United States Ex Rel. Maris Equipment Co. v. Morganti, Inc.

163 F. Supp. 2d 174, 57 Fed. R. Serv. 1177, 2001 U.S. Dist. LEXIS 16129, 2001 WL 1141382
CourtDistrict Court, E.D. New York
DecidedSeptember 20, 2001
Docket96-CV-2205(FB), 96-CV-2854(FB), 97-CV-1543(FB)
StatusPublished
Cited by20 cases

This text of 163 F. Supp. 2d 174 (United States Ex Rel. Maris Equipment Co. v. Morganti, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. Maris Equipment Co. v. Morganti, Inc., 163 F. Supp. 2d 174, 57 Fed. R. Serv. 1177, 2001 U.S. Dist. LEXIS 16129, 2001 WL 1141382 (E.D.N.Y. 2001).

Opinion

DECISION AND ORDER

BLOCK, District Judge.

TABLE OF CONTENTS

INTRODUCTION.177

I. General Overview of the Litigation.178

II. Morganti’s Rule 50(b) Motion.180

A. Standard.180

B. Liability Issues.181

1. The Government’s Complicity.181

2. Waiver.185

C. Damage Issues.185

1. The Government’s Complicity.185

2. Profit and Overhead .187

Profit .188

Overhead.191

III. Morganti’s Rule 59(a) Motion.192

A. Standard.192

B. Morganti’s Claims Against Liberty.193

1. Breach of Obligation Under the Bond.193

2. Covenant of Good Faith and Fair Dealing.195

S. Tortious Interference With Contract.195

A Tortious Interference With Business Relations.196

C. The Jury Instructions.196

1. The Liability Charge.196

2. The Damage Charge.197

D. The Court’s Management of the Trial.198

IV. Maris’s Rule 50(b) Motion.198

A. The Release .199

B. Preclusion of Pre-January 1995 Costs.200

V. Prejudgment Interest.202

CONCLUSION.202

INTRODUCTION

This litigation arose out of the construetion of the new federal detention center in BrooHyn, New York (“Project”). Morgan-ti/Trataros Joint Venture (“Morganti”), the Project’s general contractor, and Maris *178 Equipment Company, Inc. (“Maris”), a subcontractor, each claimed that the other had breached their contract. 1 On July 7, 2000, following a four-week trial, bifurcated between liability and damages, a jury returned a verdict for Maris in the sum of $8,001,249. 2 Pending before the Court are Morganti’s Rule 50(b) and 59(a) motions raising a host of issues, as well as a Rule 50(b) motion by Maris challenging an adverse ruling on one of its damage claims. The Court must also rule on two reserved issues — whether Maris established its entitlement to profit and overhead as component parts of the damage award; a stipulated issue of law regarding the application of a certain release, and Maris’s request for prejudgment interest. For simplicity of presentation, the Court will address the reserved damage issues in the context of Morganti’s Rule 50(b) motion, and will address the release issue under Maris’s Rule 50(b) motion since it is inextricably intertwined with the damage claim raised by Maris in that motion. 3

I. General Overview of the Litigation

The Project called for the construction of a nine-story, thousand-cell facility at a cost of approximately $108,000,000. The agency in charge of the construction on behalf of the federal government was the Federal Bureau of Prisons (“FBOP”). In 1993, the FBOP chose Morganti as the general contractor. Morganti thereafter entered into a subcontract with Maris, dated September 28, 1993 (“Subcontract”), to fabricate and install the cells. The Subcontract price was $12,725,000 and required Maris to obtain a performance bond. Maris bonded with Liberty Bond Services, Inc. (“Liberty”).

Work on the Project was hampered by a series of delays, primarily due to the government’s faulty design; consequently, Maris experienced financial strains, which jeopardized its performance. Pursuant to an agreement between Maris and Liberty made in June 1995, Liberty provided financial assistance. It also hired Surety & Construction Consultants (“SCC”), a consulting engineering firm, to monitor Maris’s work. Based on reports from SCC that Morganti was mismanaging the Project and not honoring its payment obligations to Maris, Liberty concluded that Morganti had breached the Subcontract and terminated funding Maris’s performance. On May 3, 1996, at Liberty’s behest, Maris declared Morganti to be in default and walked off the job. These three litigations ensued.

