Framingham Heavy Equipment Co. v. John T. Callahan & Sons, Inc.

807 N.E.2d 851, 61 Mass. App. Ct. 171, 2004 Mass. App. LEXIS 507
CourtMassachusetts Appeals Court
DecidedMay 11, 2004
DocketNo. 02-P-1159
StatusPublished
Cited by7 cases

This text of 807 N.E.2d 851 (Framingham Heavy Equipment Co. v. John T. Callahan & Sons, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Framingham Heavy Equipment Co. v. John T. Callahan & Sons, Inc., 807 N.E.2d 851, 61 Mass. App. Ct. 171, 2004 Mass. App. LEXIS 507 (Mass. Ct. App. 2004).

Opinion

Dreben, J.

In December of 1997, the plaintiff, Framingham Heavy Equipment Company, Inc. (Framingham), an excavation subcontractor, entered into a written contract with a general contractor, John T. Callahan & Sons, Inc. (Callahan), to perform certain site work at the Lynn English High School for $594,000. At that time Callahan already had entered into a contract with the city of Lynn (city) for renovations and an addition to the school. Even before the subcontract was signed, unforeseen site conditions, including discovery of large quantities of peat and other materials unsuitable for a building foundation, were discovered beneath the site,2 which, as the excavations progressed, required extensive work beyond the scope of the subcontract. Although Framingham demanded payment for these and other changes, and although Callahan applied for payment for most of these changes from the city, by January 15, 1999, Framingham had received only a very small portion of the amount requested. On that date it brought this action claiming that Callahan was in breach of contract and seeking damages (alternatively in quantum meruit) of “at least $678,757.94,” most or all of which was for work required by changes requested by the general contractor or the city’s architect. The amount sought included work performed pursuant to a “construction change directive,” a matter discussed later in this opinion. Callahan counterclaimed, alleging that it was Framingham, rather than Callahan, who was in breach of contract by walking, off the job. After a four week jury-waived trial, a judge of the Superior Court, in a careful and well-reasoned memorandum, found Callahan in breach for nonpayment, excused Framingham from further performance, and entered a judgment for Framing-ham which, as amended, included damages of $572,049.64, of which all but $6,500 was for changes not covered in the original contract. He also awarded prejudgment interest of $186,568.18 [173]*173from the date of the filing of the lawsuit, attorney’s fees, and costs.

The defendants appeal, claiming that Callahan was not in breach because the subcontract included “pay when paid” provisions that required Callahan to pay Framingham only after it received payment from the city, and that even if the subcontract did not include such provisions, Callahan was entitled to a reasonable time to obtain payment from the city. They also claim that the judge erred in excusing Framingham from continuing to perform the work required under the contract documents and in awarding interest from the date the action was commenced. We affirm.

1. Facts. We take our facts from the findings of the trial judge, supplemented on occasion by undisputed testimony or exhibits. Framingham began work on the project in late October or early November, 1997. As previously indicated, unsuitable soil conditions required far more site work than originally anticipated. Framingham’s work was supervised on nearly a daily basis by Callahan’s job superintendent and by its project supervisor as well as by a “clerk of the works” employed by the city’s architect. All of these individuals were aware of the unsuitable materials which had been discovered underneath the proposed building addition and also in utility trenches.

In November, 1998, a construction change directive (CCD) was issued by the city and its architect for the removal of the unsuitable soil in the utility trenches.3 Under the CCD, the unit prices per cubic yard for the excavation and disposal of unsuitable soils and for replacement fill and stone were set at the same rate as under the original subcontract. On December 3, 1998, Callahan wrote to Framingham stating, inter alla, that (1) the CCD “guarantees that compensation will be made at least for [174]*174the values presented”4; (2) daily slips for the excavation of the peat were to be signed by the clerk of the works to “guarantee payment”; and (3) Framingham was to provide “the width of the trenches” in order to calculate the cubic yardage of material. Callahan had also written Framingham that the architect indicated he would allow the certified work in progress to be requisitioned monthly.

