United States, for Use and Benefit of Pertun Construction Company v. Harvesters Group, Inc., National Union Fire Insurance Company of Pittsburgh, Pa.

918 F.2d 915, 36 Cont. Cas. Fed. 75,979, 1990 U.S. App. LEXIS 20991
CourtCourt of Appeals for the Eleventh Circuit
DecidedDecember 7, 1990
Docket89-5601, 89-6041
StatusPublished
Cited by33 cases

This text of 918 F.2d 915 (United States, for Use and Benefit of Pertun Construction Company v. Harvesters Group, Inc., National Union Fire Insurance Company of Pittsburgh, Pa.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States, for Use and Benefit of Pertun Construction Company v. Harvesters Group, Inc., National Union Fire Insurance Company of Pittsburgh, Pa., 918 F.2d 915, 36 Cont. Cas. Fed. 75,979, 1990 U.S. App. LEXIS 20991 (11th Cir. 1990).

Opinion

EDMONDSON, Circuit Judge:

This Miller Act case presents two basic questions on appeal. The first is a matter of first impression in this circuit: When a prime contractor causes delay in the progress of a federal government project, can the subcontractor recover from the prime contractor’s Miller Act surety for the increases, resulting from the delay, in its actual expenditures for labor and material actually supplied to the project? And the second is an issue of contract interpretation and application: Assuming recovery from the surety for the costs of delay is generally available under the Miller Act, will the subcontractor’s recovery nonetheless be barred if the subcontract agreement provides that the subcontractor’s sole remedy for delay will be an extension of time to perform, but the prime contractor has in fact wrongfully prevented the subcontractor from completing performance? We hold that the Miller Act allows recovery from the surety for increased out-of-pocket costs caused by delay and that the subcontract provision regarding no damages for delay does not preclude recovery under these circumstances. We therefore affirm the bulk of the district court’s award below. 1 Because we find the district court’s determination of additional costs incurred due to pre-commencement delay clearly erroneous, however, we reduce the damage award by $1,200, from $69,376.71 to $68,-176.71. 2

Harvesters Group, Inc. (hereinafter Harvesters) entered into a prime contract with the Navy to construct improvements at the United States Navy and Marine Corps Reserve Training Center in Miami, Florida. In accordance with the Miller Act, 40 U.S. C.A. §§ 270a-270d, Harvesters secured a payment bond in the amount of $1,517,600 from Appellant National Union Fire Insurance Co. of Pittsburgh, Pa. (hereinafter National Union). Harvesters then entered into a subcontract with Appellee Pertun *917 Construction Co. (hereinafter Pertun), a concrete forming subcontractor, under which Pertun was to perform concrete work necessary for the federal project. Paragraph 3(f) of the subcontract provided that if the prime contractor delayed the subcontractor’s work, the subcontractor would be granted an extension of time to perform, but that such extension of time would preclude other claims by the subcontractor on account of the delay.

The Navy training center project had lots of problems. Toxic wastes were discovered, the job site lacked running water and electricity, and Harvesters experienced difficulties in finding subcontractors to perform parts of the work, in obtaining necessary permits, and in obtaining timely sub-mittals of documents required by the Navy. As a result of these difficulties, construction was delayed from the outset. After construction commenced, Harvesters’ failure to supervise, schedule, and coordinate the work of the various subcontractors properly caused further delays — delays which increased the labor and equipment rental costs of Pertun. Then, when Per-tun’s concrete work was eighty percent finished, its participation in the project was wrongfully terminated by Harvesters. Pertun was not permitted to return to the job site, either to complete performance or to retrieve its tools and materials.

