Federal Insurance Co. v. I. Kruger, Inc.

829 So. 2d 732, 2002 Ala. LEXIS 93, 2002 WL 399039
CourtSupreme Court of Alabama
DecidedMarch 15, 2002
Docket1001096
StatusPublished
Cited by19 cases

This text of 829 So. 2d 732 (Federal Insurance Co. v. I. Kruger, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Federal Insurance Co. v. I. Kruger, Inc., 829 So. 2d 732, 2002 Ala. LEXIS 93, 2002 WL 399039 (Ala. 2002).

Opinions

On Application For Rehearing

The no-opinion order of affirmance of December 7, 2001 is withdrawn and the following is substituted therefor.

Bill Harbert Construction Company ("Harbert") and Federal Insurance Company ("Federal") appeal from a summary judgment entered by the Mobile Circuit Court in favor of I. Kruger, Inc. ("Kruger"), awarding Kruger $129,918.03. We affirm.

Facts
Harbert and the Board of Water and Sewer Commissioners of the City of Mobile ("the Water Board") entered into a contract, pursuant to which Harbert was to upgrade a wastewater treatment plant owned and operated by the Water Board. Federal Insurance Company acted as the surety and provided a labor and material payment bond ("the payment bond") in connection with this contract, with Harbert acting as the principal.

Harbert subcontracted with Kruger for the purchase from Kruger of a "reactor basin oxygen dissolution system," for the purchase of certain related parts, and for start-up and training services associated with the dissolution system. The total purchase price of the subcontract was $963,200. The subcontract called for Harbert to make monthly progress payments to Kruger during Kruger's performance, but also allowed Harbert to retain 10% of the total purchase price, or $96,320, until the following conditions were met:

"A final payment, consisting of the unpaid balance of the Price, shall be made thirty (30) days after the last of the following to occur, (a) Purchaser's

*Page 734
receipt of all Products in satisfactory condition, (b) final payment by Owner to Purchaser on account of the Products including retainage, (c) delivery of all guarantees, certifications and information required under the Contract Documents, and (d) delivery of a general release, in a form satisfactory to Purchaser, executed by Seller running to and in favor of Purchaser and Owner."

Kruger did, in fact, supply the dissolution system and all related parts to Harbert, as required under the subcontract. Subsequent to this delivery, but before the completion of the subcontract, however, a dispute arose between Harbert and the Water Board. Although Kruger repeatedly notified Harbert that it was ready to perform its duties under the subcontract, Harbert never requested any further services or assistance from Kruger. The Water Board subsequently terminated Harbert's contract. Thus, Kruger was unable to fulfill the terms of its subcontract with Harbert.

On September 22, 1998, after more than a year had elapsed without Harbert's requesting Kruger to perform the start-up or training services referenced in the Harbert-Kruger subcontract, Kruger billed Harbert for one-half of the remaining 10% due under the subcontract ("the retainage"). On December 18, 1998, Kruger billed Harbert for the other one-half of the retainage. When Harbert did not pay the amounts billed, Kruger notified Federal, the surety, of its claim under the payment bond.

Kruger later instituted this action against Harbert and against Federal, seeking to collect the $96,320 retainage. Kruger's claims were premised on the language of the payment bond and on Ala. Code 1975, §39-1-1 et seq., known as Alabama's "little Miller Act."1

Kruger filed a motion for a summary judgment on its claim for payment. Federal filed no opposition to Kruger's motion for a summary judgment. Harbert, however, opposed Kruger's summary-judgment motion on two grounds.

Harbert first contended that Kruger had not fully performed under its subcontract with Harbert. In support of this argument, Harbert submitted the affidavit of Michael E. Lamb, the division manager of Harbert's utility and industrial division. In that affidavit, Lamb attested that "[a]s a result of the Board's wrongful termination of the Upgrade and Modifications Contract, Kruger's obligations under the Kruger Subcontract have not been and cannot be satisfied." In particular, Lamb testified that Kruger had not fully provided the "construction assistance," "testing," "demonstrations," "start-up," and "training," specified in the subcontract and had not met the "requirements for guarantees, certifications and information."

