United States Ex Rel. Varco Pruden Buildings v. Reid & Gary Strickland Co.

161 F.3d 915, 1998 WL 827699
CourtCourt of Appeals for the Fifth Circuit
DecidedDecember 1, 1998
Docket97-11068
StatusPublished
Cited by32 cases

This text of 161 F.3d 915 (United States Ex Rel. Varco Pruden Buildings v. Reid & Gary Strickland Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. Varco Pruden Buildings v. Reid & Gary Strickland Co., 161 F.3d 915, 1998 WL 827699 (5th Cir. 1998).

Opinion

PATRICK E. HIGGINBOTHAM, Circuit Judge:

This appeal resolves several claims for attorneys’ fees and interest stemming from the construction of an Air Force hangar in New Mexico. The ultimate resolution of the damage claims is not before us. We must decide whether to apply the law of Texas or the law of New Mexico and whether the claims for attorneys’ fees are efforts to recover attorneys’ fees as part of a Miller Act claim or state law claims supplemental to a Miller Act claim.

I.

In April 1993, Reid & Gary Strickland Company, a general contractor, submitted to the United States Corps of Engineers a bid to construct a six-bay hangar at Cannon Air Force Base near Clovis, New Mexico. On June 4, 1993, Strickland signed and returned to Vareo Pruden Buildings, Inc., a purchase order for metal building components needed to complete the hangar. The purchase order was signed and returned to avoid a possible price increase and was contingent upon the award of the hangar contract to Strickland. The form provided that the transaction would be governed by the laws of Tennessee.

The United States awarded the hangar contract to Strickland on August 2,1993. On the same day, Strickland submitted an order form to Vareo Pruden which stated that Var-eo Pruden would furnish the pre-fabricated and pre-engineered metal building necessary for the completion of the hangar in return for $607,865.00. The August 2, 1993, purchase order provided that Texas law would govern the transaction. Vareo Pruden returned the form on March 15,1994.

Pursuant to the Miller Act, Strickland and St. Paul Fire and Marine Insurance Company executed and delivered to the United States on August 3 a payment bond for $6,833,599.2s. 1

On August 9, Strickland and File-Steele Erectors Company executed two subcontracts for the hangar project. One subcontract was for the unloading and erecting of all reinforcing steel, and the other was for the erection of the structural steel and the metal building.

Vareo Pruden delivered the metal building components to the job site in New Mexico, but the components were non-conforming, defective, and mismarked. As a result, File-Steele had to perform additional work — labor not originally contemplated in its subcontract with Strickland — to remedy the problems. At various times throughout the project, representatives of both Strickland and Vareo Pruden assured File-Steele that it would be paid for its extra work on the project.

In March 1994, Vareo Pruden agreed directly with File-Steele to pay File-Steele for the extra work. Pursuant to this arrangement, File-Steele submitted extra work “tickets” to Strickland so that Strickland could confirm that File-Steele had actually performed the work denoted on the tickets. Strickland then returned the tickets to File- *918 Steele for pricing; after File-Steele placed prices on the tickets, it returned them to Strickland for forwarding to Vareo Pruden.

At the end of the project, Vareo Pruden had not received full payment from Strickland, and File-Steele had not been paid for its extra work. In addition, Strickland still owed File-Steele $8,344.38 under its original contract.

Vareo Pruden filed a Miller Act claim against Strickland in federal district court in New Mexico. The case was transferred by stipulation to the district court for the Northern District of Texas. Strickland counterclaimed against Vareo Pruden, alleging breach of contract, and filed a third-party claim against File-Steele, seeking a declaratory judgment to determine the correct amount owed by Strickland to File-Steele. In its answer and counterclaim to the third-party complaint, File-Steele asserted Miller Act and state law claims against Strickland, St. Paul, and Vareo Pruden.

The case was tried to the bench for nine days. The court awarded File-Steele $238,-645.97 from Strickland and St. Paul for File-Steele’s extra work. The amount was offset by $44,403.51 — payments Strickland previously had made to File-Steele as an incentive to continue with the project. The court also awarded File-Steele $8,344.38 against Strickland under the original subcontract. The trial court found against File-Steele on its claim against Strickland for delay damages and on its claim against Strickland and Vareo Pruden for fraud and misrepresentation.

The court awarded Strickland $11,057.66 against Vareo Pruden on its breach of contract claim, and the court found that Vareo Pruden was liable to Strickland for the $44,-403.07 that Striddand had paid for File-Steele’s extra work. The court also found that Strickland was entitled to indemnification from Vareo Pruden for the remaining amounts awarded to File-Steele for extra work — $194,242.46. These amounts were offset by the amount still owed Vareo Pruden by Strickland, $244,939.00, making a net award to Strickland against Vareo Pruden of $4,764.63. That is, assuming that Strickland or St. Paul would pay File-Steele the $194,-242.46 for the extra work, Vareo Pruden would owe Strickland $4,764.63, exclusive of attorneys’ fees and prejudgment interest. The trial court found against Strickland on its claims against Vareo Pruden for delay damages and on its claims under the Texas Deceptive Trade Practices Act and the New Mexico Uniform Trade Practices Act.

Finally, the court awarded to File-Steele attorneys’ fees of $116,708.16 against Strickland and Vareo Pruden, jointly and severally, for which Vareo Pruden had to indemnify Strickland, and it awarded Strickland fees of $71,879.85 against Vareo Pruden.

II.

First, Vareo Pruden and Strickland appeal the district court’s award of attorneys’ fees against them to File-Steele. Awards of attorneys’ fees are generally reviewed for abuse of discretion, but application of the correct legal standard is reviewed de novo. See United States ex rel. Leno v. Summit Constr. Co., 892 F.2d 788, 790 (9th Cir.1989).

It is undisputed that attorneys’ fees can not be awarded in Miller Act claims absent an enforceable contract provision or evidence of bad faith. See F.D. Rich Co., Inc. v. United States ex rel. Industrial Lumber Co., Inc., 417 U.S. 116, 126-31, 94 S.Ct. 2157, 40 L.Ed.2d 703 (1974). Vareo Pruden and Strickland argue that this is solely a Miller Act case: File-Steele pressed no state law causes of action, and the trial court did not find in favor of File-Steele on any state law claim. Thus, pursuant to F.D. Rich, if this case is solely a Miller Act case, the award of attorneys’ fees pursuant to state law was improper.

File-Steele did assert state law claims against Strickland and Vareo Pruden over which the court exercised supplementary jurisdiction, and the district court awarded attorneys’ fees under those claims. The Pretrial Order clearly states that File-Steele sought recovery under state law. Further, the district court held that File-Steele was entitled to recover attorneys’ fees on its state law causes of action. We do not read F.D. Rich to prohibit an award of attorneys’ fees under a state claim over which the court has

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
161 F.3d 915, 1998 WL 827699, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-varco-pruden-buildings-v-reid-gary-strickland-co-ca5-1998.