United States Ex Rel. Metric Electric, Inc. v. EnviroServe, Inc.

301 F. Supp. 2d 56, 2003 U.S. Dist. LEXIS 24492, 2003 WL 23220233
CourtDistrict Court, D. Massachusetts
DecidedNovember 24, 2003
DocketCIV.A.01-10616-GAO
StatusPublished
Cited by10 cases

This text of 301 F. Supp. 2d 56 (United States Ex Rel. Metric Electric, Inc. v. EnviroServe, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. Metric Electric, Inc. v. EnviroServe, Inc., 301 F. Supp. 2d 56, 2003 U.S. Dist. LEXIS 24492, 2003 WL 23220233 (D. Mass. 2003).

Opinion

MEMORANDUM OF DECISION

TIMOTHY BELCHER DYK, Circuit Judge. 1

The plaintiff in this case, Metric Electric, Inc. (“Metric”) asserts claims under the Miller Act (40 U.S.C. § 3133) 2 and Massachusetts Unfair and Deceptive Trade Practices Law (M.G.L. c. 93a, §§ 2, 11) against the defendant surety, National Union Fire Insurance Company of Pittsburgh (“National Union”). The plaintiff has abandoned its claims against the defendant general contractor, EnviroServe, Inc. (“EnviroServe”). The parties agreed to trial without a jury. I make the following findings of fact and rulings of law pursuant to Rule 52 of the Federal Rules of Civil Procedure.

FINDINGS OF FACT

I.The Parties and the Subcontract

1. The plaintiff, Metric, is a corporation organized under the laws of Massachusetts with a principal place of business in Georgetown, Massachusetts. (Pretrial Order, Agreed Facts p. 6.)

2. The defendant, National Union, is a corporation organized under the laws of Pennsylvania with a principal place of business in New York, New York. (Pretrial Order, Agreed Facts p. 6.)

3. AIG Technical Services, Inc. (“AIG”) is the parent company of National Union. (Tr. 1, p. 3,11. 7-8.)

4. The defendant, EnviroServe, was a corporation organized under the laws of Maryland with a principal place of business in Sykesville, Maryland. (Pretrial Order, Agreed Facts p. 6.)

5. EnviroServe is no longer in business, and Metric does not seek to recover from EnviroServe on any of the claims brought in this action. (Tr. 1, p. 56, 11. 3-12.)

6. On August 24,1999, the Army Corps of Engineers (“the ACOE”) entered into a contract with EnviroServe to renovate a barracks known as Building 15 located at the United States Army Soldier Systems Center in Natick, Massachusetts (“the Project”). (Pretrial Order, Agreed Facts p. 6; Pl.Ex. 1).

7. On August 24, 1999, National Union agreed to serve as surety for the Project and issued a Miller Act bond (“the bond”) in accordance with 40 U.S.C. § 270a (since amended and moved to 40 U.S.C. § 3131) for the sum of $837,946.80. (Pretrial Order, Agreed Facts p. 6; Pl.Ex. 22). The bond stated that the “Surety [National Union] binds itself, jointly and severally with the Principal [EnviroServe], for payment” up to the “full amount of the penal sum.” (Pl.Ex. 22.) The bond further provided that it was “for the protection of persons supplying labor and material ... [as] required under the Act ... (40 U.S.C. 270a-270e).” Id. at 2.

*60 8. On October 5, 1999, Metric entered into a contract (“the subcontract”) for $293,406.00 with EnviroServe under which Metric agreed to perform electrical work on the Project. A subsequent change order, executed on March 8, 2000, increased the value of the subcontract to $305,000.00. (Pretrial Order, Agreed Facts p 6.)

9. The subcontract provided in relevant part that:

a. “The Contractor [EnviroServe] shall pay the Subcontractor [Metric] each progress payment within seven (7) working days after the Contractor receives payment from the Owner [the ACOE].” (Pl.Ex. 1, Art 11.3.)
b. “If the Subcontractor persistently or repeatedly fails or neglects to carry out the Work ... or otherwise to perform in accordance with this Agreement and fails within seven (7) days after receipt of written notice to commence and continue correction of such default or neglect ... the Contractor may, after seven (7) days following receipt by the Subcontractor of an additional written notice ... terminate the Subcontract and finish the Subcontractor’s Work .... If the unpaid balance of the Subcontract Sum exceeds the expense of finishing the Subcontractor’s Work, such excess shall be paid to the Subcontractor, but if such expense exceeds such unpaid balance, the Sub contractor [sic] shall pay the difference to the Contractor.” (Pl.Ex. 1, Art. 7.2.1.)
c. “Based upon applications for payment submitted to the Contractor by the Subcontractor, corresponding to Applications for Payment submitted by the Contractor to the Architect, and Certificates for Payment issued by the Architect, the Contractor shall make progress payments on account of the Subcontract Sum to the Subcontractor .... ” (PLEx. 1, Art. 11.1.)
d.“Provided an application for payment is received by the Contractor not later than the 23rd day of a month, the Contractor shall include the Subcontractor’s Work covered by that application in the next Application for Payment which the Contractor is entitled to submit to the Architect. The Contractor shall pay the Subcontractor each progress payment within seven (7) working days after the Contractor receives payment from the Owner [the ACOE].” (PLEx. 1, Art. 11.3.)

1. The subcontract did not contain any provision for attorneys’ fees in the event of litigation between EnviroServe and Metric. (PLEx. 1.) The bond also did not provide for attorneys’ fees in the event of litigation between Metric and National Union. (PL Ex. 22.)

II. Metric’s Work on the Project

2. Metric’s work on the Project consisted primarily of performing temporary wiring, electrical demolition and repairs and installing conduit. (Pl.Ex. 4, 5 and 6; Tr. 1, p. 81, 11. 21-23; p. 124, ll. 11-12; p. 134, ll. 8-16).

3. On December 13,1999, Metric began work on the Project. Metric had workers at the site on December 13-15, 21, 23, 27, 29 and 30; January 7 and 24-27; February 14, 16, 17, 24 and 25; March 1, 10, 17, 20-22 and 29; April 3-5, 11, 12, 14, 17-21 and 24-28; May 1-5, 8-12 and 15-18. (PL Ex. 16.) Metric’s last day working on the project was May 18, 2000. Id.

4. When Metric began work on the Project, the Project was already behind schedule. (Tr. 1, p. 199, ll.6-11.) Asbestos abatement and the construction of certain steel-stud wall frames, both necessary predicates to some of Metric’s work, had *61 not been completed before Metric’s arrival on the worksite. (Tr. 1, p. 23, ll. 11-20; Id. at p. 200,1. 6 — p. 201,1.11). Moreover, the building being renovated was not sufficiently weatherproof and its interior often became wet when it rained. (Tr. 1, p. 23, ll.11-23.) These factors combined were the major cause of delay in Metric’s work under the subcontract. (Tr. 1, p. 23 ll. 17-20; Id. at p. 201, ll.12-13).

5. Metric’s president, Brian Sampson, decided that the building transformer was unsafe because of standing water in the transformer room. (Tr. 1, p.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
301 F. Supp. 2d 56, 2003 U.S. Dist. LEXIS 24492, 2003 WL 23220233, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-metric-electric-inc-v-enviroserve-inc-mad-2003.