As Harvesters' surety pursuant to the Miller Act payment bond, Appellant National Union has admitted liability to Appel-lee Pertun for “work in place” — work Per-tun performed, but had not yet been paid for. The parties stipulated this amount to be $34,593: the difference between $226,-605, the value of the labor and materials provided by Pertun to the project, and $192,012, the amount Pertun had already been paid. In the meantime, however, some of Pertun’s unpaid suppliers had themselves filed claims against the bond; National Union thus sought setoffs — for payments made to Pertun’s unpaid suppliers, as well as for payments withheld by the Navy due to defects in Pertun’s work— against the $34,593 admittedly owed Per-tun for work in place. Pertun contested the validity and extent of the claimed set-offs and also asserted the right to an additional award to cover the increased costs it incurred as a result of delay.

After a bench trial, the district court rejected the majority of National Union’s claimed setoffs and granted Pertun’s request for additional damages to cover costs incurred due to delay. The resulting final judgment was for $69,376.71: $25,329.60 for work in place; $900.00 for Pertun’s equipment and materials which Harvesters retained and incorporated into the project; and $43,147.11 for increased costs of labor and equipment rentals caused by the delay. The district court also granted Pertun’s motion for reasonable attorney’s fees and costs. As noted above, this opinion will focus on the portion of damages awarded for increased costs caused by delay.

1. Damages for delay under the Miller Act

The purpose of a Miller Act payment bond is to protect subcontractors and suppliers who provide labor and material for a federal project, because federally owned lands or buildings are exempt from the liens that would normally secure these parties’ rights under state law. United States f/u/b/o Sherman v. Carter, 353 U.S. 210, 216, 77 S.Ct. 793, 797, 1 L.Ed.2d 776 (1957); see 40 U.S.C.A. §§ 270a-270b. To effectuate this congressional intent, the Miller Act is to be liberally construed and applied. F.D. Rich Co., Inc. v. United States f/u/b/o Industrial Lumber Co., Inc., 417 U.S. 116, 124, 94 S.Ct. 2157, 2162, 40 L.Ed.2d 703 (1974). But a liberal construction does not mean that the Miller Act establishes an unlimited basis for recovery; courts have held that the Miller Act surety is not liable for damages caused by the prime contractor’s breach of contract. See, e.g., United States f/u/b/o Edward E. Morgan Co., Inc. v. Maryland Casualty Co., 147 F.2d 423 (5th Cir.1945); L.P. Friedstedt Co. v. U.S. Fireproofing Co., 125 F.2d 1010 (10th Cir.1942) (applying Heard Act, predecessor of Miller Act). Thus, for example, in the present case National Union would not be liable to Pertun for profits lost as the result of Harvester’s *918 premature and wrongful termination of the subcontract. See Arthur N. Olive Co. v. United States f/u/b/o Marino, 297 F.2d 70 (1st Cir.1961). It would be liable, on the other hand, for any “sum or sums justly due” Pertun for labor or material furnished in the performance of its agreement to work on the public project. See 40 U.S. C.A. § 270b(a) (1986).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Hirani Eng'g & Land Surveying, P.C.
345 F. Supp. 3d 11 (D.C. Circuit, 2018)
Paige International, Inc. v. Xl Speciality Insurance Company
267 F. Supp. 3d 205 (District of Columbia, 2017)
United States v. Travelers Casualty & Surety Co. of America
55 F. Supp. 3d 852 (N.D. West Virginia, 2014)
United States Ex Rel. Metric Electric, Inc. v. EnviroServe, Inc.
301 F. Supp. 2d 56 (D. Massachusetts, 2003)
United States Ex Rel. Maris Equipment Co. v. Morganti, Inc.
163 F. Supp. 2d 174 (E.D. New York, 2001)
United States v. Apex Roofing of Tallahassee, Inc.
49 F.3d 1509 (Eleventh Circuit, 1995)
Chapman v. Ei Constructors, Inc., No. Cv 0040938 (Feb. 21, 1995)
1995 Conn. Super. Ct. 1702 (Connecticut Superior Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
918 F.2d 915, 36 Cont. Cas. Fed. 75,979, 1990 U.S. App. LEXIS 20991, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-for-use-and-benefit-of-pertun-construction-company-v-ca11-1990.