Hassell Construction Co. Inc., Derivatively by and Through Its Shareholder, Royce Hassell R. Hassell & Company, Inc., and R. Hassell Builders, Inc. v. Springwoods Realty Company, Springwoods Realty, Inc., Harris County Improvement District 18, Walter P. Moore & Associates, Inc., D/B/A Walter P. Moore and Costello, Inc.

Court of Appeals of Texas·Decided March 7, 2023·No. 01-17-00822-CV·Published

Opinion

Opinion issued March 7, 2023.

In The

Court of Appeals

For The

First District of Texas

Inc. (collectively, “Appellants”) appeal the trial court’s summary judgment in favor of Appellees Springwoods Realty Company, Springwoods Realty, Inc., Harris County Improvement District #18, and Walter P. Moore & Associates, Inc., d/b/a Walter P. Moore (collectively, “Appellees”). In two issues, Appellants argue (1) the trial court erred by granting summary judgment in favor of Appellees based on limitations because Appellees failed to prove conclusively when Appellants’ causes of action accrued or, alternatively, there is a genuine issue of material fact regarding the accrual dates precluding summary judgment; and (2) the trial court abused its discretion by denying Appellants’ motion to abate the case in favor of Appellate Cause No. 01-17-00154-CV, an appeal involving the same set of facts and claims for damages, which another Panel of this Court previously decided. See R. Hassell & Co., Inc. v. Springwoods Realty Co., No. 01-17-00154-CV, 2018 WL 1864627 (Tex. App.—Houston [1st Dist.] Apr. 19, 2018, pet. denied) (mem. op.).

We affirm the trial court’s judgment.

Background1

This appeal is one of the latest judicial proceedings arising from three lawsuits involving the same construction project and contract. In August 2011, the Harris County Improvement District #18 (“District”) awarded Hassell Construction

1 The facts in this section are taken directly from this Court’s opinion in R. Hassell & Co., Inc. v. Springwoods Realty Co., No. 01-17-00154-CV, 2018 WL 1864627, at *1–4 (Tex. App.—Houston [1st Dist.] Apr. 19, 2018, pet. denied) (mem. op.).

Company, Inc. (“HCCI”) a contract for roadway construction of a project in Harris County, Texas (“Contract”). The project involved the construction of Springwoods Village Parkway and related water and sanitary sewer lines, paving, and traffic and drainage improvements in connection with ExxonMobil Corporation’s campus in Houston, Texas (“Project”).

HCCI and the District entered into the Contract 2 with HCCI acting as the “Contractor” and the District as the “Owner.” Pursuant to an attached “Special Condition” document, Springwoods Realty Company (“Springwoods”), the Project developer, was also considered an “Owner” for certain purposes under the Contract. 3 Springwoods was an “Owner” for purposes of approving requests for, and making payments to, the Contractor for any portion of the Contract price and “for paying all or any damages that might ever be due, including any costs associated with any change orders to the Contract.” Costello, Inc. (“Costello”), an engineer on the

2 The Contract also includes the Contract Documents attached to the Contract, including the Standard General Conditions of the Construction Contract.

3 On December 31, 2014, Springwoods Realty Company (1) quitclaimed its interest in the subject Project to a newly formed entity, Springwoods Realty, Inc., and (2)

transferred and assigned to the new entity the right, title, and interest in and to all contracts to which Springwoods Realty Company was a party and delegated all duties and obligations owed by Springwoods Realty Company under those contracts to Springwoods Realty, Inc. In 2015, Springwoods Realty Company, which had changed its name to Springwoods Old Realty Company, voluntarily dissolved. For purposes of this opinion, we refer to Springwoods Realty Company n/k/a Springwoods Old Realty Company and Springwoods Realty, Inc. collectively as “Springwoods.”

Project, designed the water and sanitary sewer systems and was tasked with approving or denying any submitted change orders.4 Walter P. Moore & Associates, Inc. (“WPM”), who also provided engineering and design services for the Project, designed all other improvements on the Project.

According to HCCI, the Contract contained material provisions integral to the timely completion of the Project’s scope of work, including provisions that “time was of the essence” and that “HCCI would be paid for the performance of the Scope of Work required by the drawings.” HCCI alleged that, after its work on the Project started, the District and Springwoods made over 500 revisions to the construction plans, which materially changed the scope of work, the Contract price, and the timeline of the Project. Appellants contend that although they properly submitted delay claims based on these revisions to WPM and Costello pursuant to the dispute- resolution procedures in the Contract, the District and Springwoods refused to pay for the changes and further accelerated the work, resulting in damage to HCCI. The parties attempted to resolve their disputes through the Contract’s dispute-resolution process. After their attempts proved unsuccessful, Appellants elected to submit their

4 Hassell also named Costello as a defendant in the underlying lawsuit, but it later nonsuited its claims against Costello prior to the trial court’s final judgment.

Consequently, the trial court did not rule on Costello’s motion for summary judgment, and Costello is not a proper party to this appeal. See Gray v. Allen, 41 S.W.3d 330, 331 n.2 (Tex. App.—Fort Worth 2001, no pet.) (stating “appellee”

must be party to final judgment and someone against whom appellant raises issues or points of error in its appellate brief).

payment claims to mediation, as permitted under the Contract. The parties mediated their delay claims unsuccessfully on July 2, 2012.

