United States ex rel. Spectrum Control Systems, Inc. v. Staffco Construction, Inc.

107 F. App'x 453
CourtCourt of Appeals for the Sixth Circuit
DecidedJuly 22, 2004
DocketNo. 03-3651
StatusPublished
Cited by3 cases

This text of 107 F. App'x 453 (United States ex rel. Spectrum Control Systems, Inc. v. Staffco Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. Spectrum Control Systems, Inc. v. Staffco Construction, Inc., 107 F. App'x 453 (6th Cir. 2004).

Opinion

ROGERS, Circuit Judge.

Eclectic Company, Inc. (“Eclectic”) appeals the district court’s grant of summary judgment on behalf of Staffco Construction, Inc. (“Staffco”) in its cross-claim for quantum meruit relief under the Miller Act and for breach of contract. Because the district court concluded correctly that no triable issues of fact remained in this case and that Staffco was entitled to judgment as a matter of law, we affirm.

FACTS

On July 8, 1996, Wright-Patterson Air Force Base (“WPAFB”) in Dayton, Ohio, sought bids from contractors to renovate the basement of Building 262 at WPAFB. WPAFB generated full-size drawings of the project and requisitioned copies of the drawings from the Government Printing Office (“GPO”). The GPO outsourced the project to a local, privately-owned print shop that mistakenly produced half-size copies of the drawings. The print shop did not label the drawings as reduced in size.

After receiving the reduced drawings, WPAFB rejected them and the GPO required the print shop to reprint the drawings in the proper size. The print shop did so, and WPAFB received full-size drawings on August 7, 1996. After it received the full-size drawings, however, WPAFB failed to destroy all the remaining half-size drawings.

Staffco obtained a bid package from WPAFB, which contained accurate drawings, and sought bids from subcontractors to join its proposal. Eclectic provided the only bid for the HVAC and plumbing work, which Staffco accepted and incorporated into its proposal. Staffco did not know, however, that Eclectic had mistakenly received the half-size drawings from WPAFB and had based its proposal on the incorrect drawings. Staffco saw nothing on the face of Eclectic’s bid to indicate that the bid was based on incorrect dimensions.

On December 6, 1996, Staffco entered into a subcontract agreement with Eclectic to perform the HVAC and plumbing work, which incorporated by reference the terms of the bid solicitation and Staffco’s anticipated contract with the Government. On December 12, the Government awarded the contract to Staffco.

On April 1, 1997, WFAFB issued Staffco a notice to proceed with the project. After the notice was issued, Eclectic reviewed the full-size drawings and first became aware that its bid was predicated on half-size drawings. Eclectic’s president, Ronald Wantz, and project manager, Steve Eick, met with Staffco’s president, Mike Stafford, to discuss the problem. Wantz indicated to Stafford that Eclectic could not proceed with the project because it had bid on half-size drawings. Stafford replied that “Staffco had a contract with Eclectic which it expected Eclectic to perform, but that ‘the [Government had a procedure that we would go through to resolve these problems and that [Eclectic] would be paid one way or another.’” Wantz admitted that he understood this assurance to mean that Staffco intended to ask the Government to change its contract in light of the shortfall and then adjust the subcontract agreement with Eclectic. Eclectic performed and claimed an additional $417,075.23 to complete the project.

[455]*455First, Staffco petitioned the Air Force directly for an adjustment of the contract fee. The contracting officer who reviewed Staffco’s petition rejected the claim, determining that the correct dimensions were easily ascertainable from the half-size drawings, that Eclectic failed to participate in a site visit, and that Eclectic failed to provide any evidence of a mistake in its bid. Proceeding in Staffco’s name, Eclectic appealed this decision to the Armed Services Board of Contract Appeals (“ASBCA”).

The ASBCA also rejected Eclectic’s claim for additional compensation. Although the ASBCA concluded that the Government was responsible for Eclectic receiving the half-size drawings, the ASBCA first noted that the bid package encouraged potential bidders to make a physical site visit and inspect the work site. Second, the ASBCA noted that Eclectic had bid on projects at WPAFB in the past and was aware that the drawings it received were not the same size as drawings it had received from the base in the past. Despite the fact that Wantz contacted WPAFB to see if other drawings were available, the ASBCA found that Eclectic failed to notify WPAFB that the drawings may have been inaccurate. Third, with regard to the drawings themselves, the ASBCA found that:

The half-size drawings at issue contained the statement “SCALE 1"=20'.” Immediately above that written scale was a graphic bar scale in which one measured inch was denoted as “40'.” According to professional engineer C. Jeffrey Tefend, who designed the project and prepared the mechanical drawings, the graphic scale is the “true” scale of a drawing. As Mr. Stafford, Mr. Tefend and Mr. Balsamo agreed, the graphic scale remains accurate despite a reduction in drawing size. Whereas the written scale was incorrect on the half-size drawings, the graphic scale was correct. A comparison of the written scale and the graphic scale would have revealed that the drawings were half-size.

J.A. at 183-84 (emphasis added). Moreover, the ASBCA noted, the drawings Eclectic received contained “hard dimensions” — numbers printed on the drawing to indicate dimensions, saving the reader from scaling them off — that conflicted with the written scale. Because of the conflict of the written scale with the graphic scale and the hard dimensions, the ASBCA concluded that the drawings Eclectic received were patently ambiguous.

Having concluded that the drawings were patently ambiguous, the ASBCA followed the Federal Circuit’s rule that, when there is an ambiguity on the face of the drawings in a government solicitation, the ambiguity is construed against the potential bidder unless the bidder inquires as to the meaning of the ambiguity. See Triax Pacific, Inc. v. West, 130 F.3d 1469, 1474-75 (Fed.Cir.1997). The ASBCA concluded that the ambiguities in the drawings were obvious, but Eclectic nonetheless proceeded in the face of those ambiguities rather than discharge its duty to inquire.

After the ASBCA proceeding, Spectrum Controls (“Spectrum”), a subcontractor of Eclectic and not a party to this appeal, initiated in the district court this proceeding, against Staffco and Eclectic, for compensation pursuant to its installation of temperature controls in the project. Eclectic then filed a cross-claim against Staffco, alleging: (1) a claim for compensation against Staffco’s payment bond under the Miller Act, 40 U.S.C. § 270b(a), (2) breach of contract, (3) unjust enrichment, and (4) intentional interference with contractual relations. The district court entered summary judgment on Staffco’s be[456]*456half with regard to each of these claims. Eclectic appeals that determination with regard to the Miller Act claim and the contract claim.

The district court concluded that Eclectic’s Miller Act claim was precluded by res judicata. Although Eclectic argued that it was not a party to the ASBCA proceeding, the district court rejected this contention, concluding that Eclectic “had complete control” of those proceedings, and even if it had not, Eclectic was in privity of contract with Staffco.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
107 F. App'x 453, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-spectrum-control-systems-inc-v-staffco-ca6-2004.