F. D. Rich Co. v. United States Ex Rel. Industrial Lumber Co.

417 U.S. 116, 94 S. Ct. 2157, 40 L. Ed. 2d 703, 1974 U.S. LEXIS 20
CourtSupreme Court of the United States
DecidedMay 28, 1974
Docket72-1382
StatusPublished
Cited by1,053 cases

This text of 417 U.S. 116 (F. D. Rich Co. v. United States Ex Rel. Industrial Lumber Co.) is published on Counsel Stack Legal Research, covering Supreme Court of the United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
F. D. Rich Co. v. United States Ex Rel. Industrial Lumber Co., 417 U.S. 116, 94 S. Ct. 2157, 40 L. Ed. 2d 703, 1974 U.S. LEXIS 20 (1974).

Opinions

Mr. Justice Marshall

delivered the opinion of the Court.

The Miller Act, 49 Stat. 793, as amended, 80 Stat. 1139, 40 U. S. C. § 270a et seq., requires a Government contractor1 to post a surety bond “for the protection of all persons supplying labor and material in the prosecution of the work provided for” in the contract. The Act further provides that any person who has so furnished labor or material and who has not been paid in full within 90 days after the last labor was performed or material supplied may bring suit on the payment bond for the unpaid balance. 40 U. S. C. § 270b (a). This case presents several unresolved issues of importance in the administration of the Act.

I

Between 1961 and 1968, petitioner F. D. Rich Co. was the prime contractor on numerous federal housing projects. During the years 1963-1966, much if not all of the plywood and millwork for these projects was supplied by Cerpac Co. The Cerpac organization was closely intertwined with Rich. The principals of Rich held a substantial voting interest in Cerpac stock, supplied a major share of its working capital, and were thoroughly familiar with its operations and financial condition.

On October 18, 1965, Rich contracted with the United States to build 337 family housing units at Beale Air [119]*119Force Base, California. Rich’s Miller Act surety, petitioner Transamerica Insurance Co., posted the payment bond required by the Act. Rich then awarded Cerpac two contracts on the project, one to select, modify, detail, and install all custom millwork, and one merely to supply all standard exterior plywood, each contract incorporating by reference terms of the prime contract. A similar arrangement was employed by Rich and Cerpac on other projects during this period.

On February 22, 1966, Cerpac placed a single order with respondent Industrial Lumber Co. for all exterior plywood required under its plywood contract for the Beale project. Industrial is a broker, purchasing wood products and materials for resale. It acknowledged the complete Cerpac order, purchased the plywood from its own suppliers and arranged for deliveries at the Beale site to begin on March 10, 1966. Each shipment was receipted as it arrived on the site by a Rich representative.

Shortly after Industrial’s shipments began, Rich informed Cerpac that more plywood was needed for another Government project being constructed in Charleston, South Carolina, for which Cerpac had also contracted to supply Rich with all exterior plywood. Rich and Cer-pac decided to divert some of the Beale lumber to Charleston. Accordingly, Industrial was advised to supply, a shipment of the plywood called for under its Beale contract with Cerpac to the South Carolina site. Industrial arranged for the wood to be shipped by one of its suppliers to a railhead near Charleston. The shipment diverted to South Carolina was one of 22 called for by Industrial’s Beale Contract.2 There were several subsequent shipments to the California site under that contract.

[120]*120During April and May 1966, Cerpac fell behind in its payments to Industrial, and on July 13, 1966, having not received payment on invoices for nine separate shipments, Industrial gave notice to Rich and its surety of a Miller Act claim and thereafter brought the instant action in the Federal District Court for the Eastern District of California.3 The District Court recognized that under our decision in MacEvoy Co. v. United States ex rel. Tomkins Co., 322 U. S. 102 (1944), Rich’s liability turned on whether Cerpac was a “subcontractor” within the meaning of the Act or merely a materialman. The District Court found that Cerpac was a subcontractor; hence Industrial, as its supplier, could assert a Miller Act claim against Rich, the prime contractor on the project. The District Court also rejected Rich’s claim that venue for suit on the South Carolina shipment was improper in the Eastern District of California. Accordingly, the District Court granted judgment for Industrial, holding Cerpac4 and Rich as primary obligees and Transamerica on its bond, jointly and severally liable for the amount of all nine unpaid invoices, $31,402.97, including the amount [121]*121due on the shipment diverted to South Carolina. The District Court, however, denied Industrial’s claim for attorneys’ fees.

