District of Columbia Ex Rel. Strittmatter Metro, LLC v. Fidelity & Deposit Co. of Maryland

208 F. Supp. 3d 178, 2016 U.S. Dist. LEXIS 127556
CourtDistrict Court, District of Columbia
DecidedSeptember 20, 2016
DocketCivil Action No. 2015-2114
StatusPublished

This text of 208 F. Supp. 3d 178 (District of Columbia Ex Rel. Strittmatter Metro, LLC v. Fidelity & Deposit Co. of Maryland) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
District of Columbia Ex Rel. Strittmatter Metro, LLC v. Fidelity & Deposit Co. of Maryland, 208 F. Supp. 3d 178, 2016 U.S. Dist. LEXIS 127556 (D.D.C. 2016).

Opinion

MEMORANDUM OPINION and ORDER

COLLEEN KOLLAR-KOTELLY, United States District Judge

In this case brought under the District of Columbia’s Little Miller Act (“DCLMA”), D.C. Code § 2-201.02 et seq., Plaintiff Strittmatter Metro, LLC (“Stritt-matter”) seeks to collect against the payment bond guaranteed by Defendants Fidelity and Deposit Company of Maryland (“Fidelity”) and Zurich American Insurance Company (“Zurich”) for the labor, materials, and/or equipment that Stritt-. matter furnished as a subcontractor on a construction project owned by the District of Columbia at Ballou Senior High School. Compl. ¶¶ 5-9. Before the Court is Defendants’ [6] Motion to Dismiss or, in the Alternative, Stay Proceeding. Defendants contend that Plaintiff must first exhaust the dispute resolution procedure set out in the primary contract between the District and the prime contractor, Chiaramonte-Hess, a Joint Venture (“CHJV”) before it may seek recourse under the DCLMA. Strittmatter has opposed the motion, but Defendants have not filed a reply. Upon consideration of the pleadings, 1 the relevant legal authorities, and the record as a whole, the Court DENIES Defendants’ [6] Motion to Dismiss or, in the alternative, to Stay Proceedings.

I. BACKGROUND

A. The District of Columbia’s Little Miller Act

A brief review of the operation and purpose of the DCLMA is instructive at the outset in framing the analysis of Defendants’ instant motion. Although the DCLMA itself has been the subject of little judicial interpretation, because it is a statute very closely modeled on the Federal Miller Act, 40 U.S.C. § 3131, it is appropriate to look to the persuasive authority of those cases interpreting its federal counterpart. See Castro v. Fidelity & Deposit Co. of Md., 39 F.Supp.3d 1, 4-5 (D.D.C. 2014) (noting the paucity of judicial analysis of the DCLMA and looking to the persuasive authority of the Federal Miller Act); Hartford Accident & Indem. Co. v. District of Columbia, 441 A.2d 969, 972 (D.C. 1982) (adopting the interpretation of the Federal Miller Act by this District in United States ex rel. Mariana v. Piracci Constr. Co., Inc., 405 F.Supp. 904 (D.D.C. 1975), in finding the DCLMA to allow a subcontractor to recover “delay *181 damages”). See also Campbell v. Cumbari Assocs., Inc., No. 3817-84, 1987 WL 114846, at *2 (D.D.C. July 6, 1987) (“Because the District and Federal provisions are virtually in haec verba, the Court may look to cases decided under the federal law for guidance in interpreting the local statute”).

The DCLMA, like the Federal Miller Act, seeks to address the precarious position in which subcontractors on government projects find themselves. See, e.g., Castro, 39 F.Supp.3d at 5. In contrast to subcontractors on a private construction project, the subcontractor on a government project is generally unable to protect itself from losses occasioned by default by the prime contractor by placing a lien on the property. Id. The DCLMA seeks to fill this gap, providing protection for subcontractors such as Strittmatter by requiring the prime contractor to secure a payment bond, upon which the subcontractor may recover in the event of default by the prime contractor. Id. (reviewing the history and purpose of the Federal Miller Act and the DCLMA). See also F. D. Rich Co. v. United States ex rel. Indus. Lumber Co., 417 U.S. 116, 122, 94 S.Ct. 2157, 40 L.Ed.2d 703 (1974) (explaining that in the absence of the traditional protection of a lien upon which subcontractors on government projects can rely, “[t]he Miller Act was intended to provide an alternative remedy to protect the rights of these suppliers”); Hartford Accident, 441 A.2d at 972 (rejecting a more limited application of the DCLMA and finding its provisions to extend to delay damages based on the guiding principle that the DCLMA’s payment bond “was designed to protect subcontractors supplying labor and materials to a government project”).

