United States Ex Rel. Roach Concrete, Inc. v. Veteran Pacific, JV

787 F. Supp. 2d 851, 2011 U.S. Dist. LEXIS 38229, 2011 WL 1330778
CourtDistrict Court, E.D. Wisconsin
DecidedApril 7, 2011
DocketCase 10-C-0826
StatusPublished
Cited by8 cases

This text of 787 F. Supp. 2d 851 (United States Ex Rel. Roach Concrete, Inc. v. Veteran Pacific, JV) is published on Counsel Stack Legal Research, covering District Court, E.D. Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. Roach Concrete, Inc. v. Veteran Pacific, JV, 787 F. Supp. 2d 851, 2011 U.S. Dist. LEXIS 38229, 2011 WL 1330778 (E.D. Wis. 2011).

Opinion

DECISION AND ORDER

WILLIAM C. GRIESBACH, District Judge.

Veteran Pacific, JV, a joint venture between Old Veteran Construction, Inc., and Pacific Construction Services, Inc. (collectively Veteran-Pacific), was the prime contractor for the construction of a new United States Army Reserve Center in Menasha, Wisconsin. Because the United States was the client, the project was covered by the Miller Act, which grants federal courts exclusive jurisdiction. 40 U.S.C. § 3133(b)(3)(B). The contract was with the U.S. Army Corps of Engineers, and Hartford Accident & Indemnity Company supplied the surety bond for the project which is required by the Miller Act. Veteran-Pacific entered into a subcontract with Roach Concrete, Inc., for concrete work on the project. Roach filed this suit against the Veteran-Pacific, claiming it is still owed $586,098.10 for concrete work it performed. Roach’s claims against Veteran-Pacific are for breach of contract, unjust enrichment, and quantum meruit. Roach’s claims against Hartford arise under the Miller Act and Section 628.46 of the Wisconsin Statutes. The case is be *854 fore the Court on the defendants’ motion to dismiss under Fed. R. Civil P. 12(b)(6). For the reasons set forth below the motion will be granted in part and denied in part.

FACTS ALLEGED

Roach alleges in its complaint that on or about July 25, 2007, Veteran-Pacific contracted with Roach to provide labor and material for the new Army Reserve center construction project. The parties executed a subcontract. (Compl., ¶ 10; Ex. A.) In the subcontract the parties agreed to a one year statute of limitations. Section 8.6 of the subcontract specifies that: “[a]ny action [by Roach] resulting from any breach on the part of Veteran-Pacific as to materials or labor provided hereunder must be commenced within one (1) year after the cause of action has accrued.” (Compl. Ex. A.)

Roach performed a significant amount of concrete work on the veteran’s center in 2007 and 2008 and was paid over $1.3 million by the Veteran-Pacific. (Compl., Ex. E.) Veteran-Pacific did not object to pay applications submitted by Roach but “consistently refused to make payment in full when due to Roach.” (Compl. ¶ 14.) As of March 12, 2008, Roach had submitted seven pay applications to Veteran-Pacific. Later that month Roach sent a letter to Veteran-Pacific concerning the overdue payments. (Id.) Veteran-Pacific did not respond satisfactorily and Roach submitted a notice of claim and demand for payment to Veteran-Pacific on June 11, 2008. (Compl. 15.) On September 23, 2008, having received no satisfaction from Veteran-Pacific, Roach submitted an Affidavit of Claim (the “Affidavit of Claim”) to Hartford for $586,098.10, the amount Roach believed Veteran-Pacific still owed. (Compl., ¶ 17; Ex. E.)

Roach continued to perform work on the Army Reserve project after the Affidavit of Claim was submitted to Hartford. (Compl. ¶ 18; Roach Response Br., Dkt. 18 at 5.) Roach alleges in its complaint that it “completed the furnishing of ... concrete materials and labor on September 27, 2009.” (Compl. ¶ 18.) Roach filed the complaint in this action on September 22, 2010.