Maris struck first, initiating Action # 1 on the same day it declared Morganti to be in breach. In this litigation, Maris sued Morganti and its sureties, defendants American Home Assurance Company and Seaboard Surety Company, under the Mil *179 ler Act, and sued Morganti for breach of contract under state law. Morganti counterclaimed for Maris’s breach.

On June 7, 1996, Morganti sued Liberty (“Action # 2”). Morganti alleged that Liberty (1) breached its obligations under its performance bond; (2) breached an implied covenant of good faith and fair dealing; (3) tortiously interfered with the Subcontract, and (4) tortiously interfered with Morganti’s business expectations.

On March 31, 1997, Industrial Acoustics Company, Inc. (“IAC”) filed an action against Maris and Liberty (“Action # 3”), claiming that Maris breached a subcontract with IAC. Maris impleaded Morganti, which, by counterclaim, reasserted its breach of contract claim against Maris.

By Court order dated October 15, 1997, all three actions were consolidated pursuant to Fed.R.Civ.P. 42(a). Action #3, however, was severed prior to trial.

Because a lien cannot attach to federal property, the Miller Act, 40 U.S.C. §§ 270a-270d, was enacted to provide subcontractors and suppliers on federal construction projects an alternate remedy to the mechanics’ lien ordinarily available on private construction projects. See J.W. Bateson Co., Inc. v. United States ex rel. Bd. of Trs. of the Nat’l Automatic Sprinkler Indus. Pension Fund, 434 U.S. 586, 589, 98 S.Ct. 873, 55 L.Ed.2d 50 (1978). Under the Miller Act, a contractor who performs “construction, alteration, or repair of any public building or public work of the United States” must provide two types of bonds: a “performance bond ... for the protection of the United States” against defaults by the contractor, and a “payment bond ... for the protection of all persons supplying labor and material.” 40 U.S.C. § 270a(a)(l), (2).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Hirani Eng'g & Land Surveying, P.C.
345 F. Supp. 3d 11 (D.C. Circuit, 2018)
Myklatun v. Halliburton Energy Services
734 F.3d 1230 (Tenth Circuit, 2013)
Boles v. Merck & Co.
742 F. Supp. 2d 460 (S.D. New York, 2010)
In Re Fosamax Products Liability Litigation
742 F. Supp. 2d 460 (S.D. New York, 2010)
Stillman v. InService America Inc.
738 F. Supp. 2d 480 (S.D. New York, 2010)
Travelers Casualty & Surety Co. v. Dormitory Authority-State
735 F. Supp. 2d 42 (S.D. New York, 2010)
US Ex Rel. King Mountain v. Rb Constructors, LLC.
556 F. Supp. 2d 1250 (D. Colorado, 2008)
Kauffman v. Maxim Healthcare Services, Inc.
509 F. Supp. 2d 210 (E.D. New York, 2007)
Tishman Westwide Construction LLC v. ASF Glass, Inc.
33 A.D.3d 539 (Appellate Division of the Supreme Court of New York, 2006)
EMI Music Marketing v. Avatar Records, Inc.
364 F. Supp. 2d 337 (S.D. New York, 2005)
Aniero Concrete Co. v. New York City Construction Authority
308 F. Supp. 2d 164 (S.D. New York, 2003)
TVT Records v. Island Def Jam Music Group
279 F. Supp. 2d 366 (S.D. New York, 2003)
Stoma v. Miller Marine Services, Inc.
271 F. Supp. 2d 429 (E.D. New York, 2003)
Morganti Inc. v. Liberty Bond Service, Inc.
67 F. App'x 68 (Second Circuit, 2003)
United States ex rel. Maris Equipment Co. v. Morganti, Inc.
175 F. Supp. 2d 458 (E.D. New York, 2001)
US EX REL. MARIS EQUIPMENT CO. v. Morganti
175 F. Supp. 2d 458 (E.D. New York, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
163 F. Supp. 2d 174, 57 Fed. R. Serv. 1177, 2001 U.S. Dist. LEXIS 16129, 2001 WL 1141382, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-maris-equipment-co-v-morganti-inc-nyed-2001.