Like the Federal Miller Act, the DCLMA was fashioned with the particular purpose of providing aggrieved subcontractors with a mechanism for promptly recovering compensation. See United States v. Zurich Am. Ins. Co., 99 F.Supp.3d 543, 548 (E.D. Pa. 2015). Indeed, the Federal Miller Act was promulgated as a revision of the Heard Act and shortened the period between the completion of work by the subcontractor and accrual of the cause of action from six months to 90 days. It was Congress’ intent in making this revision to remedy the “resultant hardships” to the subcontractor who, under the Heard Act, could be required to wait years following the completion of its work before he could recover the full payment due. Id. (quoting United States v. Daniel, Urbahn, Seelye & Fuller, 357 F.Supp. 853, 859 (N.D. Ill. 1973)). Similarly, under the DCLMA, for a first-tier subcontractor such as Strittmatter (that is, a contractor who has contracted directly with the prime contractor), a cause of action accrues under the DCLMA 90 days following the completion of work or delivery of materials, allowing it to seek recovery from the payment bond secured by the prime contractor with no additional procedural requirements imposed by the statute. D.C. Code § 2-201.02(a). The subcontractor must bring this action within the one year of the final day of its work or delivery of materials on the government project. D.C. Code § 2-201.02(b). This clear Congressional objective of providing a speedy remedy for an aggrieved subcontractor must be borne in mind when interpreting the interplay between the Miller Act (and the District’s Little Miller Act) and any dispute resolution procedures set out in the prime contract. United States ex rel. Straightline Corp. v. American Cas. Co. of Reading, Pa., No. 5:06-00011, 2007 WL 2050323, at *3 (N.D.W. Ya. 2007) (“The Act ‘should receive a liberal construction to effectuate its protective purposes.’ ” (quoting United States ex rel. *182 Sherman v. Carter, 353 U.S. 210, 216, 77 S.O. 793, 1 L.Ed.2d 776 (1957))).

B. Factual Background

The District of Columbia entered into a contract with CHJV as the general or prime contractor for construction work on Ballou Senior High School. Compl. ¶ 5.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Landis v. North American Co.
299 U.S. 248 (Supreme Court, 1936)
United States Ex Rel. Sherman v. Carter Constr. Co.
353 U.S. 210 (Supreme Court, 1957)
Clinton v. Jones
520 U.S. 681 (Supreme Court, 1997)
Air Line Pilots Ass'n v. Miller
523 U.S. 866 (Supreme Court, 1998)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
United States Ex Rel. Mariana v. Piracci Construction Co.
405 F. Supp. 904 (District of Columbia, 1975)
Hartford Accident & Indemnity Co. v. District of Columbia
441 A.2d 969 (District of Columbia Court of Appeals, 1982)
Ward v. D.C. Department of Youth Rehabilitation Services
768 F. Supp. 2d 117 (District of Columbia, 2011)
Lopez Castro v. Fidelity and Deposit Company of Maryland
39 F. Supp. 3d 1 (District of Columbia, 2014)
United States v. Zurich American Insurance
99 F. Supp. 3d 543 (E.D. Pennsylvania, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
208 F. Supp. 3d 178, 2016 U.S. Dist. LEXIS 127556, Counsel Stack Legal Research, https://law.counselstack.com/opinion/district-of-columbia-ex-rel-strittmatter-metro-llc-v-fidelity-deposit-dcd-2016.