United States of America for the Use and Benefit of Heller Electric Co., Inc. S. E. B. Masonry, Inc. v. William F. Klingensmith, Inc.

670 F.2d 1227, 29 Cont. Cas. Fed. 82,194, 216 U.S. App. D.C. 408, 1982 U.S. App. LEXIS 22159
Court of Appeals for the D.C. Circuit·Decided February 2, 1982·No. 80-2250·Published·Cited by 26 cases

Opinion

BAZELON, Senior Circuit Judge:

This is a Miller Act 1 action brought in the name of the United States for the use and benefit of SEB Masonry, Inc. (SEB) against William F. Klingensmith, Inc. (Klin-gensmith) and its Sureties, Fireman’s Fund Insurance Co. (Fireman’s Fund) and Hanover Insurance Co. (Hanover). SEB appeals a district court ruling 2 limiting the amount of damages recoverable in a contract dispute with Klingensmith. Klingensmith and SEB were the general contractor and subcontractor, respectively, on two construction projects — the parking garage and the Allied Health Building — at the Van Ness campus of the University of the District of Columbia. 3 Fireman’s Fund was the surety on the parking garage and Hanover was the surety on the Allied Health Building.

I. BACKGROUND

On April 29, 1977 and October 12, 1977, respectively, the United States General Services Administration awarded defendant William F. Klingensmith, Inc. contracts to build the parking garage and the Allied Health Building at the Van Ness campus of the University of the District of Columbia. 4 The expected date of completion for the garage was February 12, 1978. 5 At that point, work was to begin on the -Allied Health Building, which was to be built on top of the parking garage. Klingensmith subcontracted to SEB the masonry work on each building. SEB began work on the parking garage in November 1977 and expected to complete its work within 90 calendar days. 6 As it turned out, SEB did not complete the job until October 1978. 7 Each party blamed the other for delaying completion of the project, and Klingensmith withheld $16,906.53 from the amount it owed SEB. 8

After work on the parking garage was complete, SEB began work on the Allied Health Building. After working for three days in May 1979, SEB left the site and refused to return. In June 1979, Klingen-smith terminated its agreement with SEB and hired Pentek Corp. to do the masonry work for $14,398 more than its contract with SEB provided. 9

II. THE DISTRICT COURT’S DECISION

SEB filed this action against Klingen-smith and its sureties, seeking damages for Klingensmith’s delay on the parking garage, and for lost anticipated profits on the Allied Health Building contract. Klingen-smith counterclaimed against SEB for delaying work on the parking garage and the Allied Health Building, and for breaching its contract for work on the Allied Health *1230 Building. 10 After trial, the district court found that Klingensmith had delayed the completion of the parking garage. Specifically, it found that Klingensmith had failed to coordinate adequately the work of its subcontractors and that it failed to provide sufficient supervisory personnel on the job. The court also found, however, that SEB contributed to the delay and concluded, therefore, that neither party could collect delay damages from the other. In addition, the district court found that SEB was unjustified in failing to complete its work on the Allied Health Building, and that it had, therefore, breached its contract with Klin-gensmith. 11 Accordingly, the district court ruled that SEB owed Klingensmith $14,398 —the difference between the original contract price and Pentek’s contract price. That amount was deducted from the $16,-906.53, which Klingensmith still owed SEB. for work on the garage, and the court entered a judgment against Klingensmith and Fireman’s Fund for $2,508.53. 12

III. ANALYSIS

SEB argues that the district court erred in refusing to award damages for Klingen-smith’s delay, even though SEB may have been partially responsible for the delay. SEB contends that the district court should have determined the extent to which each party was harmed as a result of the other party’s delay, and apportioned the damages accordingly. In addition, SEB urges that the district court erred in ruling that it had breached its contract to do the masonry work on the Allied Health Building. We agree with SEB with respect to delay damages on the parking garage contract, but we agree with the district court’s conclusion that SEB breached the Allied Health Building contract.

A. Damages for Delay

As stated above, the district court found that Klingensmith had violated its contractual obligations by delaying SEB’s work on the parking garage. Klingensmith asserts that the district court’s finding is invalid.as a matter of law because its subcontract with SEB contained no completion date. We disagree. In a construction contract like the subcontract at issue here, the prime contractor implicitly promises to provide such working conditions as may be necessary to allow its subcontractor to carry out its obligations under the contract. Burgess Construction Co. v. M. Morrin & Son Co., Inc., 526 F.2d 108, 113 (10th Cir. 1975); George A. Fuller Co. v. United States, 69 F.Supp. 409 (Ct.Cl.1947). 13 If a contractor interferes with the work of its subcontractor, it has breached its obligation, and the subcontractor is entitled to recover for the resulting delays. George A. Fuller v. United States, supra. We, therefore, affirm this aspect of the district court’s decision.

In addition to finding that Klingensmith had delayed SEB’s work on the parking garage, the district court found that SEB had delayed the completion of both the garage and the Allied Health Building. The court did not, however, evaluate each party’s claim for delay. Instead, it concluded, as a matter of law, that neither party could recover for the other party’s delay. In so doing, the district court erred.

Free access — add to your briefcase to read the full text and ask questions with AI

United States of America for the Use and Benefit of Heller Electric Co., Inc. S. E. B. Masonry, Inc. v. William F. Klingensmith, Inc., 670 F.2d 1227, 29 Cont. Cas. Fed. 82,194, 216 U.S. App. D.C. 408, 1982 U.S. App. LEXIS 22159 (D.C. Cir. 1982).

670 F.2d 1227 (United States of America for the Use and Benefit of Heller Electric Co., Inc. S. E. B. Masonry, Inc. v. William F. Klingensmith, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United States v. Hirani Engineering & Land
58 F.4th 1250 (D.C. Circuit, 2023)
Kelleher v. Dream Catcher, L.L.C.
District of Columbia, 2019
Blakeslee Arpaia Chapman, Inc. v. EI Constructors, Inc.
687 A.2d 506 (Supreme Court of Connecticut, 1997)
Allied Fire & Safety Equipment Co. v. Dick Enterprises, Inc.
886 F. Supp. 491 (E.D. Pennsylvania, 1995)
Chapman v. Ei Constructors, Inc., No. Cv 0040938 (Feb. 21, 1995)
1995 Conn. Super. Ct. 1702 (Connecticut Superior Court, 1995)
Levy v. Autoridad de Edificios Públicos
135 P.R. Dec. 382 (Supreme Court of Puerto Rico, 1994)
Blakeslee Arpaia Chapman v. Ei Constructors, No. 040938 (Oct. 13, 1993)
1993 Conn. Super. Ct. 8276 (Connecticut Superior Court, 1993)
Bat Masonry Co. v. Pike-Paschen Joint Venture III
842 F. Supp. 174 (D. Maryland, 1993)
Mai Steel Service Inc. v. Blake Construction Co.
981 F.2d 414 (Ninth Circuit, 1992)
Williams Enterprises, Inc. v. Strait Manufacturing & Welding, Inc.
728 F. Supp. 12 (District of Columbia, 1990)