A. J. Wolfe Co. v. Baltimore Contractors, Inc.

244 N.E.2d 717, 355 Mass. 361, 1969 Mass. LEXIS 791
CourtMassachusetts Supreme Judicial Court
DecidedFebruary 7, 1969
StatusPublished
Cited by39 cases

This text of 244 N.E.2d 717 (A. J. Wolfe Co. v. Baltimore Contractors, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A. J. Wolfe Co. v. Baltimore Contractors, Inc., 244 N.E.2d 717, 355 Mass. 361, 1969 Mass. LEXIS 791 (Mass. 1969).

Opinion

Cutter, J.

A subcontractor for electrical work (Wolfe) on a Cambridge apartment house owned by Frederick and Thomas Dupree (the owners) seeks, in an action at law, to recover from the general contractor (Baltimore) for amounts due under the subcontract and for extras and, by a bill in equity, to reach and apply a bond given by The Aetna Casualty and Surety Company (Aetna). The law action and the bill in equity were consolidated for trial and, after [363]*363trial, the trial judge ordered that they be “fused into a single proceeding,” i.e. the bill in equity.

The trial judge made somewhat summary findings which he later adopted as a report of material facts. Baltimore and Aetna appealed from the order of fusion and from what appears to be only an order including a form of final decree (a) awarding Wolfe $39,576.23 plus interest and costs, and (b) stating that, if Baltimore does not pay Wolfe in full, then Wolfe may resort to Aetna’s bond for payment. The evidence is reported. The parties have treated the order as embodying a final decree. We do so also, although appropriately a final decree should have been prepared by counsel and entered on the docket by the clerk. Rule 82 of the Superior Court (1954). See Bressler v. Averbuck, 322 Mass. 139,143; Nantucket Express Lines, Inc. v. Woods Hole, Martha’s Vineyard & Nantucket S.S. Authy. 350 Mass. 173, 174.

The action at law was commenced in the Superior Court for Suffolk County against Baltimore by writ dated December 6, 1965. It sought recovery of $39,576.23 alleged to be due under the subcontract. Baltimore’s answer included (in addition to a general denial) an allegation of breaches of the subcontract by Wolfe, references to certain terms of the subcontract (see fn. 7 and related text of this opinion), and averments that the owners had not made final payment to Baltimore and that a dispute had arisen between Baltimore and the owners concerning Wolfe’s work.

On February 13, 1967, Wolfe, in the action at law, by special precept purported to attach funds to the value of $44,000 owed to Baltimore by the owners both of whom were alleged to be of Cambridge (which is in Middlesex County). Baltimore filed a motion to dismiss the special precept on the ground that neither owner, served as trustee, dwelt or had a place of business in Suffolk County. See G. L. c. 246, § 2; Daniels v. Clarke, 193 Mass. 84, 85.2

On April 14, 1967, Wolfe filed against Baltimore and [364]*364Aetna 3 a bill to reach and apply certain assets of Baltimore. The bill also sought to have determined the amount, with interest, owed by Baltimore to Wolfe. It was alleged (a) that Wolfe had performed its work under its subcontract with Baltimore; (b) that Baltimore and the owners had submitted all disputes to arbitration, with the consequence that an award in favor of Baltimore had been paid in full; and (c) that, in order to obtain full payment of the award, Baltimore, with Aetna as surety, had furnished to the owners a bond in the penal sum of $44,000 naming Wolfe as obligee and guaranteeing “the payment of any judgment in favor of Wolfe against Baltimore.” The defendants were enjoined from cancelling or dealing with the bond. The owners were ordered to deliver the bond to the court. This was done.

The bond, entitled “Bond to Dissolve Trustee Attachment,” bears the file number of the equity suit. It recites the service of the special precept and that Baltimore, by giving bond, desires to "dissolve Ethel trustee attachment."4

The trial judge found (a) that Wolfe had “fully . . . performed all . . . services and furnished all . . . labor and materials . . . [[under] its subcontract” and that Baltimore owes Wolfe $9,348.70 on the subcontract; (b) that for change orders and extras, Baltimore owes Wolfe $30,227.53; (c) that Wolfe had paid the owners $500 and received a release from them on account of “minor and unintentional deviations” in Wolfe’s performance; (d) that Wolfe is entitled to interest on the sums and from the dates listed in the margin;5 and (e) that Aetna, on March 17,1967, [365]*365executed the $44,000 bond. The judge ruled that the bond required Aetna to pay to Wolfe any judgment against Baltimore (to the amount of the bond) if Baltimore fails to do so.

Baltimore and Aetna defend on two principal grounds: (a) that the evidence does not justify the finding that Baltimore was under liability to Wolfe, because (in effect) Wolfe did not produce evidence that the owners ever paid Baltimore amounts due to Baltimore for the several classes of work6 done by Wolfe; and (b) that despite the fusion of the law action with the equity proceeding, the judge erred in concluding that Wolfe may resort to Aetna’s bond.

1. Article II (a) of the subcontract provides that payment will be made on monthly requisitions for progress payments “within 10 days after . . . [the owners’] payment of such monthly progress payments . . . [has] been received by” Baltimore.7 Baltimore contends that its receipt of these payments from the owners is a condition precedent to any payment to Wolfe (of amounts requisitioned) and that Wolfe in order to recover must establish that Baltimore has been paid.

