§ 779.135 — Construction contracts, form of contract.
Wisconsin § 779.135
This text of Wisconsin § 779.135 (Construction contracts, form of contract.) is published on Counsel Stack Legal Research, covering Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Wis. Stat. § 779.135 (2026).
Text
779.135 The following provisions in contracts for the improvement of land in this state are void:
779.135(1) (1) Provisions requiring any person entitled to a construction lien to waive his or her right to a construction lien or to a claim against a payment bond before he or she has been paid for the labor, services, materials, plans, or specifications that he or she performed, furnished, or procured.
779.135(2) (2) Provisions making the contract subject to the laws of another state or requiring that any litigation, arbitration or other dispute resolution process on the contract occur in another state.
779.135(3) (3) Provisions making a payment to a prime contractor from any person who does not have a contractual agreement with the subcontractor, supplier, or service provider a condition
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Tri-State Mechanical, Inc. v. Northland College
2004 WI App 100 (Court of Appeals of Wisconsin, 2004)
MC Cloud Construction, Inc. v. Home Depot USA, Inc.
149 F. Supp. 2d 695 (E.D. Wisconsin, 2001)
United States Ex Rel. Roach Concrete, Inc. v. Veteran Pacific, JV
787 F. Supp. 2d 851 (E.D. Wisconsin, 2011)
SJ Properties Suites v. Specialty Finance Group, LLC
864 F. Supp. 2d 776 (E.D. Wisconsin, 2012)
Wesner Development LLC v. Class One Professionals LLC
(E.D. Wisconsin, 2024)
State ex rel. Beck v. Lamb
2018 WI App 54 (Court of Appeals of Wisconsin, 2018)
Legislative History
779.135 History History: 1993 a. 213 ss. 164 , 165 ; Stats. 1993 s. 779.135; 2005 a. 204 .
Nearby Sections
15
§ 779.01
Construction liens.§ 779.02
Notice required to preserve lien rights; exceptions; saving clause; obligations of contractors.§ 779.05
Waivers of lien.§ 779.06
Filing claim and beginning action; notice required before filing; contents of claim document.§ 779.07
Judgment and lien docket.§ 779.08
Release of lien; undertaking.§ 779.10
Judgment.Cite This Page — Counsel Stack
Bluebook (online)
Wisconsin § 779.135, Counsel Stack Legal Research, https://law.counselstack.com/statute/wi/779.135.