MidAmerica Construction Management, Inc. v. MasTec North America, Inc.

436 F.3d 1257, 2006 U.S. App. LEXIS 3022, 2006 WL 291663
CourtCourt of Appeals for the Tenth Circuit
DecidedFebruary 8, 2006
Docket04-6231
StatusPublished
Cited by61 cases

This text of 436 F.3d 1257 (MidAmerica Construction Management, Inc. v. MasTec North America, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MidAmerica Construction Management, Inc. v. MasTec North America, Inc., 436 F.3d 1257, 2006 U.S. App. LEXIS 3022, 2006 WL 291663 (10th Cir. 2006).

Opinion

EBEL, Circuit Judge.

In this case, we must determine'whether a contract between two defendant general contractors and a plaintiff subcontractor requires the general contractors to pay the subcontractor for the work the subcontractor performed only if the general contractors are first paid on their own contract with the project owner. In making this determination, we address the type of language that constitutes a “pay-if-paid” clause under both Texas and New Mexico law in a contract for a private-sector construction project.

*1259 We AFFIRM the district court’s grant of summary judgment to Defendants Mas-Tec North America, Inc. (“MasTec”) and Renegade of Idaho, Inc. (“Renegade”) on the claim of Plaintiff MidAmerica Construction Management, Inc. (“MidAmeri-ca”) that Defendants breached their contract with Plaintiff by refusing to pay Plaintiff for the work Plaintiff performed under the contract. We do so because we determine that (1) the contract contains a “pay-if-paid” clause; (2) this clause is enforceable under both Texas and New Mexico law; and (3) as a result, Defendants need not at the present time pay Plaintiff for the work that Plaintiff performed under the contract, because Defendants have not been paid by project owner PathNet, Inc. (“PathNet”) for that work.

BACKGROUND

PathNet hired Defendant Renegade to help construct the New Mexico and Texas portions of a fiber optic network. Defendant MasTec subsequently purchased Renegade. On January 31, 2001, Defendants hired Plaintiff as a subcontractor to help install a buried conduit for fiber optic line. The parties’ agreement was embodied in a written contract (the “Subcontract Agreement”).

Plaintiff began performing under the Subcontract Agreement. Defendants made an initial payment of approximately $127,000 to Plaintiff in March 2001 for work performed in January and February of that year. However, after PathNet filed for bankruptcy in April 2001, Defendants refused to make any further payments to Plaintiff because Defendants asserted that they had not received payment from PathNet for the work Plaintiff performed.

In November 2003, Plaintiff brought suit against Defendants in the United States District Court for the Western District of Oklahoma, contending that Defendants owed it approximately $1.9 million for work performed under the Subcontract Agreement. The district court denied Plaintiffs motion for partial summary judgment and granted Defendants’ counter-motion for summary judgment on all Plaintiffs claims. Specifically, the district court held that a provision in the Subcontract Agreement that provides that “all payments to Subcontractor by Contractor are expressly contingent upon and subject to receipt of payment for the work by Contractor from Owner,” was

unambiguous and makes Defendants (Contractor) receipt of payment for the work from PathNet (Owner) a condition precedent to payment of Plaintiff (Subcontractor). Thus, unless and until Defendants receive payment for the work in question from PathNet, Defendants have no duty to pay Plaintiff and Plaintiff acquires no right to enforce the promise of payment.

The court stated that:

applying either New Mexico or Texas law or the law of both states, the court enforces the contract as written and holds that Defendants have no obligation to pay Plaintiff unless or until PathNet pays Defendants.

The court also noted that:

because the Subcontract Agreement provides that it “may not be amended except by a writing signed by each of the parties,” and may not be modified or waived except in writing signed by both parties, [Defendant’s] single payment to [Plaintiff] could not effect a modification or waiver of the payment term making payment of [Plaintiff] “expressly contingent upon and subject to receipt of payment” by Defendants from PathNet.

Finally, the court found that a “termination clause” in the Subcontract Agree *1260 ment also barred Plaintiffs claims for breach of contract. 2

Plaintiff appealed from the district court’s order and judgment.

DISCUSSION

1. Jurisdiction, Standard of Review, and Choice of Law

Plaintiffs notice of appeal was timely filed. See Fed. R.App. P. 4(a)(1)(A). We exercise appellate jurisdiction over its appeal pursuant to 28 U.S.C. § 1291, reviewing the district court’s grant of summary judgment de novo. See Phillips v. New Hampshire Ins. Co., 263 F.3d 1215, 1218 (10th Cir.2001).

The Subcontract Agreement provides that the contract “is governed by the laws of the state where the Work is/was performed.” It is undisputed that Plaintiff performed work pursuant to the Subcontract Agreement in Texas and New Mexico. Neither party asserts that only one of these two states’ law should apply; rather, both parties assert that both states’ law should apply. Thus, if the Subcontract Agreement’s choice-of-law clause is enforceable, we must apply both Texas and New Mexico law in interpreting the agreement.

In cases like this one, where subject matter jurisdiction is based on diversity of citizenship, federal courts must look to the forum state’s choice-of-law rules to determine the effect of a contractual choice-of-law clause. See Lyon Dev. Co. v. Bus. Men’s Assur. Co., 76 F.3d 1118, 1122 (10th Cir.1996). Under the law of the forum state in this case, Oklahoma, “a contract will be governed by the laws of the state where the contract was entered into unless otherwise agreed and unless contrary to the law or public policy of the state where enforcement of the contract is sought.” Williams v. Shearson Lehman Bros., Inc., 917 P.2d 998, 1002 (Okla.Civ.App.1995) (emphasis added). Because in this case the parties agreed to be governed by the laws of Texas and New Mexico, we must determine whether the application of those states’ laws to the interpretation of the Subcontract Agreement would violate the law or public policy of Oklahoma as expressed in the state’s constitution, statutes, or judicial records. See Oliver v. Omnicare, Inc., 103 P.3d 626, 628-29 (Okla.Civ.App.2004); see also Cameron & Henderson, Inc. v. Franks, 199 Okla. 143, 184 P.2d 965, 972 (1947).

As is explained more fully below, we conclude that the Subcontract Agreement contains a “pay-if-paid” clause that is enforceable under both Texas and New Mexico law, making PathNet’s payment of Defendants a condition precedent to Defendants’ obligation to pay Plaintiff. Enforcing this clause does not yield a result that violates the law or public policy of Oklahoma. There are no Oklahoma cases interpreting “pay-if-paid” clauses, see John B. Hayes, Survey of Payment Provision and Trust Fund Statute: Oklahoma, 24 Construction Law. 20 (2004) — and thus there are no Oklahoma cases stating that Oklahoma does not enforce such clauses.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
436 F.3d 1257, 2006 U.S. App. LEXIS 3022, 2006 WL 291663, Counsel Stack Legal Research, https://law.counselstack.com/opinion/midamerica-construction-management-inc-v-mastec-north-america-inc-ca10-2006.