United States Ex Rel. Susi Contracting Co. v. Zara Contracting Co.

146 F.2d 606, 1944 U.S. App. LEXIS 4227
CourtCourt of Appeals for the Second Circuit
DecidedDecember 18, 1944
Docket106
StatusPublished
Cited by61 cases

This text of 146 F.2d 606 (United States Ex Rel. Susi Contracting Co. v. Zara Contracting Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. Susi Contracting Co. v. Zara Contracting Co., 146 F.2d 606, 1944 U.S. App. LEXIS 4227 (2d Cir. 1944).

Opinion

CLARK, Circuit Judge.

Plaintiffs, Susi Contracting Co., Inc., and D’Agostino & Cuccio, Inc., brought this action under the provisions of the Miller Act, 40 U.S.C.A. § 270a et seq., in the name of the United States against Zara Contracting Co., Inc., and American Bonding Company of Baltimore, the surety on its bond, to recover o for work performed for and equipment supplied Zara in the performance of its contract with the United States, dated March 4, 1941, for the extension of Tri-Cities Airport, Endicott, New York. On April 2, 1941, Zara entered into a subcontract with plaintiffs, wherein plaintiffs agreed, except for one $100 item, to perform the entire work called for by the main contract with the United States. This work involved the excavation of material and placing, manipulating, rolling, and compacting it as a base and surface course for landing strips or runways. During the course of the excavation plaintiffs encountered unexpected soil conditions, mostly due to the presence of a great deal of clay material, which made progress of their work extremely difficult, caused the breakdown of their tools, and, according to their allegations, generally required the performance of work not called for by the contract. Consequently on several occasions they made demands on Zara for extra money; and eventually the dispute arose which led to mutual claims of breach of contract and, by easy stages, to the opposing claims for monetary solace of this action. At any rate, defendant Zara took over the completion of the contract about July 12, 1941, or two months after plaintiffs had begun work. It also took possession of and for some three months utilized the equipment furnished by plaintiffs at the contract site.

In this action plaintiffs alleged that Zara wrongfully terminated the subcontract, and sought recovery for the reasonable cost and value of the actual work performed, and the fair and reasonable rental value of the equipment for the period of its retention and use. Defendant Zara put in issue the material allegations of the complaint and also filed a counterclaim wherein it alleged that it was compelled to terminate the contract by plaintiffs’ refusal to perform it, and demanded damages for its breach against plaintiffs. Defendant American also put in issue the material allegations of the complaint and asserted further that plaintiffs had failed to state a claim against it upon which relief could .be granted. The District Court found generally for the plaintiffs, holding that Zara had wrong *608 fully terminated the contract and that there was due them $39,107.10 for work done at the contract rate, $18,600 for increased cost of excavation due to the soil conditions encountered, and $5,157.75 as rental allowance for plaintiffs’ equipment, less $43,345.20, the amount advanced by Zara during- the course of the work, or-a net of $19,519.65, together with interest from the date of the filing of the suit. All parties have appealed, plaintiffs because the rental allowance was too small, and both defendants because of the holding that Zara was the one who breached the contract and because of the allowance for increased cost of excavation. In addition, Zara claims damages, while American contends that in no event does the bond which it has given pursuant to the statute cover the rental allowance for equipment.

The first issue to be determined on this appeal is whether the court below correctly held that plaintiffs were prevented from continuing their contract by the action of defendant Zara and had not themselves breached their contract so as to bar them from recovering the fair value of labor performed prior to July 12, 1941, and the rental value of their equipment used by defendant Zara in the performance of the contract after that date. The supposed grounds of Zara’s termination of the contract are set out in a letter by Zara to plaintiffs, dated July 11, 1941. Some of these allegations are so obviously without substance that no purpose would be served by discussing them here. It does appear that one steam shovel used by plaintiffs was not in accord with the contract specifications, that plaintiffs failed to keep some of the equipment free from liens, so that Zara had to make advancements when installments became due and seizure imminent, and that plaintiffs were excavating 20,000 cubic yards a week, instead of the average of 27,000 cubic yards required by the contract. These grounds were waived by Zara, however, since no protest was made at the time of the alleged incidents of breach, though Zara was well aware of them, and plaintiffs were permitted to continue with the project. See Clark v. West, 193 N.Y. 349, 360, 86 N.E. 1; Hotchkiss v. City of Binghamton, 211 N.Y. 279, 283, 105 N.E. 410; S. & E. Motor Hire Corporation v. New York Indemnity Co., 255 N.Y. 69, 72, 174 N.E. 65, 81 A.L.R. 1318. It is clear that Zara could not in this way reserve the privilege to terminate the contract at any time. Cf. Herkcnham v. Hoenzsch, 211 App.Div. 224, 207 N.Y.S. 589; Bell v. Fox, 138 App.Div. 569, 123 N.Y.S. 310.

