Chapman v. Ei Constructors, Inc., No. Cv 0040938 (Feb. 21, 1995)

1995 Conn. Super. Ct. 1702
CourtConnecticut Superior Court
DecidedFebruary 21, 1995
DocketNo. CV 0040938
StatusUnpublished

This text of 1995 Conn. Super. Ct. 1702 (Chapman v. Ei Constructors, Inc., No. Cv 0040938 (Feb. 21, 1995)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chapman v. Ei Constructors, Inc., No. Cv 0040938 (Feb. 21, 1995), 1995 Conn. Super. Ct. 1702 (Colo. Ct. App. 1995).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]MEMORANDUM OF DECISION I.

INTRODUCTION

This action arose out of the construction of the Waterbury Water Treatment Plant for the defendant City of Waterbury (City). The defendant EI Constructors, Inc. CT Page 1703 (EI) was the general contractor, and the plaintiff (BAC) was a subcontractor of EI. The defendant Aetna Insurance Company (Aetna) provided a surety bond.

BAC's suit against EI is based on its claims that EI breached its contractual promise to perform its obligations, and to pay BAC. A default was entered against EI on November 15, 1993 for its failure to appear and defend, thereby making it liable to the plaintiff for whatever damages the plaintiff might prove in its hearing in damages trial, which was part of this trial against the City and Aetna. BAC seeks to recover against Aetna under the bond Aetna posted for labor and materials (including costs, expenses and lost profits) provided on the project.

The plaintiff's claims against the City are that the City converted its equipment and materials, and negligently misrepresented site conditions.

II. BAC v. EI 1. LIABILITY

On January 11, 1983, EI and the City entered into Contract 82-11 for construction of the Waterbury Water Treatment Plant. Pursuant to this contract, EI as principal, and Aetna as surety, posted a bond. On December 30, 1982, the plaintiff contracted with EI to perform certain work under Contract 82-11 for $440,000.

In this lawsuit against EI, Aetna and the City, the plaintiff claims that EI failed to perform its obligations under Contract 82-11 and under the subcontract with the plaintiff. On November 15, 1993, this court defaulted EI for failure to appear and defend the suit. The entry of this default determined the liability issues in the case in favor of the plaintiff and the trial was a hearing in damages with respect to EI. EI did not appear at the trial at all.

The entry of a default constitutes an admission by the defendant of the truth of the facts alleged in the complaint. CT Page 1704

DeBlasio v. Aetna Life and Casualty Co., 186 Conn. 398,400 (1982).

The plaintiff must still prove [at a hearing in damages] how much of the judgment prayed for in the complaint he is entitled to receive.

United National Indemnity Co. v. Zullo, 143 Conn. 124,130 (1956).

2. DAMAGES

a. Count I. — Unmade Progress Payments

EI owes the plaintiff for unmade progress payments as shown in various invoices. The work was done and invoiced in accord with the contract as follows:

1. for period through 7/20/84 — $42,020.93;

2. for period 7/20/84 to 8/24/84 — $38,500.57;

3. for period from 8/25/84 to 9/14/84 — $23,471.08.

In addition to these amounts, the plaintiff is entitled to interest under Section 37-3a of the Conn. Gen. Stat. because the detention of the money was wrongful under the circumstances. These amounts were clearly owed right from the time of the invoices were presented. The court will more fully discuss the law concerning prejudgment interest later in this decision. Since the claims rest on a breach of contract, 10% statutory interest accrues from the date the money became due and payable, which in this count was 7/21/84 on the first invoice; 8/25/84 on the second invoice; and 9/15/84 on the third.

The total amount due the plaintiff is $208,849.11 (includes interest to 9/15/94), plus total per diem interest of $28.49 from 9/15/94 to date of judgment.

b. Count II — Equipment and Standby Costs and Expenses.

EI owes the plaintiff for the rental cost of plaintiff's equipment properly seized by the City under CT Page 1705 the contract, in the amount of $38,601.

EI also owes the plaintiff for the cost of actual standby labor in the amount of $2,871. The total amount owed is $41,472.

The reasons why the plaintiff is entitled to these amounts are more fully discussed in Section III A.2., A. and B. of this Memorandum of Decision, with reference to the plaintiff's similar claims against Aetna, pages 17, 18, 19, and 20.

No interest is awarded in this count because the amount claimed was greatly reduced by the plaintiff just before trial, and therefore not ascertainable until then. Detention of the money was not wrongful under the circumstances.

c. Count III — Impounded Steel.

From 9/15/84 to 3/15/85, the plaintiff lost the use of its steel which was in the cofferdam, and therefore is entitled to the fair rental value as stated in the contract. On 3/15/85, the plaintiff found out that it could not take back its steel, since it was being turned over to EI's successor, so in accord with contract 82-11, the plaintiff liquidated the steel for its full value of $72,410.