Both Rich and Industrial appealed. The Court of Appeals affirmed the judgment against Rich in large part.5 On Industrial’s cross-appeal, the court reversed, holding that attorneys’ fees should have been awarded to Industrial as a successful plaintiff under the Miller Act, and remanded to the District Court for consideration of the amount of attorneys’ fees to be awarded. 473 F. 2d 720 (CA9 1973). We granted certiorari.6 414 U. S. 816 (1973). We affirm the judgment below to the extent it holds that Cerpac was a “subcontractor” for Miller Act purposes and that there was proper venue, but reverse as to the propriety of an award of attorneys’ fees.

II

Section 270a (a) (2) of the Miller Act establishes the general requirement of a payment bond to protect those who supply labor or materials to a contractor on a federal [122]*122project. Ordinarily, a supplier of labor or materials on a private construction project can secure a mechanic’s lien against the improved property under state law. But a lien cannot attach to Government property, see Illinois Surety Co. v. John Davis Co., 244 U. S. 376, 380 (1917), so suppliers on Government projects are deprived of their usual security interest. The Miller Act was intended to provide an alternative remedy to protect the rights of these suppliers.

The rights afforded by the Act are limited, however, by the proviso of § 270b (a). In MacEvoy Co. v. United States ex rel. Tomkins Co., supra, this Court construed § 270b (a) to limit the protection of a Miller Act bond to those who had a contractual agreement with the prime contractor or with a “subcontractor.” Those in more remote relationships, including persons supplying labor or material to a mere materialman, were found not to be protected. 322 U. S., at 109-111. Industrial was a supplier of materials to Cerpac. Thus, if Cerpac were a subcontractor for purposes of the Act, Industrial, having given the required statutory notice, could assert a Miller Act claim against Rich, the prime contractor. But, if Cerpac were merely a materialman, Industrial could not assert its Miller Act claim since it would be merely a supplier of materials to a materialman, a relationship found too remote in MacEvoy to enjoy the protections of the Act.

Petitioners assert that the courts below erred in finding Cerpac a subcontractor. Cerpac’s role under the plywood contract alone was that of a broker receiving standard lumber supplied by Industrial and, in turn, supplying it without modification to Rich.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rodríguez-Torres v. Government Development Bank
708 F. Supp. 2d 195 (D. Puerto Rico, 2010)
Bkcap, LLC v. Captec Franchise Trust 2000-1
701 F. Supp. 2d 1030 (N.D. Indiana, 2010)
In Re Emanuel
422 B.R. 453 (S.D. New York, 2010)
Mosser Construction, Inc. v. Travelers Indemnity Co.
665 F. Supp. 2d 875 (N.D. Ohio, 2009)
Empire Enterprises JKB, Inc. v. Union City Contractors, Inc.
660 F. Supp. 2d 492 (W.D. New York, 2009)
In Re Worldcom, Inc.
352 B.R. 369 (S.D. New York, 2006)
United States Ex Rel. Metric Electric, Inc. v. EnviroServe, Inc.
301 F. Supp. 2d 56 (D. Massachusetts, 2003)
GFI, Inc. v. Franklin Corp.
227 F. Supp. 2d 602 (N.D. Mississippi, 2002)
Sloan v. U.S. Department of Housing & Urban Development
196 F. Supp. 2d 16 (District of Columbia, 2002)
Tri-Star Pictures, Inc. v. Unger
42 F. Supp. 2d 296 (S.D. New York, 1999)
Fonar Corp. v. Magnetic Resonance Plus, Inc.
935 F. Supp. 443 (S.D. New York, 1996)
Balaber-Strauss v. Markowitz (In Re Frankel)
191 B.R. 564 (S.D. New York, 1995)
In Re Spectee Group, Inc.
185 B.R. 146 (S.D. New York, 1995)
United States Ex Rel. Capps v. Fidelity & Deposit Co.
875 F. Supp. 803 (M.D. Alabama, 1995)
Greenblatt v. Delta Plumbing & Heating Corp.
849 F. Supp. 247 (S.D. New York, 1994)
United States v. Sun Engineering Enterprises, Inc.
817 F. Supp. 1009 (D. Puerto Rico, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
417 U.S. 116, 94 S. Ct. 2157, 40 L. Ed. 2d 703, 1974 U.S. LEXIS 20, Counsel Stack Legal Research, https://law.counselstack.com/opinion/f-d-rich-co-v-united-states-ex-rel-industrial-lumber-co-scotus-1974.