Metal Roofing Solutions Inc v. Composite Manufacturing and Installers Inc

CourtDistrict Court, N.D. Alabama
DecidedMarch 14, 2022
Docket2:20-cv-00935
StatusUnknown

This text of Metal Roofing Solutions Inc v. Composite Manufacturing and Installers Inc (Metal Roofing Solutions Inc v. Composite Manufacturing and Installers Inc) is published on Counsel Stack Legal Research, covering District Court, N.D. Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Metal Roofing Solutions Inc v. Composite Manufacturing and Installers Inc, (N.D. Ala. 2022).

Opinion

UNITED STATES DISTRICT COURT FOR THE NORTHERN DISTRICT OF ALABAMA SOUTHERN DIVISION

METAL ROOFING SOLUTIONS, ) INC., )

) Plaintiff, ) ) Civil Action Number v. ) 2:20-cv-00935-AKK

) TRAVELERS CASUALTY AND ) SURETY COMPANY OF ) AMERICA, )

) Defendant. )

MEMORANDUM OPINION AND ORDER To state the obvious, construction projects often involve an extensive paper trail of schematics, plans, and purchase orders. And they usually require contracts— sometimes tiers upon tiers of them. Such was the case in the current matter before the court. Metal Roofing Solutions, Inc., a sub-subcontractor, sues Travelers Casualty and Surety Company of America under Alabama’s “little Miller Act,” Alabama Code § 39-1-1, based on a construction project in which MJ Harris Construction Services, LLC served as the general contractor and Composite Manufacturing and Installers, Inc. served as a subcontractor. Doc. 1. Both MRS and Travelers have moved for summary judgment, docs. 28; 29, and submitted briefing and evidentiary material in support of their positions. As explained herein, their motions are due to be denied because genuine disputes remain with respect to whether (1) the work orders MRS submitted to CMI after its final day on the project

fall within the sub-subcontract amount that MRS can arguably recover and (2) MRS waived its claims in certain executed releases. I.

Summary judgment is proper if “the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” FED. R. CIV. P. 56. A genuine dispute of material fact exists if a reasonable jury could return a verdict for the nonmoving party. Bowen v. Manheim

Remarketing, Inc., 882 F.3d 1358, 1362 (11th Cir. 2018) (citing Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986)). Because the court must construe the evidence in the light most favorable to the nonmoving party, summary judgment is

only appropriate “if a case is so one-sided that [the movant] must prevail as a matter of law.” Id. (citing Anderson, 477 U.S. at 251–52). The filing of cross-motions for summary judgment does not alter this framework. See Cole v. Owners Ins. Co., 326 F. Supp. 3d 1307, 1314 (N.D. Ala. 2018) (citing United States v. Oakley, 744 F.2d

1553, 1555–56 (11th Cir. 1984)). II. In 2017, MJ Harris entered into a construction contract with the University of

Alabama at Birmingham for work on UAB’s College of Arts and Sciences Building. Doc. 31-1 at 2; see docs. 28 at 2; 30 at 2. MJ Harris furnished and Travelers issued a $30,127,000 payment bond for the project. Doc. 31-1 at 2–5. The bond stated that

“[a]ny person that . . . furnished labor, materials, or supplies for or in the prosecution of the Contract and Contract Change Orders for which payment ha[d] not been timely made” could “institute a civil action” upon the bond and “have their rights

and claims adjudicated in a civil action and judgment entered thereon.” Id. at 3. MJ Harris then subcontracted with CMI for certain manufacturing and installation services on the project. See doc. 28 at 2–3. MJ Harris primarily tasked CMI with fabricating and installing “aluminum composite material” or ACM panels

for the building’s exterior. See docs. 28 at 2–3; 31-2; 32-3 at 6. CMI subsequently entered into a sub-subcontract with MRS in which MRS agreed to install and caulk the ACM panels and CMI agreed to pay MRS $64,452. Doc. 31-3 at 2, 5; see docs.

28 at 3; 30 at 2–3. Several terms in MRS’s and CMI’s sub-subcontract are particularly relevant in this case. For one, the sub-subcontract required “[a]ll work[-]order additions and[/]or omissions” to “be approved” by CMI, doc. 31-3 at 2, which, according to

CMI President Erik Houston, required MRS to email the change order to CMI for Houston’s signature and approval, doc. 31-5 at 4, 7–8. Additionally, MRS agreed to (1) “accept all financial responsibility for any work [it] performed” that was “not

covered” in the agreement or not approved by CMI; (2) “be responsible for furnishing all tools and equipment required to fulfill [the] agreement”; (3) “be responsible for including any overtime, in its original bid, required to meet the

completion schedule”; (4) “reimburse” CMI for “all cost[s]” CMI incurred due to MRS’s “negligence”; and (5) “be financially responsible for the replacement of any damaged, lost, mis-measured, or stolen goods due to [MRS’s] negligence.” Id. at 2–

