. v. Byrd, 470 U.S. 213, 221, 105 S. Ct. 1238, 84 L. Ed. 2d 158 (1985). The Act provides federal courts with the authority to stay lawsuits in cases where issues are referable to arbitration pursuant to written agreements calling for such arbitration, and to compel arbitration where a party to a dispute has refused to arbitrate the dispute as required by an enforceable agreement. See 9 U.S.C. §§ 3-4. “Before compelling an unwilling party to arbitrate, the court must engage in a limited review to determine whether the dispute is

arbitrable; meaning that a valid agreement to arbitrate exists between the parties and that the specific dispute falls within the substantive scope of that agreement.” Javitch v. First Union Sec., Inc., 315 F.3d 619, 624 (6th Cir. 2003). IV. Analysis Defendant maintains the Court must “dismiss Plaintiff’s Complaint,” or at the very least “stay the pending matter subject to the conclusion of mandatory arbitration” “because the matters addressed in Plaintiff’s Complaint are properly subject to a mandatory arbitration provision.” (ECF No. 15, at 1). Plaintiff counters that “Surety’s Motion should be denied because there is no arbitration agreement between TECI and Surety, and the Payment Bond under which Surety is liable to TECI does not incorporate, reference, or otherwise refer to the arbitration agreement between TECI and non-party Brican, Inc (“Brican”). (ECF No. 18, at 1). Thus, the question before the Court is as follows: Are the matters addressed in Plaintiff’s Complaint subject to a mandatory arbitration agreement? For the reasons described below, the Court finds that they are

not. a. Arbitration Agreement Arbitration is a federally favored policy. Schearson/American Express v. McMahon, 482 U.S. 220, 227 (1987). The Federal Arbitration Act (FAA) “provides that a written arbitration agreement ‘shall be valid, irrevocable, and enforceable, save upon such grounds as exist at law or in equity for the revocation of any contract.’” American General Life and Accident Insurance Company v. Wood, 429 F. 3d 83, 87 (4th Cir. 2005), citing 9 U.S.C. § 2. However, Federal law “does not require parties to arbitrate when they have not agreed to do so ….” Volt Information Sciences, Inc. v. Board of Trustees of Leland Stanford Junior University, 489 U.S. 468, 478 (1989). In this case, it is undisputed that no written arbitration agreement exists between FIC

and TECI. As Plaintiff points out “[t]he only arbitration agreement cited in Surety’s Motion is that which appears in the Subcontract between non-party Brican and TECI.” (ECF No. 18, at 3). The portion of this agreement dealing with arbitration is as follows: ….The parties agree that any dispute or claim concerning this Agreement or the terms or conditions of employment, including whether such dispute is arbitratable, will be settled by arbitration. The arbitration proceedings shall be conducted under the Commercial Arbitration Rules of the American Arbitration Association in effect at the time a demand for arbitration under the rules is made. The decision of the arbitrators, including determination of any amount of damages suffered, shall be exclusive, final, and binding on both parties, their heirs, executors, administrators, successors and assigns… ECF No. 1, Exhibit 2, at 7).

Free access — add to your briefcase to read the full text and ask questions with AI

Total Environmental Concepts, Inc. v. Federal Insurance Company, (S.D. Ohio 2023).

Total Environmental Concepts, Inc. v. Federal Insurance Company (Total Environmental Concepts, Inc. v. Federal Insurance Company) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related