ANALYSIS

The standards governing a motion to dismiss for failure to state a claim under Rule 12(b)(6) of the Federal Rules of Civil Procedure are well established. Rule 8(a) of the Federal Rules of Civil Procedure requires that a complaint contain a “short and plain statement of the claim showing that the pleader is entitled to relief.” In deciding whether it is sufficient to state a claim, the court must “accept! ] the complaint’s well-pleaded allegations as true and draw[ ] all favorable inferences for the plaintiff.” Killingsworth v. HSBC Bank Nevada, N.A., 507 F.3d 614, 618 (7th Cir.2007). The allegations must be sufficient “to give the defendant fair notice of what the ... claim is and the grounds upon which it rests.” Bell Atlantic Corp. v. Twombly, 550 U.S. 544, 555, 127 S.Ct. 1955,167 L.Ed.2d 929 (2007) (quoting Conley v. Gibson, 355 U.S. 41, 47, 78 S.Ct. 99, 2 L.Ed.2d 80 (1957)). “While a complaint attacked by a Rule 12(b)(6) motion to dismiss does not need detailed factual allegations, ... a plaintiffs obligation to provide the ‘grounds’ of his ‘entitle[ment] to relief requires more than labels and conclusions, and a formulaic recitation of the elements of a cause of action will not do.... Factual allegations must be enough to raise a right to relief above the speculative level.” Id. (citations omitted).

Generally, a court must limit its review to the allegations of the complaint in decid *855 ing a Rule 12(b)(6) motion to dismiss. When matters outside the pleadings are presented to and not excluded by the court, the motion should be treated as one for summary judgment under Rule 56. Fed.R.Civ.P. 12(d). An exception to this rule exists, however, as to documents that are referred to in the complaint and that are central to the plaintiffs claim. The court may consider those kinds of documents without converting the motion to one seeking summary judgment. Hecker v. Deere & Co., 556 F.3d 575, 582 (7th Cir.2009). If the plaintiff fails to attach such documents to the complaint, the defendant may submit them in support of his Rule 12(b)(6) motion to dismiss. Tierney v. Vahle, 304 F.3d 734, 738 (7th Cir.2002). And where the authenticity of such a document is undisputed, “[t]he court is not bound to accept the pleader’s allegations as to the effect of the exhibit, but can independently examine the document and form its own conclusions as to the proper construction and meaning to be given the material.” 5 Wright & Miller, Federal Practice & Procedure: Civil 2d, § 1327 at 766 (1990); Rosenblum v. Travelbyus.com Ltd., 299 F.3d 657, 661 (7th Cir.2002).

I. Breach of Contract

Count II of the Complaint asserts a breach of contract claim against Veteran-Pacific. (Compl. ¶ ¶ 26-29.) The defendants move to dismiss the claim on the ground that it is barred by the one-year statute of limitations contained in Roach’s subcontract with Veteran-Pacific. The subcontract provides that Roach had one year “after the cause of action has accrued” to file a claim. (See Compl. Ex. A, Subcontract, § 8.6.) Defendants argue that the cause of action accrued on September 23, 2008, and that Roach therefore had until September 23, 2009, in which to file suit. Since Roach did not file suit until September 22, 2010, Veteran-Pacific contends Roach’s suit is barred.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ver Hagen v. BeneTek Inc
E.D. Wisconsin, 2024
Murillo v. Kohl's Corp.
197 F. Supp. 3d 1119 (E.D. Wisconsin, 2016)
Le v. Kohls Department Stores, Inc.
160 F. Supp. 3d 1096 (E.D. Wisconsin, 2016)
Montano Electrical Contractor v. United States
114 Fed. Cl. 675 (Federal Claims, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
787 F. Supp. 2d 851, 2011 U.S. Dist. LEXIS 38229, 2011 WL 1330778, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-roach-concrete-inc-v-veteran-pacific-jv-wied-2011.