EI owes the plaintiff on the invoice of 10/24/84, rental of $18,269.50, on invoice of 11/21/84, rental of $1,559.60. in invoice of 12/14/84, rental of $1,559.60, on the invoice of 1/17/84, rental of $1,559.60, on invoice of 3/8/85, rental of $1,559.60, total rental of $24,507.90, plus the liquidation value of $72,410.

The total amount due the plaintiff is $96,917.90 for rental and liquidation.

No interest is being awarded because substantial legal questions existed, as to how damages should be determined; it is the court's judgment that the demands of justice do not require the imposition of interest; that the detention of the money was not wrongful under the circumstances; and that the money was not "payable". CT Page 1706

d. Count IV — 5% Retainage From Progress Payments.

EI owes the plaintiff the 5% of payments due the plaintiff for retainage under the subcontract. This amount is $10,284.21 plus interest of $10,284.21 from 9/15/84 to 9/15/94, a total of $20,568.42, plus per diem interest of $2.82 from 9/15/94 to date of judgment. Interest is awarded because detention of the money was wrongful, inasmuch as it was clearly owed.

e. Count V — Extra Work for Removal of Pipes fromCofferdam.

This was valid extra work under the subcontract for removal of two pipes placed mistakenly within the bounds of the cofferdam site by EI and another subcontractor. Interest is awarded because of wrongful detention, because these extra costs are clearly allowable under the contract.

EI owes the plaintiff for the cost of removing the 12" pipe, $4,674.00 plus interest of $4,740.59 from 7/25/84 to 9/15/94, a total of $9,414.59, plus per diem of $1.28 from 9/15/94 to date of judgment; and $6,543.00 for removing the 36" pipe, plus interest of $6,508.94 from 10/4/84 to 9/15/94, a total of $13,051.94 plus per diem interest of $1.79 from 9/15/94 to date of judgment, a net total in Count V of $22,466.53 plus per diems.

f. Count VI — Failure to Provide Electricity

Under the terms of the subcontract, EI had to provide the plaintiff with electricity for pumps used to remove water from the cofferdam. They failed to do 80 in July 1984, thereby causing the plaintiff additional costs and expenses. For this, EI owes the plaintiff a corrected invoice in the amount of $2,217.00 plus interest from 7/23/84 to 9/15/94 in the amount of $2,256.72, a total of $4,473.72, plus per diem interest of $.61 from 9/15/94 to date of judgment. Interest is awarded because detention of the money was wrongful. Plaintiff was cleary entitled to this under the contract.

g. Count VII — Lost Margin, Overhead and Related

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Blau v. Lehman
368 U.S. 403 (Supreme Court, 1962)
Southern St. Masonry v. JA Jones Const.
507 So. 2d 198 (Supreme Court of Louisiana, 1987)
Peacock Const. Co., Inc. v. Modern Air Conditioning, Inc.
353 So. 2d 840 (Supreme Court of Florida, 1977)
DeBlasio v. Aetna Life & Casualty Co.
441 A.2d 838 (Supreme Court of Connecticut, 1982)
OBS Co., Inc. v. Pace Const. Corp.
558 So. 2d 404 (Supreme Court of Florida, 1990)
United National Indemnity Co. v. Zullo
120 A.2d 73 (Supreme Court of Connecticut, 1956)
Town of Brookfield v. Greenridge, Inc.
418 A.2d 907 (Supreme Court of Connecticut, 1979)
United Plate Glass Co. v. Metal Trims Industries, Inc.
525 A.2d 468 (Commonwealth Court of Pennsylvania, 1987)
Eastern Heavy Constructors, Inc. v. Fox
188 A.2d 286 (Court of Appeals of Maryland, 1963)
Schuler-Haas Electric Co. v. Aetna Casualty & Surety Co.
357 N.E.2d 1003 (New York Court of Appeals, 1976)
Walter Kidde Constructors, Inc. v. State
434 A.2d 962 (Connecticut Superior Court, 1981)
Star Contracting Corporation v. Manway Construction
337 A.2d 669 (Connecticut Superior Court, 1973)
Power & Pollution Services, Inc. v. Suburban Power Piping Corp.
598 N.E.2d 69 (Ohio Court of Appeals, 1991)
Schuler-Haas Electric Corp. v. Aetna Casualty & Surety Co.
49 A.D.2d 60 (Appellate Division of the Supreme Court of New York, 1975)
Otis Elevator Co. v. George A. Fuller Co.
172 A.D.2d 732 (Appellate Division of the Supreme Court of New York, 1991)
Jeremiah Sullivan & Sons, Inc. v. Kay-Locke, Inc.
459 N.E.2d 837 (Massachusetts Appeals Court, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
1995 Conn. Super. Ct. 1702, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chapman-v-ei-constructors-inc-no-cv-0040938-feb-21-1995-connsuperct-1995.