Empire Enterprises JKB, Inc. v. Union City Contractors, Inc.

660 F. Supp. 2d 492, 2009 U.S. Dist. LEXIS 88839, 2009 WL 3127485
CourtDistrict Court, W.D. New York
DecidedSeptember 25, 2009
Docket05-CV-6461P
StatusPublished
Cited by3 cases

This text of 660 F. Supp. 2d 492 (Empire Enterprises JKB, Inc. v. Union City Contractors, Inc.) is published on Counsel Stack Legal Research, covering District Court, W.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Empire Enterprises JKB, Inc. v. Union City Contractors, Inc., 660 F. Supp. 2d 492, 2009 U.S. Dist. LEXIS 88839, 2009 WL 3127485 (W.D.N.Y. 2009).

Opinion

DECISION & ORDER

MARIAN W. PAYSON, United States Magistrate Judge.

INTRODUCTION

This case involves a breach of contract claim by Empire Enterprises JKB, Inc. (“Empire”) against Union City Contractors, Inc. (“Union City”) and a Miller Act claim, 40 U.S.C. §§ 3131 and 3133, against its sureties, Nova Casualty Company and Nova American Groups, Inc. (collectively, “Nova”). 1 Pursuant to 28 U.S.C. § 636(c), the parties have consented to the disposition of this case by a magistrate judge. (Docket # 7).

*495 Overview

In July 2004, the United States Army Corps of Engineers entered into a contract with Union City for the removal and disposal of tree debris and silt from the Mount Morris Dam in Livingston County, New York. Shortly thereafter, in August 2004, Union City entered into a subcontract with Empire, pursuant to which Empire agreed to chip and remove the tree debris, also referred to as “floatable debris,” from the dam. The contract required Union City to pay Empire $10 per cubic yard of debris chipped and removed from the site. Empire claims that it performed its contractual obligations by removing 11,470 cubic yards of material, but that Union City paid it only for approximately 3000 cubic yards. Empire seeks payment of the alleged balance, $84,653.63, plus interest. (Docket # 1, Ex. A). As an affirmative defense, defendants have asserted that Empire fraudulently and substantially overstated the quantity of debris that it removed from the dam site. (Docket # 31). 2

A bench trial was conducted in January 2008. The testimony at trial related principally to Empire’s work on the project, and specifically to the dispute over the quantity of debris that it chipped and removed during the course of that work. Defendants argue that the trial evidence demonstrates that Empire’s quantity calculations are not credible. Specifically, defendants contend that Empire’s representation that it removed 11,470 cubic yards of material is grossly inflated when compared with the historical data for the dam site. Second, defendants maintain that Empire’s record-keeping practices were unreliable and that Empire’s bills to Union City were fraudulently based upon Empire’s inaccurate records.

Empire counters that its calculations were accurate and that Union City accepted its performance when it signed Empire’s daily reports reflecting the quantity of debris chipped and removed each day. Empire further argues that Union City has waived its right to challenge the accuracy of Empire’s calculations by failing to contest the quantities reported until approximately three months after Empire had completed its work and Union City had issued two payments on the account.

Union City’s Bankruptcy

After trial and the submission of post-trial memoranda, defendants’ counsel advised this Court by letter that Union City had filed for bankruptcy under Chapter 7 of the Bankruptcy Code. The parties concede that, as a result of this filing, the automatic stay under Section 362 of the Code applies to Empire’s claims against Union City in this litigation. See 11 U.S.C. § 362. Because the stay has not been lifted, this Court may not determine Union City’s liability, if any, on Empire’s claim.

The automatic stay does not apply, however, to claims against the bankrupt debtor’s sureties. In re Capitol-York Constr. Corp., 43 B.R. 52, 55-56 (S.D.N.Y. *496 1984) (collecting cases). Thus, Empire’s Miller Act claim against Nova under the payment bond may proceed without violating the stay. Id. at 56 (“[a] subcontractor’s action against a general contractor’s surety to recover under a Miller Act bond which was posted to protect materialmen for public works projects does not implicate Code § 362 because the bond is not property of the debtor’s estate”). See United States ex rel. F & G Mech. Corp. v. Manshul Constr. Corp., 1998 WL 849327, *1 n. 7 (E.D.N.Y.1998) (due to post-trial bankruptcy of defendant contractor, court proceeded to determine liability under the Miller Act only of co-defendant surety).

Although some authority suggests that the Court may impose an equitable stay under these circumstances, see United States ex rel. Cent. Bldg. Supply, Inc. v. William F. Wilke, Inc., 685 F.Supp. 936, 938-39 (D.Md.1988) (affirming equitable stay because bankrupt contractor represented that it had good faith and valid defenses to subcontractor’s claim, but surety had no knowledge of such defenses), Nova’s counsel has not sought one. Moreover, I find that no basis in equity exists to impose one here considering that Nova has answered Empire’s complaint and has participated through counsel in the entirety of this litigation, including trial. For these reasons, I will proceed to determine Nova’s liability, if any, to Empire on its Miller Act claim.

FINDINGS OF FACT

I. The Parties

Empire is a land clearing, demolition and recycling business owned by Joseph Bartucca. (Tr. 7). Union City is a commercial construction company owned by Duane Cuyler; its business consists principally of contracts with federal government agencies. (Tr. 323-24). Nova is an insurance company that executed a payment bond in the amount of $161,100 for the Mount Morris Dam project. (Ex. 1).

II. The Tidal Witnesses

At trial, Empire called Joseph Bartucca (“Bartucca”), the owner and president of Empire, as its sole witness. (Tr. 6-109, 466-73). Defendants called four witnesses: Duane Cuyler (“Cuyler”), the owner and president of Union City (Tr. 322-466); Richard Collins (“Collins”), Union City’s project manager for the dam project (Tr. 111-239); Gerald DiPaolo (“DiPaolo”), a civil engineer with the United States Army Corps of Engineers (“ACE”) who served as the contracting officer’s representative during the project (Tr. 240-305); and, Heather Collins, who was employed by Union City and worked at the project site (Tr. 306-19). Deposition testimony of Jennifer Collins Bertrand, another Union City employee who worked at the dam site, was also admitted. (Tr. 360; Ex. O).

III. The August 2004 Mount Morris Dam Debris Removal Project

A. Annual Collection and Removal of Silt and Floatable Ti'ee Debris

The Mount Morris Dam is located on the Genesee River in Livingston County, New York, about forty-five miles south of Rochester, New York. ACE is responsible for operating and maintaining the dam. Each year ACE contracts with a private construction company to remove wood debris from the dam site and to redistribute silt from the dam’s spillways to the river basin upstream. (Tr. 243).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
660 F. Supp. 2d 492, 2009 U.S. Dist. LEXIS 88839, 2009 WL 3127485, Counsel Stack Legal Research, https://law.counselstack.com/opinion/empire-enterprises-jkb-inc-v-union-city-contractors-inc-nywd-2009.