Second, Harbert relied on the "pay-when-paid" clause in the Harbert-Kruger subcontract for the proposition that Kruger was not due payment of the retainage until the Water Board paid Harbert. As authority for this position, Harbert relied upon the case of James E. Watts SonsContractors, Inc. v. Nabors, 484 So.2d 373 (Ala. 1985), and A.G. GastonConstruction Co. v. Hicks, 674 So.2d 545 (Ala.Civ.App. 1995). *Page 735

The trial court entered a summary judgment in favor of Kruger against both Harbert and Federal. Harbert and Federal appealed, and we initially affirmed the trial court's judgment without an opinion. Harbert filed an application for rehearing, which we are overruling.

Standard of Review
In Jefferson County Commission v. ECO Preservation Services, L.L.C.,788 So.2d 121 (Ala. 2000), this Court addressed the standard applicable to our review of a ruling on a summary-judgment motion. The ECOPreservation Services Court stated:

"When reviewing a ruling on a motion for a summary judgment, this Court uses the same standard of review the trial court used `in determining whether the evidence before the court made out a genuine issue of material fact.' Bussey v. John Deere Co., 531 So.2d 860, 862 (Ala. 1988). When a party moving for a summary judgment makes a prima facie showing that there is no genuine issue of material fact and that the movant is entitled to a judgment as a matter of law, the burden shifts to the nonmovant to present substantial evidence creating a genuine issue of material fact. Bass v. SouthTrust Bank of Baldwin County, 538 So.2d 794, 797-98 (Ala. 1989). Substantial evidence is `evidence of such weight and quality that fair-minded persons in the exercise of impartial judgment can reasonably infer the existence of the fact sought to be proved.' West v. Founders Life Assur. Co. of Florida, 547 So.2d 870, 871 (Ala. 1989). In reviewing a ruling on a motion for a summary judgment, this Court views the evidence in the light most favorable to the nonmovant and entertains such reasonable inferences as the [fact-finder] would have been free to draw. Renfro v. Georgia Power Co., 604 So.2d 408 (Ala. 1992)."

788 So.2d at 126-27.

Analysis
We must determine whether Kruger is entitled to recover under the payment bond. The payment bond states that it was given pursuant to §39-1-1, Ala. Code 1975, the little Miller Act. The little Miller Act provides, in pertinent part:

"(a) Any person entering into a contract with an awarding authority in this state for the prosecution of any public works shall, before commencing the work, execute a performance bond, with penalty equal to 100 percent of the amount of the contract price.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ex Parte Consolidated Pipe & Supply Co., Inc.
265 So. 3d 1267 (Supreme Court of Alabama, 2018)
Johnson Controls, Inc. v. Liberty Mutual Insurance Co.
160 So. 3d 249 (Supreme Court of Alabama, 2014)
CAM Investments, LLC v. Totty
128 So. 3d 749 (Court of Civil Appeals of Alabama, 2013)
Finish Line v. J.F. Pate & Associates Contractors, Inc.
90 So. 3d 749 (Court of Civil Appeals of Alabama, 2012)
Evans, Mechwart, Hambleton & Tilton, Inc. v. Triad Architects, Ltd.
965 N.E.2d 1007 (Ohio Court of Appeals, 2011)
Lemoine Co. of Alabama v. HLH Constructors, Inc.
62 So. 3d 1020 (Supreme Court of Alabama, 2010)
Safeco Insurance Co. of America v. Graybar Electric Co.
59 So. 3d 649 (Supreme Court of Alabama, 2010)
Baldwin v. Panetta
4 So. 3d 555 (Court of Civil Appeals of Alabama, 2008)
Champion Home Builders Co. v. Johnson
993 So. 2d 875 (Supreme Court of Alabama, 2008)
Ex Parte Johnson v. Sabrina Johnson
993 So. 2d 875 (Supreme Court of Alabama, 2008)
Hartford Accident & Indemnity Co. v. Cochran Plastering Co.
935 So. 2d 462 (Court of Civil Appeals of Alabama, 2006)
Federal Insurance Co. v. I. Kruger, Inc.
829 So. 2d 732 (Supreme Court of Alabama, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
829 So. 2d 732, 2002 Ala. LEXIS 93, 2002 WL 399039, Counsel Stack Legal Research, https://law.counselstack.com/opinion/federal-insurance-co-v-i-kruger-inc-ala-2002.