Chapman Excavating v. Fortney Weygandt, Unpublished Decision (7-22-2004)

2004 Ohio 3867
CourtOhio Court of Appeals
DecidedJuly 22, 2004
DocketCase No. 84005.
StatusUnpublished
Cited by5 cases

This text of 2004 Ohio 3867 (Chapman Excavating v. Fortney Weygandt, Unpublished Decision (7-22-2004)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chapman Excavating v. Fortney Weygandt, Unpublished Decision (7-22-2004), 2004 Ohio 3867 (Ohio Ct. App. 2004).

Opinion

JOURNAL ENTRY AND OPINION
{¶ 1} Plaintiff Chapman Excavating Co., Inc. ("Chapman") appeals from the order of the trial court which entered summary judgment in favor of defendant Fortney Weygant ("F W") in Chapman's action for recovery pursuant to a "pay-when-paid" provision in its contract with F W. F W cross-appeals and maintains that Chapman's action is barred because it did not arbitrate this claim. For the reasons set forth below, we reverse the order granting summary judgment to F W and remand this matter for further proceedings consistent with this opinion.

{¶ 2} On November 9, 1998, F W, as general contractor, and Chapman, as subcontractor, entered into "Work Order 2" an agreement pursuant to which Chapman would provide various grading, excavation, erosion control and other work on the Cypress Equity Site, owned by Cypress/Cleveland I Ltd.

{¶ 3} In relevant part, this agreement provided:

{¶ 4} "4. a. All progress payments are conditioned upon the Sub furnishing to F W 1) a signed copy of this work order * * * Partial payments of the Subcontract Sum shall be made within ten (10) days after payment is received by F W from Owner[.]

{¶ 5} "b. Final payment constituting the entire unpaid balance of the Subcontract Sum, shall be made by F W to the Sub when the Sub's work is fully performed in accordance with the requirements of the Contract Documents. * * *.

{¶ 6} "* * *

{¶ 7} "12. A Claim is a demand or assertion by Sub or F W seeking any remedy under, or adjustment or interpretation of, this work order. Any and all Claims by sub shall be made initially to F W's project manager in writing within twenty-one days of the event or occurrence giving rise to the claim. If a satisfactory resolution does not follow, or if forty-five days pass without a response from F W, the party making the claim may only pursue the claim further by filing a demand for arbitration * * * within twenty-one (21) days of F W's rejection of the claim, or within sixty-six (66) days of the initial filing of the claim if no response is made. * * *."

{¶ 8} On April 1, 2003, Chapman filed this action against F W and alleged that, pursuant to the terms of the parties' agreement, F W is required to pay Chapman even if it is not paid by the owner of the project, and that F W owes it $257,127.78. Chapman asserted claims for breach of contract, unjust enrichment and action on account. F W denied liability and asserted, inter alia, that Chapman's claims were subject to mandatory arbitration.

{¶ 9} On September 2, 2003, F W moved for summary judgment. Within this motion, F W asserted that it received its last progress payment from the owner, Cypress, on June 16, 2000. Since that time, F W issued three additional applications for payment to Cypress, and issued its request for final payment to Cypress in June 2002. Cypress has not paid F W, however, and on April 17, 2002, F W filed suit against Cypress in the Court of Common Pleas, see Fortney Weygant, Inc. v. Cypress/Cleveland I, Ltd.,et al., Cuyahoga Common Pleas Case No. 486273. F W claims that it is undisputed that Cypress owes F W $332,839.81 plus interest, and that F W anticipated reaching a settlement agreement with Cypress whereby it "will receive some payment up front, with the balance deferred over a period of time expected to stretch into 2005."

{¶ 10} F W also asserted that on June 16, 2000, it made two progress payments to Chapman (Applications #7 and # 8). On September 2000, Chapman requested that F W pay an additional progress payment and final payment to Chapman under the Work Order. The record further reveals that in March 2001, a question arose as to whether Chapman had double billed for a portion of the work and F W was subsequently credited in the amount of $24,450. F W has made no further payments to Chapman, however.

{¶ 11} F W further asserted that "[t]here is also no genuine issue of material fact that [F W] owes significant funds ($257,127.78) to Chapman for work performed on the Cypress Equity Project." Defendant's Motion for Summary Judgment at 4. F W acknowledged that its agreement with Chapman contains a "pay-when-paid" provision in which F W "made an absolute promise to pay Chapman, fixing payments by Cypress [the owner] to [F W] as reasonable time for [F W]'s payment to Chapman." Defendant's Motion for Summary Judgment at 7. F W insisted, however, that a "reasonable time" for payment "lasts until the prospect of payment from Cypress is impossible or, arguably, until [F W] demonstrates an unwillingness to pursue payment from Cypress.

{¶ 12} F W also maintained that Chapman's claims were barred by operation of the parties' contract because Chapman did not demand arbitration within the sixty-six day limitation period.

{¶ 13} In its brief in opposition, Chapman asserted that F W had failed to demonstrate that there was no genuine issue of material fact that a "reasonable time" for payment had not yet lapsed. Moreover, Carl Douglass, Jr., Chapman's Treasurer/Secretary, averred as follows:

{¶ 14} "It is * * * expected that a reasonable time for final payment would be longer than the time period needed to process progress payments. On this job, progress payments were due within ten (10) days. * * * For final payment on this job, a `reasonable time' to wait before payment would be due would be thirty (30) days, but no more than sixty (60) days."

{¶ 15} Chapman also asserted that the arbitration provision was waived when F W filed an answer in this matter, did not file a motion to stay proceedings pending arbitration, and engaged in extensive discovery. Chapman further claimed that F W was equitably estopped from invoking the arbitration provision, and Chapman presented evidence that F W's project manager repeatedly represented to Chapman that it was aggressively pursuing its rights against Cypress and would protect Chapman's rights. In addition, a F W representative had opined in deposition that demands for payment were not subject to the arbitration provision. In addition, counsel for Chapman averred that prior to trial, he inquired as to whether F W's attorneys would consent to arbitration but received no response from them. On December 15, 2003, the trial court entered summary judgment for F W. Relying upon the Article 4(a) of the parties' agreement, which pertains to "progress payments," the Court determined that payment was due under the "pay-when-paid" clause "within 10 days from the date F W receives payment from the owner."

Chapman's Appeal
{¶ 16} Chapman assigns the following error for our review:

{¶ 17} "The trial court erred as a matter of law in granting F W's motion for summary judgment."

{¶ 18} Within this assignment of error, Chapman asserts that the trial court erred in awarding summary judgment to F W because, inter alia, F W failed to meet its burden of proof. Chapman further asserts that the trial court erroneously converted the "pay-when-paid" provision into a "paid-if-paid" provision and incorrectly determined, in essence, that F W's "reasonable time" for payment would expire only when payment from Cypress becomes impossible.1

{¶ 19} With regard to procedure, we note that appellate review of summary judgment is de novo.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2004 Ohio 3867, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chapman-excavating-v-fortney-weygandt-unpublished-decision-7-22-2004-ohioctapp-2004.