Hubble v. Lone Star Contracting Corp.

883 S.W.2d 379, 1994 WL 451319
Court of Appeals of Texas·Decided October 11, 1994·No. 2-93-264-CV·Published·Cited by 45 cases

Opinion

OPINION

LATTIMORE, Justice.

Appellant G. Craig Hubble, Trustee (“Hubble”), appeals from a judgment in favor of appellee Lone Star Contracting Corp. (“Lone Star”) in which the trial court foreclosed Lone Star’s mechanic’s and material-men’s hen on a three-acre tract (the “Property”) owned by Hubble. On appeal Hubble raises three points of error contending that the trial court erred: (1) in granting judgment foreclosing Lone Star’s hen on the Property because the hen is barred by limitations; (2) in failing to find that Lone Star’s cause of action accrued for limitations purposes more than four years before the filing date of this suit; and (3) in failing to grant Hubble a declaratory judgment that Lone Star’s hen was extinguished because the limitations period had run.

We affirm.

Lone Star is an earth moving contractor. Starting in 1983, Lone Star began work on a large contract at the south end of Lake Arlington known as the Enchanted Bays project. Though the work was done under one contract, it involved six different sections of land, each owned by a different partnership. All of the work involved in this suit was done on section six, which was owned by a partnership known as Park Lake Joint Venture (“Park Lake”). The agreement between Lone Star and Park Lake provided for monthly progress draws based on work actually performed during the preceding calendar month on estimates certified by the project engineer. The contract provided that five percent of each progress draw would be retained by the owner until the contract was completed. After about three years of work, Park Lake failed to pay four monthly progress draws that were due and payable on March 10,1986, April 10,1986, June 10,1986, and September 10, 1986. To protect its interests, Lone Star filed its lien affidavit on November 3, 1986. The hen was filed on all six sections of the project for a total claimed sum of $1,590,507.57, of which Lone Star attributed $108,632.01 to section six.

Charles G. Starnes and Associates, Inc. (“Starnes”) was the engineer on the Enchanted Bays project. When Starnes was not paid for its services, it filed a hen on section six of Enchanted Bays. Subsequently, Starnes filed suit against Park Lake to foreclose its hen and obtained a judgment ordering foreclosure of the hen on a three-acre tract (the “Property”) located within *381 section six. At the sheriffs sale, the Property was purchased by Hubble. Starnes did not notify Lone Star of its foreclosure, even though Lone Star had a lien on the Property. On October 31, 1990, Lone Star filed suit against Hubble, seeking foreclosure of its lien on that portion of section six owned by Hubble, and against Park Lake, seeking recovery of the sums due Lone Star by Park Lake. Hubble defended the action by asserting that Lone Star’s claim was barred by the four-year statute of limitations. Hubble also sought a' declaratory judgment that Lone Star’s lien on his property was extinguished by expiration of the limitations period. Park Lake filed for bankruptcy protection and did not participate in the trial of this case.

In the contract, Lone Star was referred to as “Contractor” and the landowners, including Park Lake, were referred to as “Owner.” Paragraph 4.10 of the contract states:

The Contract will be considered as having been fulfilled, save as provided in any bond or bonds or by law, when all the work and all sections or parts of the project covered by the Contract Documents have been finished and completed, the final inspection made by the Engineer, and final acceptance and final payment made by the Owner.

Paragraph 9.9 of the Contract provides for a final estimate and final payment when all work was finished and the Contract was complete. At completion the project engineer was to prepare a certificate of completion and final estimate of the work performed, which the Owner was to pay within thirty days. Paragraph 9.9 also provides that “[a]ll prior estimates upon which partial payment has been made are subject to necessary corrections or revisions on the final estimate.” Paragraph 4.8 addresses a situation where the Owner defaults before completion of the Contract:

In case the Owner shall fail to comply with the terms of this Contract and should fail or refuse to comply with said terms within ten (10) days after written notification by the Contractor, then the Contractor may suspend or wholly abandon the work and may remove therefrom all machinery, tools, and equipment and all materials on the project that have not been included in payments to the Contractor and have not been wrought into the work. And thereupon, the Engineer shall make an estimate of the total amount earned by the Contractor, which estimate shall include the value of all of the work actually completed by said Contractor at the prices stated in the attached Proposal, the value of all partially completed work at a fair and equitable price, and the amount of all extra work performed at the prices agreed upon or provided for by the terms of this Contract, and a reasonable sum to cover the cost of any provisions made by the Contractor to carry the whole work to completion, and which cannot be utilized. The Engineer shall then make a final statement of the balance due the Contractor by deducting from the above estimate all previous payments by the Owner and all other sums that may be retained by the Owner under the terms of this Agreement and shall certify same to the Owner who shall pay to the Contractor, on or before thirty (30) days after the notification by the Contractor, the balance shown by said final statement as due the Contractor under the terms of this Agreement.

A statutory mechanic’s lien is only an incident to the debt, and there can be no judicial foreclosure of the lien if the debt is barred by limitations. Holcroft v. Wheatley, 112 S.W.2d 298, 299 (Tex.Civ.App.—Amarillo 1937, writ dism’d). The applicable limitations period for an action on a debt contracted before September 1, 1989 is four years. 1 Tex.Civ.PRAC. & Rem.Code Ann. § 16.004 (Vernon 1986): Typically, construction is performed under a continuing contract. In a continuing contract, the contemplated performance and payment is divided into several parts or, where the work is continuous and indivisible, the payment for work is made in installments as the work is completed. *382 Godde v. Wood, 509 S.W.2d 435, 441 (Tex.Civ.App.—Corpus Christi 1974, writ ref'd n.r.e.); City and County of Dallas Levee Improvement Dist. v. Halsey, Stuart & Co., Inc., 202 S.W.2d 957, 961 (Tex.Civ.App.—Amarillo 1947, no writ). Thus, a construction contract continues until the work is completed by the contractor, with periodic progress payments made by the owner to the contractor based on estimates of the value of work completed in each period. Godde, 509 S.W.2d at 441.

Free access — add to your briefcase to read the full text and ask questions with AI

Hubble v. Lone Star Contracting Corp., 883 S.W.2d 379, 1994 WL 451319 (Tex. Ct. App. 1994).

883 S.W.2d 379 (Hubble v. Lone Star Contracting Corp.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Deborah Ann Walton v. Donal R. Delf, Jr.
Court of Appeals of Texas, 2022
Billy Ray Johnson v. Juan Pena Garcia
Court of Appeals of Texas, 2020
Lloyd Walterscheid & Walterscheid Farms, LLC v. Danny Walterscheid
557 S.W.3d 245 (Court of Appeals of Texas, 2018)
El Paso County v. Sunlight Enterprises Co., Inc.
504 S.W.3d 922 (Court of Appeals of Texas, 2016)
Estate of Norma L. Bessire
Court of Appeals of Texas, 2013
Beesley v. Hydrocarbon Separation, Inc.
358 S.W.3d 415 (Court of Appeals of Texas, 2012)
Holman Street Baptist Church v. Jefferson
317 S.W.3d 540 (Court of Appeals of Texas, 2010)
Pagosa Oil & Gas, L.L.C. v. Marrs & Smith Partnership
323 S.W.3d 203 (Court of Appeals of Texas, 2010)
Capstone Hlth. Equipmt. Servs. Ex Rel. Hlth. Sys. Grp. v. Qhhc
295 S.W.3d 696 (Court of Appeals of Texas, 2009)