Lafayette Steel Erectors, Inc. v. Roy Anderson Corp.

71 F. Supp. 2d 582, 1997 U.S. Dist. LEXIS 23587, 1997 WL 1168442
CourtDistrict Court, S.D. Mississippi
DecidedNovember 14, 1997
Docket1:96-cv-00065
StatusPublished
Cited by4 cases

This text of 71 F. Supp. 2d 582 (Lafayette Steel Erectors, Inc. v. Roy Anderson Corp.) is published on Counsel Stack Legal Research, covering District Court, S.D. Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lafayette Steel Erectors, Inc. v. Roy Anderson Corp., 71 F. Supp. 2d 582, 1997 U.S. Dist. LEXIS 23587, 1997 WL 1168442 (S.D. Miss. 1997).

Opinion

MEMORANDUM OPINION

DAN M. RUSSELL, Jr., District Judge.

This matter has been submitted to the Court on the memoranda and exhibits of the parties for a determination of the issues of fact and law.

Facts

. I. Stipulations.

The following facts are set out in the Pre-trial Order as stipulated by the parties:

A.Plaintiff, is a Louisiana corporation whose principal place of business is in the Parish of Lafayette, but which is authorized to do, and actually is doing business within the State of Mississippi.
B. The defendant is a Mississippi corporation whose principal place of business is in the State of Mississippi.
C. The plaintiff and defendant entered into a written contractual agreement whereby the plaintiff was to furnish specified labor, equipment and material to the defendant in connection with the construction of a project known as Treasure Bay Casino and Resort in Robinsonville, Mississippi.
D. The plaintiff fully completed all of its obligations under its subcontract with the defendant.
E. As of the date of completion of the plaintiffs subcontractual obligations, there was a- balance remaining on the plaintiffs subcontract in the principal sum of $512,899.48.
F. The owner of the Treasure Bay Casino project, Treasure Bay, Inc., has filed for relief under the United States Bankruptcy Code and has not paid the $512,899.48 to Anderson.

II. Findings of the Court.

The following facts are those determined by the Court from the exhibits and depositions placed in the record by the parties:

On September 27, 1993, the parties entered into a written subcontract wherein at Article 13, in pertinent part, it is set out:

The Amount will be paid as follows: Monthly payments will be made for 90% of the work approved by the GENERAL CONTRACTOR, and the Owner’s authorized representative, within ten days after the GENERAL CONTRACTOR receives payment from the Owner for the SUBCONTRACTOR’S work. Final payment will be made within ten days after the GENERAL CONTRACTOR receives final payment from the Owner providing the entire amount of work to be done hereunder has been accepted by *585 the Owner and a complete release of any and all claims against the GENERAL CONTRACTOR has been delivered by the SUBCONTRACTOR to the GENERAL CONTRACTOR (the acceptance of such release shall not relieve SUBCONTRACTOR of liability for defects in said work which may thereafter be discovered) and the GENERAL CONTRACTOR has not received any notice of any outstanding bills against' the SUBCONTRACTOR on this project. SUBCONTRACTOR agrees to await payment to the GENERAL CONTRACTOR by the Owner, unless the nonpayment is not caused by the SUBCONTRACTOR, in which case the GENERAL CONTRACTOR then agrees to pay the SUBCONTRACTOR within 10 days of written request for payment. If, however, the cause of non-payment is a result on the insolvency of the Owner, the CONTRACTOR agrees to use whatever reasonable means that are available to pursue payment to the SUBCONTRACTOR by the Owner.

Plaintiff submits, as Exhibit 3 to it’s trial brief, a computer print recap of pay requests submitted by the plaintiff to the defendant and amounts received by the plaintiff under the terms of the subcontract. According to entries of said exhibit, the defendant initially complied by paying the plaintiff 90% of amounts invoiced; making payments during the months of December, 1993 through March 10, 1994. These payments were for work done and invoiced from the beginning of the contract to November 24, 1993. However, according to the recap, the plaintiff received no significant payments from March 10, 1994 until August 29, 1994; at which time a lump sum of approximately $100,000.00 was paid on invoices submitted during December 1993.

Finally, said Exhibit 3 indicates that, as to invoices submitted from January, 1994 through March 14, 1994, the defendant made no further payments until September 9, 1994, at which time the sum of $394,388.00 was paid. The plaintiff continued to bill the defendant during the following months; however, no further payments have to date been made on the outstanding remaining balance.

According to the deposition testimony of Ronnie Prudhomme, at page 14, “[b]y February, 1994, the plaintiff had completed the performance of all of its work under the subcontract.” This testimony is uncontro-verted by the defendant and no where is it alleged that the plaintiffs work under the agreement was not satisfactory.

The record does not specifically set out when the owner applied for protection under the bankruptcy laws. It is clear, however, that after the plaintiff finished its part of the project satisfactorily, but before the owner indicated its alleged insolvent condition, the defendant had been paid for forty-three (43) percent of the total cost of the project. It is also admitted that the $394,388.00 sum was calculated as the amount of money needed to bring the total amount paid to the plaintiff up to forty-three percent of the total value of the plaintiff’s work.

Discussion and Conclusions of Law

I. Effect of Plaintiffs Negotiation of September 9 Check.

Although it is also hornbook law, the Court notes that the Mississippi Supreme Court, speaking in Anderton v. Business Aircraft, Inc., 650 So.2d 473, 475-476 (Miss.1995), succinctly set out:

“ ‘Any contract, however made or evidenced, can be discharged or modified by subsequent agreement of the parties.’ ’’Kelso v. McGowan, 604 So.2d 726, 731 (Miss.1992), quoting 3A. Corbin, Contracts § 574 at 373-75 (1960). In order for such a subsequent agreement to effect a modification, it must meet the requirements for a valid contract. Singing River Mall v. Mark Fields, Inc., 599 So.2d 938, 947 (Miss.1992). A valid contract requires an offer and acceptance. R.C. Const. Co. v. National Office Systems, 622 So.2d 1253, 1255 (Miss.1993), *586 citing Houston Dairy, Inc. v. John Hancock Mut. Life Ins. Co., 643 F.2d 1185, 1186 (5th Cir.1981).

It is also unquestionable that any attempt to modify a written contract “must be supported by new or additional consideration.” See Iuka Guar. Bank v. Beard, 658 So.2d 1367, 1372 (Miss.1995). And while this consideration need not be equal in value to the corresponding promise, it must consist of either a “benefit to the promisor or [some] loss, detriment, or inconvenience to the promisee.” Id.

The only questions which must be answered for a determination of this issue are (1) whether or not there was a meeting of the minds of the respective parties, i.e., an offer and acceptance, and (2) whether or not the check constituted a new or additional consideration.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
71 F. Supp. 2d 582, 1997 U.S. Dist. LEXIS 23587, 1997 WL 1168442, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lafayette-steel-erectors-inc-v-roy-anderson-corp-mssd-1997.