3. Invoices were “required by the 14th of each month and [would] be paid upon receipt of payment from [MJ Harris].” Id. at 2. The sub-subcontract “[could] be modified or amended in writing . . . signed by the party obligated under the amendment” and would “be construed in accordance with the laws of the State of

Tennessee.” Id. at 4. MRS President Bobbie Smith, Jr. signed this agreement in February 2019. Id. Meanwhile, in late 2018, MRS began to work on the project, and it took field

measurements of the building so CMI could manufacture ACM panels for MRS’s installation. See docs. 28 at 3; 30 at 4–5; 31-5 at 6. MRS and CMI dispute whether MRS took inaccurate measurements, see doc. 31-5 at 10, but agree that when the ACM panels arrived, they did not fit properly on the building, see docs. 28 at 4; 30

at 5. As a result, MRS modified or remeasured the panels, requiring additional time and labor.1 Docs. 28 at 4; 30 at 5. MRS claims that CMI told it to modify the panels

1 MRS contends that it modified the panels on the ground, doc. 28 at 4, while Travelers claims that MRS remeasured some of the panels for CMI to refabricate, doc. 30 at 5. Ultimately, the parties in the field, doc. 28 at 4, and MRS did not send any work-order additions or changes to CMI for the remedial work during its time on the project, see docs. 30 at 5; 31-7

at 3; 31-8 at 3. MRS finished its last day on the project on May 19, 2019. See doc. 31-7 at 3. During and after its work on the project, MRS executed several releases of

certain claims against CMI and MJ Harris. On April 29, 2019, MRS agreed to a “Progress Release of Lien and Affidavit” that included: CURRENT MONTH CONDITIONAL RELEASE: The undersigned lienor, in consideration of the sum of $25,000.00 due through the date of February 28, 2019, hereby waives and releases its lien and right to claim a lien for labor, services and/or materials invoiced to M.J Harris for the described property. The undersigned does hereby certify and warrant that all labor, services and/or materials described herein have been provided prior to the execution of this document and have been paid in full. Doc. 31-19 at 2. On June 14, 2019, MRS agreed to another “Current Month Conditional Release” and a “Release for Previous Payments Received to Date”: CURRENT MONTH CONDITIONAL RELEASE: The undersigned lienor, in consideration of the sum of $16,275.70 due through the date of May 31[,] 2019, hereby waives and releases its lien and right to claim a lien for labor, services, and/or materials invoiced to CMI, Inc. for the described property. The undersigned does hereby certify and warrant that all labor, services and/or materials described herein have been provided prior to the execution of this document and have been paid in full. * * *

do not dispute that MRS performed some work to install accurately measured ACM panels after the original ones did not fit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
United States v. Frank M. Oakley
744 F.2d 1553 (Eleventh Circuit, 1984)
Nora E. Riddle v. Cerro Wire and Cable Group, Inc.
902 F.2d 918 (Eleventh Circuit, 1990)
Wayne J. Griffin Elec. v. Dunn Const.
622 So. 2d 314 (Supreme Court of Alabama, 1993)
A.G. Gaston Const. Co., Inc. v. Hicks
674 So. 2d 545 (Court of Civil Appeals of Alabama, 1995)
Lott v. Toomey
477 So. 2d 316 (Supreme Court of Alabama, 1985)
Federal Insurance Co. v. I. Kruger, Inc.
829 So. 2d 732 (Supreme Court of Alabama, 2002)
Safeco Insurance Co. of America v. Graybar Electric Co.
59 So. 3d 649 (Supreme Court of Alabama, 2010)
Magic City Paint & Varnish Co. v. American Surety Co.
152 So. 42 (Supreme Court of Alabama, 1934)
Qunesha Bowen v. Manheim Remarketing, Inc.
882 F.3d 1358 (Eleventh Circuit, 2018)
Johnson Controls, Inc. v. Liberty Mutual Insurance Co.
160 So. 3d 249 (Supreme Court of Alabama, 2014)
Bella Investments, Inc. v. Multi Family Services, Inc.
97 So. 3d 787 (Court of Civil Appeals of Alabama, 2012)
Cole v. Owners Ins. Co.
326 F. Supp. 3d 1307 (N.D. Alabama, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Metal Roofing Solutions Inc v. Composite Manufacturing and Installers Inc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/metal-roofing-solutions-inc-v-composite-manufacturing-and-installers-inc-alnd-2022.