On July 26, 2012, HCCI sued the District and Springwoods based on their refusal to pay HCCI’s delay claims. Appellants contend that although HCCI filed suit on July 26, 2012, none of the parties to the lawsuit acted as if negotiations were at an impasse or that the Contract had been terminated. According to Appellants, they kept performing under the Contract through December 28, 2012. Appellants allege that they continued to negotiate their delay claims even after mediation proved unsuccessful, citing to correspondence exchanged between various parties from July 2012 until July 2013, when Appellants were officially removed from the Project. A. First Lawsuit (Trial Court Case Number 2012–42981)

On July 26, 2012, HCCI filed suit against the District and Springwoods (“First Lawsuit”). HCCI asserted claims against Springwood and the District for breach of contract and against Springwoods for fraud. In the alternative, HCCI asserted claims against the District under Texas Local Government Code section 271.153(a)(2), 5 and against Springwoods for assumpsit, quantum meruit, and unjust enrichment. The District and Springwoods each filed a third-party petition against WPM, who had provided engineering and design services on the Project. The District brought claims

5 TEX. LOC. GOV’T CODE § 271.153(a)(2) (governing breach-of-contract damages against local governmental entities, including amounts owed for change orders).

against WPM for breach of contract, breach of warranty, and negligence seeking indemnity. Springwoods asserted a negligence claim against WPM, also seeking indemnity. WPM, in turn, filed a third-party petition against Costello seeking contribution.

On September 15, 2014, R. Hassell & Company, Inc. (“RHC”) and Hassell Builders, Inc. (“RHB”)6 filed their First Petition in Intervention, alleging that RHC, RHB, and HCCI were partners, noting that its “joint venture relationship” with HCCI was disclosed to the District and Springwoods. RHC and RHB asserted that they provided project management and performed work on the Project using RHC’s and RHB’s equipment and personnel, and HCCI submitted RHC’s and RHB’s progress- payment reports to the District and Springwoods. HCCI, RHC, and RHB then split the proceeds received from the Project, with “99% to RHC [and RHB] and 1% to HCCI.”

RHC and RHB further alleged that HCCI had filed suit against Springwoods and the District “under the name HCCI representing the partnership.” RHC and RHB asserted that, “as a partner of HCCI,” they had a justiciable interest in HCCI’s

Free access — add to your briefcase to read the full text and ask questions with AI

Hassell Construction Co. Inc., Derivatively by and Through Its Shareholder, Royce Hassell R. Hassell & Company, Inc., and R. Hassell Builders, Inc. v. Springwoods Realty Company, Springwoods Realty, Inc., Harris County Improvement District 18, Walter P. Moore & Associates, Inc., D/B/A Walter P. Moore and Costello, Inc., (Tex. Ct. App. 2023).

Hassell Construction Co. Inc., Derivatively by and Through Its Shareholder, Royce Hassell R. Hassell & Company, Inc., and R. Hassell Builders, Inc. v. Springwoods Realty Company, Springwoods Realty, Inc., Harris County Improvement District 18, Walter P. Moore & Associates, Inc., D/B/A Walter P. Moore and Costello, Inc. (Hassell Construction Co. Inc., Derivatively by and Through Its Shareholder, Royce Hassell R. Hassell & Company, Inc., and R. Hassell Builders, Inc. v. Springwoods Realty Company, Springwoods Realty, Inc., Harris County Improvement District 18, Walter P. Moore & Associates, Inc., D/B/A Walter P. Moore and Costello, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

In Re Prudential Insurance Co. of America
148 S.W.3d 124 (Texas Supreme Court, 2004)
Schneider National Carriers, Inc. v. Bates
147 S.W.3d 264 (Texas Supreme Court, 2004)
In Re Kellogg Brown & Root, Inc.
166 S.W.3d 732 (Texas Supreme Court, 2005)
Via Net v. TIG Insurance Co.
211 S.W.3d 310 (Texas Supreme Court, 2006)
Citizens Insurance Co. of America v. Daccach
217 S.W.3d 430 (Texas Supreme Court, 2007)
Gym-N-I Playgrounds, Inc. v. Snider
220 S.W.3d 905 (Texas Supreme Court, 2007)
Equistar Chemicals, L.P. v. Dresser-Rand Co.
240 S.W.3d 864 (Texas Supreme Court, 2007)
Goodyear Tire and Rubber Co. v. Mayes
236 S.W.3d 754 (Texas Supreme Court, 2007)
Elledge v. Friberg-Cooper Water Supply Corp.
240 S.W.3d 869 (Texas Supreme Court, 2007)
Texas Mutual Insurance Co. v. Ledbetter
251 S.W.3d 31 (Texas Supreme Court, 2008)
Travelers Insurance Co. v. Joachim
315 S.W.3d 860 (Texas Supreme Court, 2010)
Exxon Corp. v. Emerald Oil & Gas Co., LC
348 S.W.3d 194 (Texas Supreme Court, 2011)
State v. Boyd
51 S.W.3d 206 (Court of Criminal Appeals of Tennessee, 2000)
Bailey v. Gardner
154 S.W.3d 917 (Court of Appeals of Texas, 2005)
Tri-State Chemicals, Inc. v. Western Organics, Inc.
83 S.W.3d 189 (Court of Appeals of Texas, 2002)
Hester v. Friedkin Companies, Inc.
132 S.W.3d 100 (Court of Appeals of Texas, 2004)
Solutioneers Consulting, Ltd. v. Gulf Greyhound Partners, Ltd.
237 S.W.3d 379 (Court of Appeals of Texas, 2007)
Williams v. Glash
789 S.W.2d 261 (Texas Supreme Court, 1990)