United States Ex Rel. Mariana v. Piracci Construction Co.

405 F. Supp. 904, 1975 U.S. Dist. LEXIS 16222
CourtDistrict Court, District of Columbia
DecidedSeptember 12, 1975
DocketCiv. A. 75-0342
StatusPublished
Cited by33 cases

This text of 405 F. Supp. 904 (United States Ex Rel. Mariana v. Piracci Construction Co.) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. Mariana v. Piracci Construction Co., 405 F. Supp. 904, 1975 U.S. Dist. LEXIS 16222 (D.D.C. 1975).

Opinion

MEMORANDUM AND ORDER

GESELL, District Judge.

This is a suit brought under the Miller Act 1 by use plaintiff Mariana, a subcon *905 tractor, against the prime contractor, Piracci, and its surety, Aetna. Aetna has moved for partial summary judgment and the issue presented, which is purely a legal issue at this stage, was fully briefed and argued. The question for decision is whether a Miller Act surety is liable to a subcontractor for the increased costs of performing the subcontracted work where additional costs for labor and material are caused solely by delay in the commencement and completion of the job and the delay is not attributable to the subcontractor.

The federal project here involved concerns construction of the Joseph H. Hirshhorn Museum and Sculpture Garden in Washington, D. C. Piracci obtained the contract on a bid basis and in computing its bid included the amount it had agreed on with use plaintiff for the performance of the subcontract work. The job was then delayed nineteen months primarily through a controversy between the general contractor and the General Services Administration. 2 When the work eventually went forward use plaintiff found it had increased costs caused by the delay, including standby expenses and added outlays for materials and labor required by the job. In particular, five categories of increased actual expenses are claimed in this suit: (1) increased cost of labor due to performance of the work at a period when higher 1 wage rates were in effect; (2) increased cost of materials due to higher prices at the later time; (3) increased labor costs due to inefficient performance stemming from the piecemeal, disjointed method of work caused by the delay; (4) increased cost of field operations due to the longer time of actual job performance resulting from the delay; (5) increased indirect expenses, composed of home office overhead and general and administrative (G&A) expenses.

Aetna takes the position that it is bound on its Miller Act bond 3 only to pay the amount specified in the subcontract for the work, and this amount has already been paid. Aetna argues the increased costs of performing must be met solely by a separate contract action between use plaintiff and the general contractor, and the surety must be relieved of further obligation. Use plaintiff claims to the contrary, stating that the Miller Act by its terms entitles it to be reimbursed by the surety for these added costs. No claim is made for lost or expected profits, only labor and materials and related expenses incurred.

*906 The Miller Act provides:

(a) Every person who has furnished labor or material in the prosecution of the work provided for in such contract, in respect of which a payment bond is furnished under section 270a of this title and who has not been paid in full therefor before the expiration of a period of ninety days after the day on which the last of the labor was done or performed by him or material was furnished or supplied by him for which such claim is made, shall have the right to sue on such payment bond for the amount, or the balance thereof, unpaid at the time of institution of such suit and to prosecute said action to final execution and judgment for the sum or sums justly due him . 40 U.S.C. § 270b(a) (1970).

The purpose of this statute has been explained by the Supreme Court:

Section 270a(a)(2) of the Miller Act establishes the general requirement of a payment bond to protect those who supply labor or materials to a contractor on a federal project. Ordinarily, a supplier of labor or materials on a private construction project can secure a mechanic’s lien against the improved property under state law. But a lien cannot attach to government property ., so suppliers on government projects are deprived of their usual security interest. The Miller Act was intended to provide an alternative remedy to protect the rights of these suppliers. F. D. Rich Co. v. United States for the use of Industrial Lumber Co., Inc., 417 U.S. 116, 121-22, 94 S.Ct. 2157, 2161, 40 L.Ed.2d 703 (1974).

Although enacted as a replacement for state lien law, the Miller Act provides a federal cause of. action, and the scope and substance of recovery are governed by federal rather than state law. F. D, Rich, supra, 417 U.S. at 126-31, 94 S.Ct. 2157. “The Miller Act is ‘. . . highly remedial [and] entitled to a liberal construction and application in order properly to effectuate the Congressional intent to protect those whose labor and materials go into public projects.’ MacEvoy, supra [Clifford F. MacEvoy Co. v. United States ex rel. Tomkins Co.], 322 U.S. [102] at 107, 64 S.Ct. [890] at 893 [88 L.Ed. 1163 (1944)].” F. D. Rich, supra, 417 U.S. at 124, 94 S.Ct. at 2162. Under the statute, use plaintiff is entitled to the “sum or sums justly due him.” 4 By its terms, however, the Miller Act is limited to claims for “labor or material [furnished] in the prosecution of the work provided for in [the] contract ..” The issue thus becomes whether delay costs as alleged in this case are expenses for “labor or material” within the intendment of the statute. The Court holds that the Miller Act surety is liable to a subcontractor for increased costs actually incurred due to delay for labor or material, to the extent such delay is not attributable to the subcontractor.

Several reasons support this conclusion. First, the claims asserted in this case are within the literal language of the statute, since the amounts sought are for out-of-pocket expenses for labor or materials that were furnished and used by the subcontractor in performing his contractual obligations. 5 Recovery in the instant circumstances would also promote the underlying purpose of the Miller Act: to afford the subcontractor the financial protection of an action against the surety. To deny relief would remit the use plaintiff to his remedy for breach of contract, and it was the inadequacy of such a remedy in the context of federal construction projects that prompted the enactment of the Miller *907 Act. Moreover, there is a public interest in the smooth completion of these Government projects which is promoted by reducing the possibility that delay will frustrate the governmental objective due to disputes between the prime and its subs.

Moreover, the Miller Act, like the mechanic’s lien for which it substitutes, is premised on “the equity in favor of those whose actual expenditure of work or utilization of material has enhanced the value of the property in question,” Arthur N. Olive Co. v. United States ex rel. Marino, 297 F.2d 70

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Hirani Engineering & Land
58 F.4th 1250 (D.C. Circuit, 2023)
Window Specialists, Inc. v. Forney Enterprises, Inc.
106 F. Supp. 3d 64 (District of Columbia, 2015)
United States Ex Rel. Milestone Tarant, LLC v. Federal Insurance
672 F. Supp. 2d 92 (District of Columbia, 2009)
Mai Steel Service Inc. v. Blake Construction Co.
981 F.2d 414 (Ninth Circuit, 1992)
US FOR USE OF SUPERIOR INSULATION v. McKee, Inc.
702 F. Supp. 1298 (N.D. Texas, 1988)
W.S.A. Inc. v. Stratton
680 F. Supp. 375 (S.D. Florida, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
405 F. Supp. 904, 1975 U.S. Dist. LEXIS 16222, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-mariana-v-piracci-construction-co-dcd-1975.