The work was performed, some of the daily work slips contained the width of the peat removed while some contained the depth, and the slips were signed by the city’s clerk of the works. Framingham requisitioned payment for this work on December 17, 1998; January 4, 1999; January 15, 1999; and on February 16, 1999, by which time the excavation on the utility trenches had been completed.5 The February 16 requisition documents explicitly set forth the cubic yardage of peat removed and fill provided and sought an amount which, together with the previous requisitions, totaled $180,266. Callahan in its December, 1998 and February and March, 1999 applications for payment included a line item for the CCD work. The city, however, struck the line item in these applications and on the March application noted “No CCD’s.” After the architect recommended approval of payment for the CCD work,6 Callahan again sought payment from the city, but the city once more struck the the item.7

By late February or early March, 1999, subcontractors in other trades were working in areas requiring excavation. As a [175]*175result, Framingham was running out of work and needed to move its equipment from the site and return later to finish the work. Framingham, with no protest from Callahan, removed its equipment.

At the time it took away its equipment, Framingham had not received any payment for its work under the CCD despite repeated requests. Its March, 1999 requisition shows claims for additional work of $76,184.14, so that the total claimed for changes, including the CCD work, was $754,944.14. No payments were received from Callahan8 in April, and on April 30, 1999, Framingham sent a letter to Callahan again demanding payment for the CCD and other work, asserting that Callahan’s failure to pay was a breach of the subcontract. The judge agreed, stating that “at least by the end of April, 1999,” Callahan was in breach of its contract with Framingham.

Although it did not send any money, Callahan continued to call Framingham to return to the site, and in June, 1999, requested documentation concerning the location where peat had been delivered and other information apparently sought by the city concerning the work covered by the CCD. The judge found that Framingham’s owner by this time was disgusted, and that he did not respond. On June 22, 1999, Callahan sent Framingham a letter stating it was terminating the subcontract. The next day Framingham wrote Callahan asserting that it, rather than Framingham, was in breach.

2. “Pay when paid” claim. Callahan’s primary claim on this appeal is that it was not in breach of contract for not paying Framingham because the subcontract documents contained “pay when paid” provisions, that is, payment to Callahan by the city was a condition precedent to payment by Callahan to Framingham. We are mindful that in construing such a contract, a condition precedent to payment may not be inferred; the contract must clearly state “that payment to the subcontractor is to be directly contingent upon the receipt by the general contractor of payment from the owner.” A.J. Wolfe Co. v. Baltimore Contractors, Inc., 355 Mass. 361, 365-366 (1969). See Jer[176]*176emiah Sullivan & Sons v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

U.W. Marx, Inc. v. Koko Contracting, Inc.
124 A.D.3d 1121 (Appellate Division of the Supreme Court of New York, 2015)
Evans, Mechwart, Hambleton & Tilton, Inc. v. Triad Architects, Ltd.
965 N.E.2d 1007 (Ohio Court of Appeals, 2011)
City Rentals, LLC v. BBC Co.
947 N.E.2d 1103 (Massachusetts Appeals Court, 2011)
Aimtek, Inc. v. Norton Co.
870 N.E.2d 1114 (Massachusetts Appeals Court, 2007)
Mechanical Construction Management, Inc. v. Dowd Plumbing Corp.
19 Mass. L. Rptr. 25 (Massachusetts Superior Court, 2005)
Coastline Fire Protection Co. v. Peabody Construction Co.
18 Mass. L. Rptr. 234 (Massachusetts Superior Court, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
807 N.E.2d 851, 61 Mass. App. Ct. 171, 2004 Mass. App. LEXIS 507, Counsel Stack Legal Research, https://law.counselstack.com/opinion/framingham-heavy-equipment-co-v-john-t-callahan-sons-inc-massappct-2004.