There is another reason which supports the court’s decision that Zara could not base its termination of the contract on plaintiffs’ failure to maintain the excavation schedule. Under the terms of the subcontract Zara could not terminate it because of delays “due to unforeseeable causes beyond the control and without the fault or negligence of the Sub-Contractor,” provided plaintiffs gave certain notices to the Government and certain steps were taken by the latter to fix the facts and extent of the delay. There were, however, unforeseen consequences in the nature of the soil encountered, about which fact revolve (as we shall see) the most controverted issues of the case. Sheet 1 of the plans forming part of the main contract set forth test borings showing that the subsoil surface over a considerable portion of the excavation area was of gravel, sand, and silt nature. Actual excavation disclosed, however, that the subsoil area was of a clay material, much more difficult and expensive to remove; and it was in consequence of this unforeseen condition that work was slowed down. Both Zara and the Government officials were thoroughly apprised of the situation; in fact Zara made it the grounds of a claim to the United States for additional compensation and received a substantial additional allowance. Even without this contract provision no termination would have been justified under the circumstances, cf. Lossing v. Cushman, 123 App.Div. 693, 108 N.Y.S. 368, reversed on other grounds 195 N.Y. 386, 88 N.E. 649; Gutman v. Crouch, 57 Hun 586, 10 N.Y.S. 275; with the provision it would have been clearly inequitable so to hold. 1

But Zara makes the further contention that the subcontract was terminated because of plaintiffs’ refusal to remove the clay material. The evidence shows that on July 8 and 9, plaintiffs interrupted their work and that on the latter day Joseph Susi, president of the Susi Company, said *609 in some heat that he would not dig anymore of that “lousy” material. But the evidence also indicates that work was resumed on July 10 and 11; and in view of the overwhelming testimony to the contrary, we cannot accept Zara’s rather farfetched and hypothetical proposition, based on mathematical formulae, that, since the amount of excavation on these days exceeded the daily average, plaintiffs must have failed to excavate the more difficult clay material. The testimony does indicate that on the days in question at least some of the excavation was in the clay area.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Hirani Engineering & Land
58 F.4th 1250 (D.C. Circuit, 2023)
Empire Enterprises JKB, Inc. v. Union City Contractors, Inc.
660 F. Supp. 2d 492 (W.D. New York, 2009)
United States Ex Rel. Maris Equipment Co. v. Morganti, Inc.
163 F. Supp. 2d 174 (E.D. New York, 2001)
Carlino v. Kaplan
139 F. Supp. 2d 563 (S.D. New York, 2001)
Bausch & Lomb Inc. v. Bressler
977 F.2d 720 (Second Circuit, 1992)
Bausch & Lomb Incorporated v. Bernard Bressler
977 F.2d 720 (Second Circuit, 1992)
Marisa Christina, Inc. v. Freis
646 F. Supp. 252 (S.D. New York, 1986)
Lee v. Foote
481 A.2d 484 (District of Columbia Court of Appeals, 1984)
Murdock-Bryant Construction, Inc. v. Pearson
703 P.2d 1206 (Court of Appeals of Arizona, 1984)
Action Engineering v. Alumina
18 V.I. 485 (Virgin Islands, 1981)
Constantino v. American S/T Achilles
580 F.2d 121 (Fourth Circuit, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
146 F.2d 606, 1944 U.S. App. LEXIS 4227, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-susi-contracting-co-v-zara-contracting-co-ca2-1944.