United States of America, F/u/b/o Krupp Steel Products, Inc., D/B/A Diversified Steel Services v. Aetna Insurance Company

831 F.2d 978, 34 Cont. Cas. Fed. 75,401, 1987 U.S. App. LEXIS 14616
CourtCourt of Appeals for the Eleventh Circuit
DecidedNovember 5, 1987
Docket86-3647
StatusPublished
Cited by50 cases

This text of 831 F.2d 978 (United States of America, F/u/b/o Krupp Steel Products, Inc., D/B/A Diversified Steel Services v. Aetna Insurance Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States of America, F/u/b/o Krupp Steel Products, Inc., D/B/A Diversified Steel Services v. Aetna Insurance Company, 831 F.2d 978, 34 Cont. Cas. Fed. 75,401, 1987 U.S. App. LEXIS 14616 (11th Cir. 1987).

Opinion

JOHNSON, Circuit Judge:

Krupp Steel Products, Inc., d/b/a Diversified Steel Services, is a supplier of steel. Allied Steel Fabrications fabricates steel. As a subcontractor under contractor John D. Grubbs, Inc., for construction of the Forest Hills Post Office in Tampa, Florida, Allied ordered steel from Diversified. Only one payment of $10,058.39 has been made for Diversified’s deliveries to Allied. Allied still owes Diversified $39,667.82. To cover the outstanding payments Diversified sued *980 Aetna Insurance Company, the surety for the project, under the Miller Act.

The District Court granted Diversified’s motion for summary judgment and correspondingly awarded to Diversified the full sum of $39,667.82 as well as attorneys’ fees of $5,524.00. Aetna contests both the summary judgment and the attorneys’ fees award in this appeal.

We first consider whether the district court was correct in finding no remaining genuine and material issues of fact in this case. This review requires an understanding of Miller Act claims generally and an understanding of the practice of the supplier trade specifically. We then consider the issue of attorneys’ fees.

The Miller Act, 40 U.S.C.A. § 270a-270d, “requires a Government contractor to post a surety bond ‘for the protection of all persons supplying labor and material in the prosecution of the work provided for’ in the contract.” F.D. Rich Co. v. Industrial Lumber Co., 417 U.S. 116, 118, 94 S.Ct. 2157, 2159, 40 L.Ed.2d 703 (1974). The Act is “highly remedial in nature,” and its terms should be liberally construed. J. W. Bateson Co. v. U.S. ex rel. Board of Trustees, 434 U.S. 586, 594, 98 S.Ct. 873, 877, 55 L.Ed.2d 50 (1978); United States ex rel. Carlson v. Continental Casualty Co., 414 F.2d 431 (5th Cir.1969). Four elements must be proven by a plaintiff to collect under Section 270b: 1) that materials were supplied for work in the particular contract at issue; 2) that the supplier is unpaid; 3) that the supplier had a good faith belief that the materials were for the specified work; and 4) that jurisdictional requisites are met. United States v. Avanti Constructors, Inc., 750 F.2d 759 (9th Cir. 1984). 1

Appellant Aetna pursues several defenses on this appeal: 1) that the steel delivered by Diversified was not used for the Forest Hills project; and 2) that Aetna is entitled to a set-off for improper lien waivers, or that Diversified is estopped from claiming payment because of reliance on improper lien waivers. In the context of arguing these points, Aetna maintains that there are unresolved issues of fact that should have precluded summary judgment. We address these defenses in turn.

As to the destination of the materials supplied, Aetna’s arguments are unsupported by fact and law. First, Aetna fails to substantiate that the materials were not actually used for the Forest Hills project. There is simply no evidence that the materials were used elsewhere or not at all. Aetna is incorrect in claiming that the burden is on Diversified to provide affirmative proof that the materials were used to build the Forest Hills Post Office. As long as there is good faith, “under the law of this Circuit, delivery to the job site or actual use in the prosecution of the work is immaterial to a right of recovery.” United States ex rel. Lanahan Lumber v. Spearin, Preston & Burrows, Inc., 496 F.Supp. 816 (M.D.Fla.1980) (citing Continental Casualty).

