Marshall F. Dancy v. William J. Howard, Inc., a Corporation

297 F.2d 686, 1961 U.S. App. LEXIS 2851
CourtCourt of Appeals for the Seventh Circuit
DecidedDecember 28, 1961
Docket13399_1
StatusPublished
Cited by9 cases

This text of 297 F.2d 686 (Marshall F. Dancy v. William J. Howard, Inc., a Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Marshall F. Dancy v. William J. Howard, Inc., a Corporation, 297 F.2d 686, 1961 U.S. App. LEXIS 2851 (7th Cir. 1961).

Opinion

HASTINGS, Chief Judge.

Marshall F. Dancy (plaintiff-appellee) brought this diversity action against William J. Howard, Inc. (defendant-appelant) to recover the amount due under an agreement for the services of plaintiff. The cause was tried to the court without the intervention of a jury. Judgment for plaintiff wás entered in the amount of $20,000 with interest, and this appeal followed.

On October 3,1951, defendant executed a preliminary agreement with the City of Dunbar, West Virginia and its Bridge *687 Commission contemplating the construction of a bridge over the Kanawha River. The agreement provided that defendant would do preliminary engineering work, make traffic reports, and arrange for financing the project and all costs incident thereto through the sale of bonds. On November 5, 1951, plaintiff accepted an assignment from defendant of that part of the preliminary agreement relating to the arranging of financing.

After signing the final bridge construction contract with the City and Bridge Commission on December 29, 1951, defendant entered into an agreement with Marshall Dancy & Associates. This agreement was in the form of a letter to Marshal] Dancy & Associates from defendant and was a re-write of a letter that had previously been sent to defendant from Marshall Dancy & Associates. It was dated January 18, 1952. The pertinent paragraph of this agreement provides :

“Marshall Dancy & Associates have agreed to provide financing for construction of said bridge, and to continue to provide said service in connection therewith until such time as the project has been completed. Thereupon for the aforesaid financing and additional services, William J. Howard, Inc., has agreed to pay Marshall Dancy & Associates, through Marshall Dancy [plaintiff], the sum of $100,000 to be paid in monthly installments starting at the time William J. Howard, Inc., receives his first partial payment under its contract and in amounts in direct proportions to the ratio of the construction contract monthly payments to the total construction contract. * * * ”

No question is raised as to the foregoing agreement, and the full amount of $100,000 therein mentioned was paid to plaintiff by defendant between July 1, 1952 and January 1, 1954.

The supplemental agreement sued upon by plaintiff was accepted by defendant on the same day as the above agreement. The pertinent parts of this contract provide:

“This supplemental contract on the Dunbar Bridge is in addition to that signed the 18th day of January, 1952, in the sum of $100,000 and it is to be considered in payment for services outside the purely functional aspect of the other contract, as well as to make up for a lack of personal earning power in the above stated principal contract.
“This contract shall not become payable until William J. Howard, Incorporated, has received final payment for construction of the said Dunbar Bridge.
“The amount herein agreed to between the principals shall be $20,000 (Twenty thousand dollars).
“If there is no contract nor any financing, there will be due no fees or expenses from William J. Howard, Incorporated, to Marshall F. Dancy.” (Emphasis added.)

The date and amount to be paid plaintiff were inserted therein by William J. Howard as president of defendant. Spaces for these items had been left blank by plaintiff when the supplemental contract was sent to defendant. No part of the agreed payment of $20,000 to plaintiff has been paid by defendant.

The trial court admitted, over defendant’s objection, parol testimony as to what was meant by “services outside the purely functional aspects of the other contract,” as this phrase appears in the supplemental agreement.

Under these agreements, Marshall Dancy & Associates handled the City’s bond issue for financing the bridge construction. Marshall Dancy obtained the consent of the Federal Reserve Credit Restraint Committee for the bond issue and dealt with right-of-way problems.

The bridge was ultimately constructed, and under defendant's contract with the City of Dunbar and the Bridge Commission it became entitled to receive a bonus for early completion in the amount of $197,340. Of this bonus, $97,340 was un *688 paid at the time of trial. On March 10, 1954, the final payment for construction (the total amount paid being $2,846,481.-89), as distinguished from bonus, was paid to defendant. On May 13, 1954, engineers from the City and Bridge Commission issued their certificate of completion of the bridge construction.

Defendant contends that the trial court erroneously permitted parol testimony to vary the terms of the contract; that the supplemental contract was without consideration in that plaintiff was obliged by the original contract to perform the services called for in the supplemental contract; in the alternative, that this suit is premature since it has not received “final payment for construction” of the bridge because of the balance due on the bonus payment; and finally, that the trial court’s award of interest on the amount of the judgment was erroneous. These contentions present the issues for consideration in this appeal.

The trial court did not err in admitting parol evidence to explain the meaning of “services outside the purely functional aspects of the other contract.” At the time defendant objected to the explanation offered by plaintiff, the trial court remarked, “Well, I am frank to say that I do not understand what it means,” and permitted the witness to answer the inquiry. We agree that this clause in the agreement is ambiguous and required an explanation.

Plaintiff then testified that the “functional aspects” meant “providing the money, the sale of the bonds.” It is undisputed that plaintiff did provide the required amount of financing for the bridge construction project.

Plaintiff further testified that he successfully handled problems dealing with rights-of-way and that the bonds to be issued could not be delivered without the consent of the Federal Reserve Credit Restraint Committee, which had been formed as a result of the Korean War. These services were actually within the province of the City Attorney of Dunbar, West Virginia, who was unable to perform them because of lack of experience in this type of work. In this connection, plaintiff was required to do considerable research and engage in time consuming activities in order to establish the military necessity for the bridge project. Plaintiff rendered these services and the trial court found that they were of benefit to defendant.

The admission of such testimony comes within the rule “that parol or extrinsic evidence is admissible to explain the purpose of the execution of a written instrument, what the parties intended, the consideration for its execution and the circumstances surrounding its execution.” Lincoln Nat. Life Ins. Co. v. Horwich, 7 Cir., 115 F.2d 892, 895-96 (1940).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Paloian v. GRUPO SERLA SA DE CV
433 B.R. 19 (N.D. Illinois, 2010)
Federal Insurance Co. v. I. Kruger, Inc.
829 So. 2d 732 (Supreme Court of Alabama, 2002)
Capitol Steel Fabricators, Inc. v. Mega Constr. Co.
58 Cal. App. 4th 1049 (California Court of Appeal, 1997)
Koch v. Construction Technology, Inc.
924 S.W.2d 68 (Tennessee Supreme Court, 1996)
A. J. Wolfe Co. v. Baltimore Contractors, Inc.
244 N.E.2d 717 (Massachusetts Supreme Judicial Court, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
297 F.2d 686, 1961 U.S. App. LEXIS 2851, Counsel Stack Legal Research, https://law.counselstack.com/opinion/marshall-f-dancy-v-william-j-howard-inc-a-corporation-ca7-1961.