We interpret art. II (a) merely as setting the time of payment and not as creating a condition precedent to payment. In the absence of a clear provision that payment to the subcontractor is to be directly contingent upon the receipt by [366]*366the general contractor of payment from the owner, such a provision should be viewed only as postponing payment by the general contractor for a reasonable time after requisition (and completion of the subcontractor's work mentioned in the requisition) so as to afford the general contractor an opportunity to obtain funds from the owner. See Thos. J. Dyer Co. v. Bishop Intl. Eng. Co. 303 F. 2d 655, 659-661 (6th Cir.); Byler v. Great Am. Ins. Co. 395 F. 2d 273, 276-277 (10th Cir.). See also Trinity Universal Ins. Co. v. Smithwick, 222 F. 2d 16, 22-23 (8th Cir.) cert. den. 350 U. S. 837; Dancy v. William J. Howard, Inc. 297 F. 2d 686, 688-689 (7th Cir.); Darrell T. Stuart Contractor of Ariz. v. J. A. Bridges & Rust-Proofing, Inc. 2 Ariz. App. 63, 65; Mignot v. Parkhill, 237 Ore. 450, 457-461.8 Cf. Mascioni v. I. B. Miller, Inc. 261 N. Y. 1, 4-6 (paroi evidence received to explain intention of parties as imposing a condition and not merely setting time for payment); Nassau Suffolk Lumber & Supply Corp. v. Bruce, 177 Misc. (N. Y.) 825, 828 (County Court), mod. 265 App. Div. (N. Y.) 879.

Although no Massachusetts case directly controls the present situation, our decisions, in somewhat comparable situations, generally support our interpretation. See E. Van Noorden Co. v. Hartford Roofing & Sheet Metal Co. Inc. 336 Mass. 676, 678, citing Alvord v. Cook, 174 Mass. 120, 124-125, Rosenthal v. Schwartz, 214 Mass. 371, 373, and Canton v. Thomas, 264 Mass. 457, 459, three cases dealing with the date when a brokerage commission is due under an agreement that commission will be payable when “papers are [367]*367passed” or the agreement “is carried into effect.” See also C. J. Hogan, Inc. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Evans, Mechwart, Hambleton & Tilton, Inc. v. Triad Architects, Ltd.
965 N.E.2d 1007 (Ohio Court of Appeals, 2011)
Strecker v. Tavares
23 Mass. L. Rptr. 684 (Massachusetts Superior Court, 2008)
Wenger v. Aceto
22 Mass. L. Rptr. 81 (Massachusetts Superior Court, 2007)
Mechanical Construction Management, Inc. v. Dowd Plumbing Corp.
19 Mass. L. Rptr. 25 (Massachusetts Superior Court, 2005)
Coastline Fire Protection Co. v. Peabody Construction Co.
18 Mass. L. Rptr. 234 (Massachusetts Superior Court, 2004)
Framingham Heavy Equipment Co. v. John T. Callahan & Sons, Inc.
807 N.E.2d 851 (Massachusetts Appeals Court, 2004)
R L Acoustics v. Liberty Mutual Ins., No. Cv00 0380506s (Sep. 27, 2001)
2001 Conn. Super. Ct. 13161 (Connecticut Superior Court, 2001)
DeCarlo & Doll, Inc. v. Dilozir
698 A.2d 318 (Connecticut Appellate Court, 1997)
Blakeslee Arpaia Chapman, Inc. v. EI Constructors, Inc.
687 A.2d 506 (Supreme Court of Connecticut, 1997)
Canam Steel Corp. v. Bowdoin Construction Corp.
613 N.E.2d 121 (Massachusetts Appeals Court, 1993)
Ritz-Craft Corp. v. Stanford Management Group
800 F. Supp. 1312 (D. Maryland, 1992)
Massachusetts Municipal Wholesale Electric Co. v. Town of Danvers
411 Mass. 39 (Massachusetts Supreme Judicial Court, 1991)
MASSACHUSETTS MUNICIPAL WHOLESALE ELECTRIC v. Danvers
577 N.E.2d 283 (Massachusetts Supreme Judicial Court, 1991)
Colonial Mechanical Corp. v. Jesson & Frantz Contractors & Developers, Inc.
22 Va. Cir. 304 (Richmond County Circuit Court, 1990)
Mrozik Construction, Inc. v. Lovering Associates, Inc.
461 N.W.2d 49 (Court of Appeals of Minnesota, 1990)
Riverside Iron Works, Inc. v. Insurance of North America
156 A.D.2d 919 (Appellate Division of the Supreme Court of New York, 1989)
Statesville Roofing & Heating Co., Inc. v. Duncan
702 F. Supp. 118 (W.D. North Carolina, 1988)
Southern St. Masonry v. JA Jones Const.
507 So. 2d 198 (Supreme Court of Louisiana, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
244 N.E.2d 717, 355 Mass. 361, 1969 Mass. LEXIS 791, Counsel Stack Legal Research, https://law.counselstack.com/opinion/a-j-wolfe-co-v-baltimore-contractors-inc-mass-1969.