There are no facts to put Diversified’s good faith at issue, and the record suffices to indicate good faith. Continental Casualty, 414 F.2d at 433-34. Each invoice and each delivery ticket for shipments of steel designated the Forest Hills project as the reason for the purchase. Diversified’s credit manager testified that the steel was intended for the Forest Hills project. Even Aetna’s answer to the complaint admits the fact. The district court was correct to accept the pretrial record as definitive on this point. With no remaining factual dispute regarding Diversified’s good faith belief, Diversified is entitled to the presumption that the steel was used for Forest Hills as contracted.

As to the estoppel defense, Aetna has made a showing of genuine and material unresolved issues of fact. The unresolved issues of fact turn on the issuance by Diversified to Allied of two partial lien waivers during one pay period. Aetna alleges that Grubbs made two payments to Allied to cover the two lien waivers and argues that, because Diversified issued the *981 two lien waivers, Grubbs justifiably relied on them.

To understand the issues in this case, one must understand the practice of financing transactions for supplied materials. In the normal course of events, Grubbs pays Allied who pays Diversified. However, Grubbs only pays Allied for work performed or materials supplied. Diversified holds security for materials it supplies on a “job basis,” the credit arrangement for the Forest Hills Post Office, based on lien rights against the payment bond executed by the surety of the project. Diversified relinquishes its lien bit by bit as it receives payment from Allied. This exchange is formally recorded as a partial lien waiver, issued by Diversified, and subsequently presented by Allied to Grubbs as proof of delivery by Diversified and payment by Allied. Grubbs correspondingly reimburses Allied for the payment to Diversified.

At issue in this case are one partial lien waiver signed October 26, 1984, and a second partial lien waiver signed November 15, 1984. The first waiver of lien was issued for a nominal $10.00. The second waiver of lien explicitly covered the one payment of $10,058.34 received from Allied. The confusion arises in that the two lien waivers cover the same pay period and represent only one actual payment by Allied to Diversified. Both have “effective dates” of August 31, 1984.

Aetna’s objection is that Diversified misled Grubbs in its payments to Allied. Aetna alleges that Grubbs has already made two progress payments to Allied in accordance with the two partial lien waivers. In figures, the difference is whether Diversified is entitled to $39,667.82 for supplies delivered after August 31, or to $1,156.00 for supplies delivered after November 15. Aetna claims that Grubbs interpreted and detrimentally relied on the execution date on the second partial lien waiver of November 15 as the effective date, meaning the date through which payments would have been received from Allied.

This dispute puts into question the relative meanings and importance of an effective date versus an execution date. Both partial lien waivers in question were filled out first with the project, Forest Hills, and then listed immediately below that was the date, 8/31/84, followed below that by the receiver, Allied.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dicks v. Fipps
M.D. Florida, 2023
Archie v. Covington County
M.D. Alabama, 2021
Univalor Trust, SA v. Columbia Petroleum, LLC
315 F.R.D. 374 (S.D. Alabama, 2016)
Johnson Controls, Inc. v. Liberty Mutual Insurance Co.
160 So. 3d 249 (Supreme Court of Alabama, 2014)
State Ex Rel. Solsbury Hill v. Liberty Mut.
2012 NMCA 032 (New Mexico Court of Appeals, 2012)
State ex rel Solsbury Hill, LLC v. Liberty Mut. Ins. Co.
2012 NMCA 32 (New Mexico Court of Appeals, 2011)
Safeco Insurance Co. of America v. Graybar Electric Co.
59 So. 3d 649 (Supreme Court of Alabama, 2010)
US for Use and Ben. of Wfi Georgia v. Gray Ins.
701 F. Supp. 2d 1320 (N.D. Georgia, 2010)
United States v. Gray Insurance
701 F. Supp. 2d 1320 (N.D. Georgia, 2010)
United States v. Certain Real Property, Huntsville, Al
579 F.3d 1315 (Eleventh Circuit, 2009)
Federal Insurance Co. v. I. Kruger, Inc.
829 So. 2d 732 (Supreme Court of Alabama, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
831 F.2d 978, 34 Cont. Cas. Fed. 75,401, 1987 U.S. App. LEXIS 14616, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-of-america-fubo-krupp-steel-products-inc-dba-ca11-1987.